2460787
CONDITIONALKildare - Kildare County Council
Proposed Development
for a Data Centre and will comprise of: The demolition of 3 no. dwelling houses, associated garages and farm outbuildings / agricultural buildings (total floor area 1,591m2); The construction of 6 no. two storey data centre buildings, each with loading bays, external plant area including electrical and mechanical plant rooms, fuel compound, sprinkler tanks and associated ancillary development; Data centre building Nos. 1, 2, 3, 4 and 6 will consist of: a data hall (24,756m2, overall height 19m), an administration block (2,505m2 overall height 15m) and include an external screened plant area of 18m in height and 6,164m2; Gas turbines, gas engine and battery energy storage systems will be provided within each plant area; Data centre building No. 5 will consist of: a data hall (24,756m2, overall height 19m), an administration block (2,505m2 overall height 15m) and include an external screened plant area of 18m in height and 6,375m2 in area and includes infrastructure for district heating; Gas turbines, gas engine and battery energy storage systems will be provided within the plant area; Adjacent to each data centre building will be a screened sprinkler tank compound (408m2 to 528 m2 in area) comprising of 3 no. above ground sprinkler pump containers, (1 no. 240m3 and 2 no. 268.8m3 containers) and a screened fuel compound (331m2 in area) comprising 1 no. 38m3 fuel pump container and 6 no. 64m3 tanks; and Solar panels with a total area of 3,600m2 will be provided on the roof of each data centre building and rainwater harvesting is included in the development. The proposed development of the Data Centre also comprises: A screened Gas Networks Ireland (GNI) compound (61m2 in area) with 1 no. kiosk (3m in height and 19.5m2 in area) with a biomethane gas injection point; A screened above Ground Installation (AGI) compound (1,753m2 in area) with 4 no. kiosks each of 3m in height and 51.5 m2 in area; A district heating building (5m in height and 341m2 in area) district heating plant and in ground piping for district heating system; Security hub building (4.1m in height and 42m2 in area) at main entrance to the proposed development; A single storey admin workshop/office (504m2 in area) and water treatment plant (315m2 in area) building (4.8m in height) and associated hydrant pump room (5m in height and 80m2 in area) and 2 no. hydrant pump room storage tanks (5m in height and c.251m3 in area); A new access/egress from the R409 and a new emergency access/egress from th
View the full application file on the council's planning portal →Application Timeline
Application received
13 Aug 2024
Further information requested
4 Oct 2024
Further information received
26 Jun 2025
Decision due
20 Aug 2025
Decision: CONDITIONAL
20 Aug 2025
Appeal submitted
16 Sept 2025
Application Details
- Location
- Townlands of Halverstown , Jigginstown and Newhall , Naas
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kildare County Council
- Site Area
- 37.51 ha
Timeline
- Registration Date
- 13 August 2024
- Status
- APPEALED
- Decision
- CONDITIONAL
- Decision Date
- 20 August 2025
An Coimisiún Pleanála Appeal
- Appeal Reference
- 323677-25
- Submitted
- 16 September 2025
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for a Data Centre and will comprise of: The demolition of 3 no. dwelling houses, associated garages and farm outbuildings / agricultural buildings (total floor area 1,591m2); The construction of 6 no. two storey data centre buildings, each with loading bays, external plant area including electrical and mechanical plant rooms, fuel compound, sprinkler tanks and associated ancillary development; Data centre building Nos. 1, 2, 3, 4 and 6 will consist of: a data hall (24,756m2, overall height 19m), an administration block (2,505m2 overall height 15m) and include an external screened plant area of 18m in height and 6,164m2; Gas turbines, gas engine and battery energy storage systems will be provided within each plant area; Data centre building No. 5 will consist of: a data hall (24,756m2, overall height 19m), an administration block (2,505m2 overall height 15m) and include an external screened plant area of 18m in height and 6,375m2 in area and includes infrastructure for district heating; Gas turbines, gas engine and battery energy storage systems will be provided within the plant area; Adjacent to each data centre building will be a screened sprinkler tank compound (408m2 to 528 m2 in area) comprising of 3 no. above ground sprinkler pump containers, (1 no. 240m3 and 2 no. 268.8m3 containers) and a screened fuel compound (331m2 in area) comprising 1 no. 38m3 fuel pump container and 6 no. 64m3 tanks; and Solar panels with a total area of 3,600m2 will be provided on the roof of each data centre building and rainwater harvesting is included in the development. The proposed development of the Data Centre also comprises: A screened Gas Networks Ireland (GNI) compound (61m2 in area) with 1 no. kiosk (3m in height and 19.5m2 in area) with a biomethane gas injection point; A screened above Ground Installation (AGI) compound (1,753m2 in area) with 4 no. kiosks each of 3m in height and 51.5 m2 in area; A district heating building (5m in height and 341m2 in area) district heating plant and in ground piping for district heating system; Security hub building (4.1m in height and 42m2 in area) at main entrance to the proposed development; A single storey admin workshop/office (504m2 in area) and water treatment plant (315m2 in area) building (4.8m in height) and associated hydrant pump room (5m in height and 80m2 in area) and 2 no. hydrant pump room storage tanks (5m in height and c.251m3 in area); A new access/egress from the R409 and a new emergency access/egress from th
Townlands of Halverstown Jigginstown and Newhall , Naas , County Kildare.
