2460225
CONDITIONALSligo - Sligo County Council
Proposed Development
to carry out repair and renovation work to a protected structure (RPS No. 4) as follows; 1) Demolition of existing rear non original extension. 2) New windows to be added to the rear wall on the ground floor and first floor. 3) Replace existing pvc windows with timber sash windows to replicate original design. 4) Maintenance and repairs to existing fabric and finishes. 5) Internal works to existing structure. 6) Widen existing entrance at the north-east boundary to accommodate parking. 7) Create a new entrance for off-street parking. 8) All ancillary site works
View the full application file on the council's planning portal →Application Timeline
Application received
28 Jun 2024
Further information requested
19 Aug 2024
Further information received
11 Oct 2024
Decision: CONDITIONAL
5 Nov 2024
Decision due
7 Nov 2024
Grant issued
6 Dec 2024
Application Details
- Location
- Inver View , Adervoher TD , Easkey Co. Sligo
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Sligo County Council
- Site Area
- 0.163 ha
Timeline
- Registration Date
- 28 June 2024
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 5 November 2024
- Grant Date
- 6 December 2024
- Permission Expires
- 5 December 2029
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
PP - for development consisting of erection of a two storey house with domestic garage. Connection to public mains sewer and all associated site works.
Bunowna TD , Easkey , Co. Sligo
development consisting of the construction of a new single storey extension together with works to the existing school at Colaiste Iascaigh (formerly Easkey Vocational School). (Part of the existing school contain a Protected Structure; Sligo Record of Protected Structures 2011-2017 Register No. 87 and National Inventory of Architectural Heritage Reg. No: 32306013). The works shall include the construction of new school accommodation of 312 sqm floor area to include generally; 2 no. classrooms, science lab and prep area, sanitary accommodation and new boiler house. Works to the existing school shall include: the demolition of existing external gas service enclosure; reconfiguration and refurbishment of the existing science lab building. The new building and all works are to be connected to all existing public utilities together with all associated site development works
Colaiste Iascaigh , Bunowna , Easkey
development consisting of (1) Repair/replace roof, fascias, gutters and downpipes, (2) Repair render to external façade where required, (3) Repair/replace windows and doors, (4) Repair/replace floorboards and joists, (5) Retain/repair existing features including fireplaces, internal doors, skirtings, and coving where possible, (6) Retain and repair timber stairs, (7) Repair boundary walls and gates. All the above to be carried out in accordance with the Conservation report and recommendations submitted with this application, (8) Demolish existing boiler house to the rear, (9) Construct a single storey extension to the rear (12.4 m2), (10) All associated site works. The building is Number 88 on the Sligo County Council Record of Protected Structures.
Bridge House , Bunowna , Easkey Co. Sligo.
Development consisting of the installation of 116 sq.metres of temporary prefabricated accommodation together with all associated site works and connection to existing services and utilities. The accommodation includes 2 no. single storey classrooms each with floor area of 58 sqm. Part of the existing school contains a protected structure; Sligo record of protected structures 2017-2023 register no. 87 and national inventory of architectural heritage register no. 32306013.
Colaiste Iascaigh , Bunowna Td , Easkey
(1) construction of new entrance, boundary wall and car parking area; (2) construction of an all-weather pitch with associated fencing, ball stop netting and running/cycling track; (3) construction of playground and walking track; (4) construction of a changing facility; (5) connection to existing services and (6) carrying out of ancillary site works including passive lighting and landscaping
Aderavoher , Easkey , Co. Sligo
for development consisting of the construction of a dwelling house, domestic garage and connect to public utilities, together with all associated site works
Bunowna Td , Easky , Co. Sligo
We, Easkey Community Council CLG, intend to apply to Sligo County Council for Planning Permission for: The construction of an extension to the side of the existing community centre to accommodate a sauna area and to carry out all ancillary site works at Easkey Community Centre, Curraghnagap TD, Easkey, Co. Sligo.
Easkey Community Centre , Curraghnagap , Easky Co. Sligo
Development consisting of installation of a single storey prefabricated container unit (30m2) for storage of local artisan products
Easkey Community Grounds , Easkey , Co Sligo
for development consisting of 1) Install a single-storey prefabricated container unit (25m2) to facilitate the process of herbs for distribution, 2) Retain two no. single-storey prefabricated container units with area 16m2 and 12m2, subject of planning applications PL 08/420 & PL08/473 respectively, in use as storage ancillary to the community centre, 3) All ancillary site works involved
Easkey Community Council Property , Curraghnagap Td. , Easkey
for development consisting of a single-storey community enterprise unit (50m2) for storage, display and sales of local artisan products at
Easkey Community Grounds , Easkey , Co. Sligo
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?