2460473
CONDITIONALWestmeath - Westmeath County Council
Proposed Development
construction of a new Warehouse / Garage Unit and associated office space (1,054 sqm total) for the servicing / maintenance of vehicles, primarily trucks and vans. The proposed development will include all earthworks, drainage infrastructure and attenuation, landscaping, security fencing / boundary treatment, car parking spaces, truck parking spaces, bicycle parking spaces, and all other associated site development works above and below ground level. The proposed development will include all associated site development works with connections to existing services previously permitted and constructed
View the full application file on the council's planning portal →Application Timeline
Application received
12 Dec 2024
Further information requested
13 Feb 2025
Further information received
27 Mar 2025
Decision: CONDITIONAL
8 Apr 2025
Decision due
23 Apr 2025
Grant issued
12 May 2025
Application Details
- Location
- Athlone Business Park Kilmacuagh (Castlemaine) TD. , and Bunnahinly TD. , Athlone
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Westmeath County Council
- Site Area
- 1.818 ha
Timeline
- Registration Date
- 12 December 2024
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 8 April 2025
- Grant Date
- 12 May 2025
- Permission Expires
- 11 May 2030
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Erection of one internally illuminated wall sign and two non-illuminated wall signs to replace existing
Athlone Business Park , Dublin Road , Bunnahily
development will principally consist of the reversion of the premises (2,116 sq m) from its current use as a distribution hub to the previously permitted use as a builders’ merchants; removal of the existing mezzanine (182 sq m), and provision of two new mezzanine areas (670 sq m and 133 sq m); internal modifications; elevational changes including the provision of a roller shutter door on the east elevation and 3 No. fire escape doors on the east, west and south elevations; a canopy structure attached to the south elevation; new signage including elevational signage and an illuminated freestanding sign (3 m in height); provision of a security hut (5.3 sq m); the omission of 1 No. car parking space to facilitate cycle parking; the minor repositioning of car parking spaces; HGV loading bays; external storage; hard and soft landscaping; and all associated site and development works above and below ground. The gross floor area of the building will increase from 2,116 sq m to 2,737 sq m, and the maximum building height of 10.265 m will remain unchanged
A site of 1.26 Ha at Athlone Business Park , Dublin Road Athlone , Co. Westmeath
The development will consist of the installation of 2 No. HVO fuel above ground storage tanks (a 80,000 litre and a 50,000 litre tank), the relocation of an existing 12,000 litre HVO fuel above ground storage tank and an existing 1,000 litre Ad Blue above ground storage tank, the installation of 2no. fuel pumps and all ancillary site works
Athlone Business Park , Dublin Road , Kilmacuagh (Castlemaine)
erect 1256.36 sq m of photovoltaic panels on the roof of the existing building in our factory, trading as DPD HQ Ireland, with all associated site works
Athlone Business Park , Dublin Road , Athlone
development which will consist of : The Construction of a Temporary Car parking Facility for 195 cars complete with new entrance off existing road network, new fencing, gates, public lighting, landscaping and all associated site works
Athlone Business Park , Kilmacuagh Bunahinley , Dublin Road Athlone
development which will consist of amendments and extension to the existing car park (c. 2,517sqm) to provide segregated parking for 13 no. HGV's a dedicated pedestrian route and all associated site development works
The Mail Centre , Athlone Business Park , Kilmacuagh Athlone
development consisting of proposals to retain the existing use of Willow Park Community House as a community centre and construct new single-storey extensions to either end of the existing building; Construct a new canopy along the length of the building; Alter the existing building and carry out associated site works. The site works will comprise new fencing, drainage, hard & soft landscaping, relocation of existing sheds and works to widen the existing site entrance. The proposed works will be carried out in two phases. Phase 1 will comprise an extension to Room no.1, alterations to the existing building, a new canopy and associated site works. Phase 2 will comprise an extension to Room no.2, associated canopy, relocation of existing sheds and associated site works
133 Meadowbrook , Willow Park , Athlone
To construct a single storey extension onto the side of my existing dwelling and associated site works
137 Meadowbrook , Willow Park , Athlone
new two storey , two bedroom residential contemporary mews dwelling on an infill site, together with a new site entrance from Meadowbrook and connections to the existing site services
134 Meadowbrook , Willow Park , Athlone
construction of a ground floor extension to the rear of their existing house. The extension will include a new bedroom and disabled accessed bathroom. The application will also include and all other minor site-works and drainage
148 Meadowbrook , Athlone , Co. Westmeath
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?