the construction of 266sqm extension, with a ground floor of 206sqm and a mezzanine of 60sqm, connection to existing services and all associated site works to the side of our existing industrial unit at M7 Business Park. The structure will be constructed in a three bay portal framed, metal cladding to match the existing unit
Unit Q2 Nugent Manufacturing , M7 Business Park , Newhall
an existing 25 metre high telecommunications support structure together with associated ground equipment cabinets within a fenced compound
M7 Business Park , Newhall (Ed Ladytown) Td. , Naas
Erection of a 3m high fence around perimeter of the site, 2 no. vehicular entrance gates and 1 no. pedestrian entrance, along with all associated site works. Note. A concurrent application is being sought for a regional depot on the site to be contained by the new fencing and gates
Site 16 Osberstown Business Park , Caragh Road , Naas
a regional depot building (2,057 sqm gfa). This building will contain a 4-bay machine repair area with three-storey machine parts storage (max. c. 16m high), along with two-storey administration area. It is also proposed to provide an ancillary building (c. 10.79m high) containing storage and internal wash bay (302 sqm gfa); a permanent tower crane (c. 14m high), external wash bay; underground storage tanks; car parking; cycle parking; landscaping; 2 No. free-standing signs and all associated site works. Note: a concurrent application is being sought for perimeter fence around the site, 2 No. vehicular entrance gates and 1 No. pedestrian entrance,
Site 16 Osberstown Business Park , Caragh Road , Naas
for the construction of a 2.4m high paladin fence on the south west & north west boundary of the site & all ancillary site works
BNL Science Ltd , Unit S M7 Business Park , Newhall Naas
retention permission is sought for a 106sqm first floor mezzanine storage area within an existing industrial unit and all associated site works
Unit J6 M7 Business Park , Newhall , Naas
Extension of Duration of planning ref. 07/1034 (as per planning ref no. 99/2266)construction of a terrace of 3 no. industrial units with mezzanine floor located in one building 2 no. new vehicular and pedestrian accesses from South and West delivery area located to the East of proposed building and 52 no. parking spaces to facilitate the development. The total gross floor area of proposed development is 2196.55m2 (including mezzanine floor) and is divided into 3 no. units equal in size. The height of the building to ridge is 6.95m. All together with landscaping, boundary treatment and site development works
No 1 Osberstown Business Park , Osberstown , Naas
proposed expansion of their existing 'Waste Processing and Transfer Facility' located at Unit M1, Osberstown Industrial Park, Osberstown, Naas, Co. Kildare, W91 FXP7. The proposed development will consist of 1) an increase in waste throughput at the facility from 21,000 to 49,500 tonnes per annum, 2) alterations to existing site layout to include the construction of an additional two waste processing buildings with approximate gross floor areas of 1,571m2 and 1,821m2, 3) relocation of an existing shed, originally approved planning permission under planning reference 13/581 to an alternate location within the yard, 4) expansion of existing storage yard, 5) stormwater attenuation unit and associated drainage and treatment infrastructure, 6) construction of additional staff welfare facilities, 7) provision of car and lorry parking areas, 8) provision of yard lighting, including lighting poles, 9) site boundary walls and 10) all ancillary site development works. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application. The proposed facility will require a review of the existing 'Waste Facility Permit' which shall be sought through a separate application to Kildare County Council. Revised by significant further information consisting of; a revised Environmental Impact Assessment Report (EIAR), a revised Natura Impact Statement (NIS) and revised plans
Unit M1 , Osberstown Industrial Park , Osberstown Naas
The development consists of retention permission for a change of use of 194m2 existing warehouse to light industrial with ancillary offices; retention permission for 83m2 of light industrial at first floor and planning permission for the use of 439m2 first floor mezzanine for light industrial and ancillary offices; and retention for existing sign 8m2 to front elevation and 8m2 of additional signage to the front of the building together with associated site works
Unit TM7 Business Park , Newhall , Naas