2460476
CONDITIONALDonegal - Donegal County Council
Proposed Development
CONSTRUCTION OF A DWELLING HOUSE, DETACHED DOMESTIC GARAGE, SEPTIC TANK/SEWAGE TREATMENT SYSTEM AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
View the full application file on the council's planning portal →Application Timeline
Application received
8 Apr 2024
Further information requested
23 May 2024
Further information received
19 Aug 2024
Decision: CONDITIONAL
5 Sept 2024
Decision due
15 Sept 2024
Grant issued
9 Oct 2024
Application Details
- Location
- WOODLANDS , RAPHOE , LIFFORD
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 0.415 ha
- Floor Area
- 209.16 sq m
- Residential Units
- 1
Timeline
- Registration Date
- 8 April 2024
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 5 September 2024
- Grant Date
- 9 October 2024
- Permission Expires
- 8 October 2029
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
(1) DEMOLITION OF EXISTING AGRICULTURAL STORAGE SHED AND ERECTION OF A REPLACEMENT SLATTED COW SHED WITH UNDERGROUND EFFLUENT STORAGE TANKS (2) DEMOLITION OF EXISTING OPEN SIDE ROUND BALE STORAGE SHED AND CONSTRUCTION OF A NEW DRY BED CALVING SHED AND ALL ASSOCIATED SITE WORKS
WOODLANDS , RAPHOE , LIFFORD PO
DRY BEDDED SHED AND PERMISSION FOR CONSTRUCTION OF AN AGRICULTURAL SLATTED SHED WITH UNDERGROUND TANK AND ASSOCIATED SITE DEVELOPMENT WORKS
LETTERGULL , RAPHOE , LIFFORD PO
ERECTION OF A MILKING PARLOUR, A SLATTED SHED, A SILAGE PIT, A FEEDING SILO, A DRY SHED AND COMPLETION OF A ROOF OVER THE EXISTING SILAGE PIT WITH CONNECTION TO EXISTING SERVICES INCLUDING A PROPOSED ACO QUADRACEPTOR SURFACE WATER RUN-OFF FILTRATION SYSTEM
CARRICKADAWSON , RAPHOE , LIFFORD PO
ERECTION OF 12 HORSE STABLES WITH ALL ANCILLARY AREAS, A STORAGE AREA, AN OUTDOOR ARENA, A PADDOCK AND A DRY SHED WITH CONNECTION TO EXISTING SERVICES INCLUDING A PROPOSED ACO QUADRACEPTOR SURFACE WATER RUN-OFF FILTRATION SYSTEM
CARRICKADAWSON , RAPHOE , LIFFORD PO
(1) CHANGE OF CONDITION NO. 2 OF PLANNING REF. NO. 22/51106 TO PERMIT BUSINESS USE AND (2) APPROVAL OF A CAR-PARKING AREA WITHIN THE SITE BOUNDARY FOR THE VISITING PUBLIC AND ALL OTHER ASSOCIATED SITE WORKS
CARRICKADAWSON , RAPHOE , LIFFORD PO
(1) USE OF THE DEVELOPMENT PERMITTED UNDER PLANNING REF. NO. 22/51106 FOR AN EQUINE BUSINESS FOR HORSE RIDING LESSONS / EQUESTRIAN FACILITY, (2) CAR-PARKING AREA WITHIN THE SITE BOUNDARY FOR THE VISITING PUBLIC AND (3) INSTALLATION OF A SEPTIC TANK AND PERCOLATION AREA AND ALL OTHER ASSOCIATED SITE WORKS
CARRICKADAWSON , RAPHOE , CO. DONEGAL
RENOVATION AND CONSTRUCTION OF EXTENSION TO EXISTING DERELICT COTTAGE WITH ALL ASSOCIATED WORKS AND CONNECTION TO PROPOSED SEPTIC TANK AND PERCOLATION AREA
CARRICKADAWSON , RAHPOE , LIFFORD PO
A TEN YEAR PLANNING PERMISSION FOR A WIND FARM WITH A 30 YEAR OPERATIONAL LIFE (FROM THE DATE OF COMMISSIONING OF THE ENTIRE WIND FARM) AND ALL ASSOCIATED WORKS. THE PROPOSED DEVELOPMENT WILL CONSIST OF THE FOLLOWING: UP TO 6 NO. WIND TURBINES WITH AN OVERALL BLADE TIP HEIGHT OF UP 135 METRES AND ALL ASSOCIATED FOUNDATIONS AND HARD-STANDING AREAS, 1 NO. BORROW PIT, 1 NO. PERMANENT ANEMOMETRY MAST UP TO A HEIGHT OF 100 METRES, UPGRADE OF EXISTING AND PROVISION OF NEW SITE ACCESS ROADS AND ASSOCIATED DRAINAGE, 1 NO. ELECTRICAL SUBSTATION COMPOUND, WHICH WILL HAVE 1 NO. CONTROL BUILDING, ASSOCIATED ELECTRICAL PLANT AND EQUIPMENT, AND A WASTE WATER HOLDING TANK. 1 NO. TEMPORARY CONSTRUCTION