2460316
CONDITIONALDonegal - Donegal County Council
Proposed Development
ALTERATIONS TO PREVIOUSLY GRANTED PLANNING APPLICATION REF. NO. 20/51161 CONSISTING OF (1) INCREASED FLOOR AREA TO FIRST FLOOR, (2) ALTERATIONS TO THE ROOF, (3) CHANGE OF USE FROM 7 ENSUITE BEDROOMS TO 3 NO. ONE BED APARTMENTS AND 1 NO. TWO BED APARTMENT AND (4) ALL ASSOCIATED SITE DEVELOPMENT WORKS
View the full application file on the council's planning portal →Application Timeline
Application received
12 Mar 2024
Further information requested
25 Apr 2024
Further information received
20 May 2024
Decision: CONDITIONAL
12 Jun 2024
Decision due
16 Jun 2024
Grant issued
17 Jul 2024
Application Details
- Location
- CABRY , QUIGLEY'S POINT , CO DONEGAL
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 0.5 ha
Timeline
- Registration Date
- 12 March 2024
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 12 June 2024
- Grant Date
- 17 July 2024
- Permission Expires
- 15 December 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
RENOVATION AND EXTENSION WORKS TO EXISTING ENGINEERING BUILDING AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
CABRY , QUIGLEYS POINT , LIFFORD PO
RENOVATION AND EXTENSION WORKS TO EXISTING ENGINEERING BUILDING AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
CABRY , QUIGLEY'S POINT , LIFFORD PO
(1) CONSTRUCTION OF ADDITIONAL TOILETS TO PUBLIC BAR AREA AND NEW KITCHEN, DINING AREA AND RECEPTION AREA ALL ON THE GROUND FLOOR (2) RENOVATION OF EXISTING BEDROOMS TO INCORPORATE EN-SUITE BATHROOMS AND PROVISION OF 2NO ADDITIONAL EN-SUITE BEDROOMS AND LOUNGE AREA ON FIRST FLOOR (3) CONSTRUCTION OF AN EXTENSION TO BASEMENT CELLAR (4) ERECTION OF NEW RAISED ROOF TO EXISTING BUILDING TO REPLACE DILAPATED EXISTING ROOF AND (5) CONSTRUCTION OF NEW CAR PARK WITH ACCESS VIA EXISTING ENTRANCE WITH CONNECTION TO EXISTING SEPTIC AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
CABRY , QUIGLEY'S POINT , LIFFORD PO
(1) ALTERATIONS TO PREVIOUSLY GRANTED PLANNING APPLICATION 20/51161, (2) INCREASED FLOOR AREA TO FIRST FLOOR, (3) ALTERATIONS TO THE ROOF, (4) CHANGE OF USE FROM 7 EN-SUITE BEDROOMS TO 3 NO. ONE BED APARTMENTS AND 1 NO. 2 BED APARTMENT AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
CABRY , QUIGLEY'S POINT , LIFFORD
(1) CONSTRUCTION OF ADDITIONAL TOILETS TO PUBLIC BAR AREA AND NEW KITCHEN, DINING AREA AND RECEPTION AREA ALL ON THE GROUND FLOOR (2) RENOVATION OF EXISTING BEDROOMS TO INCORPORATE EN-SUITE BATHROOMS AND PROVISION OF 2NO ADDITIONAL EN-SUITE BEDROOMS AND LOUNGE AREA ON FIRST FLOOR (3) CONSTRUCTION OF AN EXTENSION TO BASEMENT CELLAR (4) ERECTION OF NEW RAISED ROOF TO EXISTING BUILDING TO REPLACE DILAPATED EXISTING ROOF AND (5) CONSTRUCTION OF NEW CAR PARK WITH ACCESS VIA EXISTING ENTRANCE WITH CONNECTION TO EXISTING SEPTIC AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
CABRY , QUIGLEY'S POINT , LIFFORD PO
CONSTRUCTION OF A DWELLING HOUSE WITH CONNECTION TO PROPOSED SEPTIC TANK AND SOIL POLISHING FILTER
CABRY , QUIGLEYS POINT , CO. DONEGAL
EXTENSION TO SENIOR CITZIENS ROOM ON GROUND FLOOR AND EXTENSION TO MAIN MEETING ROOM ON FIRST FLOOR AND TOILETS AND STORAGE AREAS AS PER DRAWINGS AND PERMISSION FOR CONSTRUCTION OF AN EXTENSION AND ALL ANCILLARY WORKS TO FRONT OF BUILDING KNOWN LOCALLY AS QUIGLEYS POINT COMMUNITY CENTRE TO FACILITATE PLAYSCHOOL ACCOMMODATION AND CHANGE OF INTERNAL USE FROM A SENIOR CITIZENS ACCOMMODATION TO A PLAYSCHOOL ACCOMMODATION
CABRY , QUIGLEYS POINT , CO DONEGAL
EXTENSION TO (1) SENIOR CITIZENS ROOM ON THE GROUND FLOOR (2) MAIN MEETING ROOM ON THE FIRST FLOOR (3) TOILETS AND STORAGE AREAS AND PERMISSION FOR (1) CONSTRUCTION OF AN EXTENSION AND ALL ANCILLARY WORKS TO THE FRONT OF THE BUILDING KNOWN LOCALLY AS QUIGLEYS POINT COMMUNITY CENTRE TO FACILITATE PLAYSCHOOL ACCOMMODATION (2) CHANGE OF INTERNAL USE FROM SENIOR CITIZENS ACCOMMODATION TO PLAYSCHOOL ACCOMMODATION
CABRY , QUIGLEYS POINT , CO. DONEGAL
EXTENSION TO SENIOR CITZIENS ROOM ON GROUND FLOOR AND EXTENSION TO MAIN MEETING ROOM ON FIRST FLOOR AND TOILETS AND STORAGE AREAS AS PER DRAWINGS AND PERMISSION FOR CONSTRUCTION OF AN EXTENSION AND ALL ANCILLARY WORKS TO FRONT OF BUILDING KNOWN LOCALLY AS QUIGLEYS POINT COMMUNITY CENTRE TO FACILITATE PLAYSCHOOL ACCOMMODATION AND CHANGE OF INTERNAL USE FROM A SENIOR CITIZENS ACCOMODATION TO A PLAYSCHOOL ACCOMODATION IF NEEDED AS AN ALTERNATIVE
CABRY , QUIGLEYS POINT , CO DONEGAL
CHANGE OF USE OF PART OF THE PREMISES KNOWN LOCALLY AS QUIGLEYS POINT COMMUNITY CENTRE, PLANNING REF: 20/51523 TO FACILITATE A FULL DAY CARE AND AFTER SCHOOL CARE TO CATER FOR AGES 0 TO 15
CABRY , QUIGLEYS POINT , LIFFORD PO
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?