2460147

CONDITIONAL

Limerick - Limerick County Council

Proposed Development

the replacement of an existing telecommunications support structure with a new 24m metre multi-user lattice type telecommunications support structure carrying antenna and dishes together with associated ground equipment cabinets, extended compound and palisade fencing and associated site works located within the grounds

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    22 Feb 2024

  2. Decision: CONDITIONAL

    11 Apr 2024

  3. Decision due

    17 Apr 2024

  4. Grant issued

    14 May 2024

Application Details

Location
Gore Transport , Clondrinagh Industrial Estate , Ennis Road Co. Limerick.
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Limerick County Council
Site Area
0.001 ha

Timeline

Registration Date
22 February 2024
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
11 April 2024
Grant Date
14 May 2024
Permission Expires
13 May 2029

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

151m
19690N/A12 Jul 2019

the appropriate treatment and recycling or reclamation of metals and metal compounds from end of life vehicles subject to a waste facility permit

Clondrinagh Industrial Estate , Clondrinagh , Co. Limerick.

181m
258296N/A6 Oct 2025

(a) The construction of a two bed extension and all ancillary site development works at No. 5 Clondrinagh Park, and (b) The construction of a new dwelling, connection to existing waste-water treatment system and all associated ancillary site development works

Clondrinagh Park , Ennis Road , Limerick.

186m
19697CONDITIONAL16 Jul 2019

storage bays to be used for the short term temporary storage of different types of non-hazardous excavated materials, until viable 20 tonne loads can be assembled for transport off site to suitably licensed waste disposal/recovery facilities

Clondrinagh Industrial Estate , Clondrinagh , Co. Limerick.

215m
2460263CONDITIONAL27 Mar 2024

of a change of use from retail use (12sq.m) to retail with ancillary off Licence use

Applegreen Service Station Retail Building , Clondrinagh Roundabout , Clondrinagh

250m
17420CONDITIONAL11 May 2017

the development will consist of: (a) the demolition of all existing structures, (b) the construction of a single storey service station building of 253 sqm gross floor space incorporating a convenience shop that will consist of 100 sqm net retail area and 50sqm deli which includes food preparation space (no frying), seating, storage, office, toilets, bin storage and delivery yard to the rear. The service station forecourt will comprise a canopy with an illuminated fascia and 6 no. fuel pump islands, electric car charging points, car servicing area, a car wash facility and 2 no. 40,000 litre and 1 no. 60,000 litre underground fuel storage tanks with associated pipework and overground fill points, (c) the construction of a two storey restaurant building of 517 sqm gross floor space with drive thru facility, ground floor seating, ground floor seating, children's play area, food preparation space, refrigeration, storage and toilet areas, and first floor staff room, office, storage and toilet areas, (d) parking to comprise a total of 46 no. car parking spaces, 2 no. coach/HGV parking spaces and bicycle stands, (e) and ESB substation, associated signage throughout the site, attenuation tank and interceptors, connection to the foul sewer, new access slip-lane into site from Ennis Road (R445) and upgrade of existing site access/egress arrangement off Clondrinagh Industrial Estate Road, all associated site boundary treatments, landscaping and site development works

Clondrinagh Roundabout , Clondrinagh , Co Limerick

266m
2560165CONDITIONAL3 Mar 2025

a high-power electric vehicle charging hub & associated infrastructure, consisting of the following: i) installation of 4no. electric vehicle bays, (ZEVI compliant) & 4no. charging points (powered by 100% renewable energy), (ii) new modular ESB substation & (iii) landscape renewal

Applegreen Clondrinagh Service Area , Clondrinagh Roundabout , Co. Limerick

354m
22408CONDITIONAL11 Apr 2022

the construction of an enclosed hard-cored area for the storage of site accommodation cabins including 2.4m high perimeter V-Mesh fencing

Westlink Business Park , Clondrinagh , Limerick

360m
18962CONDITIONAL2 Oct 2018

the construction of a single storey car showroom and for 2 no. external car display areas with covered canopies, car parking, site lighting, building signage, 1 no. totem sign, connect to existing wastewater network, all with associated site development works

Clondrinagh , Limerick.

361m
2660098N/A3 Feb 2026

revised ground levels of an enclosed hardcored area

Westlink Business Park , Clondrinagh , Limerick

408m
221209CONDITIONAL15 Nov 2022

(a) completion of the existing shell and core building that was previously granted under PI.Reg. 072395, (b) change of use from retail warehousing to a gymnasium with all associated services, (c) construction of a new partial mezzanine floor at first floor level to serve as a part of the gymnasium with all associated services, (d) minor elevational changes to the existing building inclusive of proposed signage, (e) extension of the existing access road and construction of a new car parking area to the front of proposed entrance(s), (f) proposed relocation of Plant Room, (g) connection to all existing services already terminated within the building and all associated site works

Warehouse Unit no.5 Coonagh Cross Shopping Centre , Clondrinagh , Ennis Road

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?