2360249
CONDITIONALClare - Clare County Council
Proposed Development
a solar farm on a site of 70 hectares consisting of the following: 309,008 sq. m. of solar photovoltaic panels on ground mounted steel frames; a 38 kV electrical substation with electrical control building and associated compound with palisade fence; the installation of 21 electrical skids within 7 no. electrical compounds (with acoustic barrier fencing); underground power and communication cables and ducts, including underground cabling along the L3056 public road; new and upgraded internal access tracks (including stream crossings as required); 3 no. upgraded site entrances to the public road (one entrance to L-3054 (Lackyle Heights), and 2 no. entrances to L-30541); boundary fencing (including 607m of acoustic barrier fencing on the eastern boundary); landscaping and biodiversity enhancement measures; and all associated ancillary development, site works and services. The solar farm will be operational for 40 years. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development and will be submitted to the planning authority with the application.
View the full application file on the council's planning portal →Application Timeline
Application received
13 Jul 2023
Decision due
6 Sept 2023
Decision: CONDITIONAL
6 Sept 2023
Grant issued
10 Oct 2023
Application Details
- Location
- Land to the west/north-west of Ardnacrusha within the townlands of Castlebank Drummin , Glenlon North Glenlon South and Ballykeelaun , Co Clare
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Clare County Council
- Site Area
- 70 ha
Timeline
- Registration Date
- 13 July 2023
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 6 September 2023
- Grant Date
- 10 October 2023
- Permission Expires
- 9 October 2028
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
to apply for a 10-year planning permission for development at land to the west/north west of Ardnacrusha within the townlands of Castlebank, Glenlon North, Glenlon South, Drummin and Ballykeelaun, for the development of a solar farm on a site of approximately 70 hectares consisting of the following; up to 309,008 sq.m of solar photovoltaic panels on ground mounted steel frames; a 38 kV electrical substation with electrical control building and associated compound with palisade fence; the installation of up to 21 no. inverter/transformer stations on 7 no. hardstanding locations; underground power and communication cables and ducts, including underground cabling along the L3056 public road; new and upgraded internal access tracks (including stream crossings as required); 3 no. upgraded site entrances to the public road (one entrance to L-3054 (Lackyle Heights), and 2 no. entrances to L-30541); boundary fencing; landscaping and biodiversity enhancement measures; and all associated ancillary development, site works and services. The solar farm will be operational for 40 years. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development and will be submitted to the planning authority with the application
Castlebank Glenlon North Glenlon South , Drummin and Ballykeelaun , Co Clare
the construction of a dwelling house, new vehicular splayed entrance and piers, new wastewater treatment & percolation system, demolition of existing shed and all associated site works. Note :- An Appropriate Assessment Screening and Natura Impact Statement Report is included with the proposed development.
Roo West , Ardnacrusha , Co. Clare
to construct a dwelling house, garage, bored well, waste water treatment system, percolation area, entrance and all associated site works
Glenlon North , Ardnacrusha , Co Clare
to construct dwelling house, garage, bored well, waste water treatment system, percolation area, entrance and all associated site works
Glenlon North , Ardnacrusha , Co Clare
to construct a dwelling house, garage, bored well, waste water treatment system, percolation area, entrance and all associated site works
Glenlon North , Ardnacrusha , Co Clare
for the construction of a detached dwelling house, detached shed, new vehicular entrance and piers in existing splayed wall, connection to existing waste water treatment system and all ancillary site works
Roo West , Ardnacrusha , Co. Clare
for the construction of a dwelling house, new vehicular splayed entrance and piers, new wastewater treatment & percolation system, demolition of existing shed and all associated site works
Roo West , Ardnacrusha , Co. Clare
to RETAIN changes to original house plans submitted for grant of planning permission P8/10268, and for detached shed and all associated site development works
Roo West , Ardnacrusha , Co Clare
Amendments to part of the design of an approved solar farm development (Clare County Council Planning Reg. Ref. P23/60249). The proposed amendments comprise the erection of eight new pole sets and two new masts and replacement of two existing pole sets with two new masts; Placement of overhead lines (comprising 688m) to enable connection to the national grid; Placement of underground cables (comprising 91m) to enable connection from the overhead lines to the approved substation; Alterations to the design, layout and scale of the approved substation; Removal of solar panels (comprising 668sqm) adjacent to the substation; Removal of underground cable route (comprising 1,457m) and associated works for the cable route from the substation to the national grid at Ardnacrusha; and all other associated works
Land to the west/north-west of Ardnacrusha , within the townlands of Castlebank , and Glenlon South.
for the construction of a dwelling house, detached garage, new vehicular splayed entrance and piers, new wastewater treatment and percolation system, and all associated site works
Roo West , Ardnacrusha , Co. Clare
Planning a project of your own?