COMPOUND, ALL ASSOCIATED UNDERGROUND ELECTRICAL AND COMMUNICATIONS CABLING CONNECTING THE TURBINES TO THE PROPOSED ON-SITE SUBSTATION, AS WELL AS ON-SITE UNDERGROUND CABLING TO FACILITATE ELECTRICAL CONNECTION TO THE NATIONAL GRID, AND ALL ASSOCIATED SITE DEVELOPMENT WORKS, INCLUDING AMENITY TRAILS ON WIND FARM ROADS, CAR PARKING, SEATING/BENCHES AND SIGNAGE. AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) AND A NATURA IMPACT STATEMENT (NIS) HAVE BEEN PREPARED IN RESPECT OF THE PROPOSED DEVELOPMENT
MOMEEN & LETTERGULL , CO. DONEGAL
DEVELOPMENT ON LANDS WITHIN AND ADJOINING THE PERMITTED LETTERGULL WIND FARM (PLANNING REF. NO. 18/50156, ACP REF. 304685-19) WHICH WILL COMPRISE OF THE PROVISION OF A RENEWABLE ENERGY DEVELOPMENT CONSISTING OF THE FOLLOWING: (1) 1 NO. WIND TURBINE WITH AN OVERALL BLADE TIP HEIGHT OF 135M, ROTOR DIAMETER OF 115M, AND A HUB HEIGHT OF 77.5M, (2) TURBINE FOUNDATION AND ASSOCIATED HARD-STANDING AREAS, (3) TEMPORARY WORKS TO THE EXISTING LETTERGULL WIND FARM SITE ACCESS (AS PERMITTED UNDER PLANNING REF. NO. 18/50156, ACP REF. 304685-19) TO FACILITATE THE CONSTRUCTION OF THE PROPOSED WIND TURBINE CONSISTING OF THE REMOVAL AND REINSTATEMENT OF FENCING AND LANDSCAPING AND TEMPORARY WIDENING OF THE SITE ACCESS JUNCTION, (4) PROVISION OF NEW SITE ACCESS TRACK CONNECTING THE PROPOSED WIND TURBINE TO THE EXISTING INTERNAL LETTERGULL WIND FARM SITE ACCESS TRACKS (AS PERMITTED UNDER PLANNING REF. NO. 18/50156, ACP REF. 304685-19), (5) TEMPORARY CONSTRUCTION COMPOUND AND TEMPORARY LAYDOWN AREA, (6) ASSOCIATED UNDERGROUND ELECTRICAL AND COMMUNICATIONS CABLING CONNECTING THE PROPOSED WIND TURBINE TO THE PERMITTED ON-SITE 38KV SUBSTATION (AS PERMITTED UNDER PLANNING REF. NO. 18/50156, ACP REF. 304685-19), (7) SITE DRAINAGE, (8) ACCESS GATES, FENCING AND SIGNAGE AND (9) ALL RELATED SITE WORKS ABOVE AND BELOW GROUND AND ALL ANCILLARY DEVELOPMENT. FOLLOWING A THIRTY-YEAR OPERATIONAL LIFE FROM THE DATE OF FULL COMMISSIONING OF THE WIND TURBINE THE PROPOSED WIND TURBINE AND ASSOCIATED UNDERGROUND ELECTRICAL AND COMMUNICATIONS CABLING WILL BE DECOMMISSIONED. THE DEVELOPMENT WILL BE ACCESSED VIA THE EXISTING LETTERGULL WIND FARM SITE ENTRANCE ON THE R236 REGIONAL ROAD AND EXISTING INTERNAL LETTERGULL WIND FARM SITE ACCESS TRACKS (AS PERMITTED UNDER PLANNING REF. NO. 18/50156, ACP REF. 304685-19). AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) AND NATURA IMPACT STATEMENT (NIS) ACCOMPANY THIS APPLICATION. THE EIAR AND NIS ASSESS THE FULL EXTENT OF THE PROPOSED DEVELOPMENT AS DESCRIBED IN (1) – (9) ABOVE AS WELL AS THE TEMPORARY ACCOMMODATION WORKS TO FACILITATE THE DELIVERY OF TURBINE COMPONENTS FROM THE PORT OF KILLYBEGS TO THE EXISTING SITE ENTRANCE VIA THE NATIONAL (N56, N15 AND N14) REGIONAL (R263 AND R236) PUBLIC ROAD NETWORK IN COUNTY DONEGAL. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
MOMEEN & LETTERGULL , LIFFORD PO , CO. DONEGAL
(1) CONSTRUCTION OF AN EXTENSION TO THE SIDE ELEVATION AND PROVISION FOR A PITCHED ROOF OVER EXISTING REAR EXTENSION INCORPORATING MINOR ELEVATIONAL AMENDMENTS (2) DEVELOPMENT OF A ROOF DORMER TO FRONT ELEVATION AND CONVERSION OF EXISTING ATTIC SPACE INTO HABITABLE AREA INCORPORATING ROOFLIGHTS AND (3) DEVELOPMENT OF A NEW PERCOLATION AREA CONNECTED INTO EXISTING SEPTIC TANK SYSTEM AND ASSOCIATED SITE DEVELOPMENT WORKS
MOMEEN , ST. JOHNSTON , LIFFORD P.O.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?