Hilltop Farm Matthewstown , Fenor Tramore , Co. Waterford
CONDITIONALPlanning application 2460405
Waterford - Waterford City and County Council
Proposed Development
construct new Staff Facilities for existing Staff on Fenor Pig Farm, consisting of Reception, Office, Store, Canteen and Changing Rooms (Approx. 13m x 16m x 5m high) and all ancillary and associated Site works.
View the full application file on the council's planning portal →Application Timeline
Application received
17 Jul 2024
Further information requested
5 Sept 2024
Further information received
17 Feb 2025
Decision due
12 Apr 2025
Decision: CONDITIONAL
12 Apr 2025
Grant issued
21 May 2025
Application Details
- Location
- Hilltop Farm Matthewstown , Fenor Tramore , Co. Waterford
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Waterford City and County Council
- Site Area
- 38.2 ha
Timeline
- Registration Date
- 17 July 2024
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 12 April 2025
- Grant Date
- 21 May 2025
- Permission Expires
- 20 May 2030
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Solar energy development to erect 292.32 kWp of photovoltaic panels on ground mounted steel frames with associated cabling and ducting to service existing building with all associated site works. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413)
Matthewstown , Fenor Tramore , Co. Waterford
on a site of approximately 18.75 hectares. The proposed development will consist of the expansion, upgrade and modernisation of an existing EPA licensed pig rearing installation (Licence Ref. P0410-01) as follows: • Construction of 1 no. single-storey pig fattening house (Building 511, maximum height c. 4.5m above ground level) with a gross floor area of approximately 3,763sqm (approximately 106m in length × 35.5m in width overall, including covered walkway), including associated feed storage silos, accommodating approximately 3,698 production pigs; • Provision of roof structures to existing whey storage tanks (Area 802) with a maximum height of approximately 5.93m to 8.99m above ground level; • Decommissioning of the existing open slurry lagoon (Structure 955), including emptying and removal of the existing concrete structure, reinstatement of suitable excavated material on site and removal of any contaminated material, and the construction of 2 no. covered overground slurry storage tanks, comprising: o 1 no. tank (Structure 951) with a capacity of approximately 5,236 cu.m and an overall height of approximately 7.3m above ground level; and o 1 no. tank (Structure 963) with a capacity of approximately 1,428cu.m³and an overall height of approximately 6.0m above ground level; • Provision of 1 no. single-storey dry store building with a floor area of approximately 531sqm and an overall height of approximately 9.83m above ground level; • Provision of a truck wash and wheel wash facility, including associated drainage infrastructure, silt trap and hydrocarbon interceptor; • Installation of slurry handling infrastructure serving the proposed pig fattening house (Building 511), including automatic scraper systems, channels, pumps, sumps and abstraction points; • Implementation of emission control measures, including the upgrade and conversion of Buildings 503–510 from natural to mechanical ventilation and modifications to ventilation infrastructure, including an increase in stack height at Building 204; • Installation of 3 no. new monitoring boreholes and 1 no. new on-site groundwater abstraction (production) well; • Provision of ancillary infrastructure including covered whey storage tanks, a designated carcass storage and collection area incorporating sealed and covered bio secure storage, upgrades to internal roadways and improvements to site drainage infrastructure, including connection to the existing integrated constructed wetland and all associated site
Fenor Pig Farm , Matthewstown , Fenor County Waterford (within the townland of Matthewstown)
development at Fenor Pig Farm, Matthewstown, Fenor, County Waterford(within the townland of Matthewstown), on a site of approximately 18.75 hectares. The proposed development will consist of the expansion, upgrade and modernisation of an existing EPA licensed pig rearing installation (Licence Ref. P0410-01) as follows: • Construction of 1 no. single-storey pig fattening house (Building 511, maximum height c. 4.5m above ground level) with a gross floor area of approximately 3,763sqm (approximately 106m in length × 35.5m in width overall, including covered walkway), including associated feed storage silos, accommodating approximately 3,698 production pigs; • Provision of roof structures to existing whey storage tanks (Area 802) with a maximum height of approximately 5.93m to 8.99m above ground level; • Decommissioning of the existing open slurry lagoon (Structure 955), including emptying and removal of the existing concrete structure, reinstatement of suitable excavated material on site and removal of any contaminated material, and the construction of 2 no. covered overground slurry storage tanks, comprising: o 1 no. tank (Structure 951) with a capacity of approximately 5,236m³ and an overall height of approximately 7.3m above ground level; and o 1 no. tank (Structure 963) with a capacity of approximately 1,428m³and an overall height of approximately 6.0m above ground level; • Provision of 1 no. single-storey dry store building with a floor area of approximately 531sqm and an overall height of approximately 9.83m above ground level; • Provision of a truck wash and wheel wash facility, including associated drainage infrastructure, silt trap and hydrocarbon interceptor; • Installation of slurry handling infrastructure serving the proposed pig fattening house (Building 511), including automatic scraper systems, channels, pumps, sumps and abstraction points; • Implementation of emission control measures, including the upgrade and conversion of Buildings 503–510 from natural to mechanical ventilation and modifications to ventilation infrastructure, including an increase in stack height at Building 204; • Installation of 3 no. new monitoring boreholes and 1 no. new on-site groundwater abstraction (production) well; • Provision of ancillary infrastructure including covered whey storage tanks, a designated carcass storage and collection area incorporating sealed andand covered bio-secure storage, upgrades to internal roadways and yard areas
Fenor Pig Farm , Matthewstown , Fenor County Waterford (within the townland of Matthewstown)
to replace, upgrade and extend the existing feed milling building, to incorporate roof over existing feed silos and associated site works including a concrete yard and bunded area for existing liquid feed tanks. The site of the proposed development is on an IPPC Licensed facility Ref. No. P0410-01
Matthewson , Fenor , Co. Waterford
construction of a single storey dwelling, detached garage, new entrance, new bored well, septic tank and percolation area and all associated site works
Ballydermody , Fenor , Co. Waterford
permission for changes to an existing dwelling house to include the conversion of attic space to living accommodation, the provision of new dormer and velux windows and changes to the ground floor layout resulting in minor changes to the facades of the existing dwelling house at
Ballydermody , Fenor , Co Waterford
for retention permission for changes to an existing dwelling house to include the construction of a side extension, the conversion of an attached garage space to living accommodation, the conversion of attic space to living accommodation and changes to the front façade of the dwelling house at
Ballydermody , Fenor , Co Waterford
indefinite retention of raised timber deck with stone facing to front of house
Ballydermody , Dunhill , Co. Waterford
indefinite retention of raised timber deck with stone facing to front of house
Ballydermody , Dunhill , Co. Waterford
change of use from storage area to 2 bedrooms and bathroom at first floor and altering 2 first floor gable windows to provide fire escape at residence
Ballydermody , Dunhill , Co. Waterford
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?