2560129
CONDITIONALOffaly - Offaly County Council
Proposed Development
an Operations Building with a floor area of approximately 285m2. The Operations Building will consist of: - 1 No. Kitchen/Mess - 1 No. Locker Room including welfare facilities - 1 No. Accessible Toilet - 1 No. Toilet - 3 No. Offices - 1 No. Workshop/Store - 2 No. Server/IT store - 1 No. Meeting room - 1 No. External compound - 6 No. Permanent storage containers - Roof mounted solar panels - Connection to existing water, storm water and sewage infrastructure at Rhode Green Energy Park - Temporary cabins to be used during the construction phase - External parking, EV charging, lighting, CCTV, fencing etc. and ancillary site works
View the full application file on the council's planning portal →Application Timeline
Application received
17 Apr 2025
Further information requested
10 Jun 2025
Further information received
6 Aug 2025
Decision due
2 Sept 2025
Decision: CONDITIONAL
2 Sept 2025
Grant issued
8 Oct 2025
Application Details
- Location
- Coolcor , Rhode , Co. Offaly
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Offaly County Council
- Site Area
- 0.243 ha
Timeline
- Registration Date
- 17 April 2025
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 2 September 2025
- Grant Date
- 8 October 2025
- Permission Expires
- 7 October 2030
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
an Operations Building with a floor area of approximately 285m2. The Operations Building will consist of: - 1 No. Kitchen/Mess - 1 No. Locker Room including welfare facilities - 1 No. Accessible Toilet - 1 No. Toilet - 3 No. Offices - 1 No. Workshop/Store - 2 No. Server/IT store - 1 No. Meeting room - 1 No. External compound - 6 No. Permanent storage containers - Roof mounted solar panels - Connection to existing water, storm water and sewage infrastructure at Rhode Green Energy Park - Temporary cabins to be used during the construction phase - External parking, EV charging, lighting, CCTV, fencing etc. and ancillary site works.
Coolcor , Rhode , Co. Offaly
(i) one new super capacitor container, (ii) two new two-storey modular DC containers, (iii) one new control room container, (iv) one new transformer and concrete bund, (v) one new IPP module, (vi) one new ESB MV substation module, (vii) one new PCS module, (viii) internal site access roads and connection to Rhode Green Energy Park road network, (ix) all civil engineering and electrical engineering work, including temporary construction compound, surface water and foul water drainage, landscaping, lighting and security fencing
Coolcor , Rhode , County Offaly
provision of research and development equipment. The proposed development includes the following: (i) one new super capacitor container, (ii) two new two-storey modular DC containers, (iii) one new control room container, (iv) one new transformer and concrete bund, (v) one new IPP module, (vi) one new ESB MV substation module, (vii) one new PCS module, (viii) internal site access roads and connection to Rhode Green Energy Park road network, (ix) all civil engineering and electrical engineering work, including temporary construction compound, surface water and foul water drainage, landscaping, lighting and security fencing
Coolcor , Rhode , County Offaly
(i) two new capacitor containers each measuring 13.7m x 2.7m x 2.9m placed on an existing concrete slabs, (ii) one new inverter container measuring 5.9m x 2.35m x 2.37m placed on an existing concrete slab, (iii) access to the site is from the L-10093-2 which connects the R400 regional road, (v) all civil engineering and electrical engineering works to provide for connection to the electricity distribution network on site via the existing medium voltage substation within the site.
Coolcor , Rhode , County Offaly
(i) two new capacitor containers each measuring 13.7m x 2.7m x 2.9m placed on existing concrete slabs, (ii) one new inverter container measuring 5.9m x 2.35m x 2.37m placed on an existing concrete slab, (iii) access to the site is from the L-10093-2 which connects the R400 regional road, (v) all civil engineering and electrical engineering works to provide for connection to the electricity distribution network on site via the existing medium voltage substation within the site.
Coolcor , Rhode , County Offaly
DEVELOPMENT OF AN ENERGY STORAGE FACILITY DESIGNED TO PROVIDE 20MW OF SYSTEM SUPPORT SERVICES TO THE ELECTRICITY GRID ON A 0.95 HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (I) AN OPEN AREA BATTERY ENERGY STORAGE SYSTEM (BESS) COMPOUND (AREA OF 563 SQM) CONTAINING 8 NO. BATTERY AND CONTROL SYSTEM ENCLOSURES (C. 12.2M LONG X 2.5M WIDE X 4M HIGH), (II) SINGLE STOREY SWITCHGEAR BUILDING (C. 18M LONG X 15M WIDE X 3M HIGH) CONTAINING ELECTRICIAL PLANT AND CONTROL ROOM, (III) BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT VIA OVERHEAD CABLE TO THE EXISTING 110KV DERRYIRON SUBSTATION LOCATED ON LANDS ADJOINING THE SITE TO THE SOUTH, AND (IV) ALL ANCILLARY DEVELOPMENT, INCLUDING; PERIMIETER PALISADE FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUISINESS PARK PROVIDING ACCESS TO THE R400, LANDSCAPING, LIGHTING, CAR PARKING, INTERNAL ACCESS ROADS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER
COOLCOR , RHODE , CO. OFFALY
a ten-year permission for construction of a new site entrance and access track to serve the already consented development refs; PL2/16/246 & 19/194.
Clonin , Co. Offaly , Ireland
a ten-year permission for construction of a new site entrance and access track to serve the already consented development refs; PL2/16/246 & 19/194
Clonin Rhode , Co. Offaly , Ireland
A TEN- YEAR LIFECYCLE FOR CONSTRUCTION OF A NEW SITE ENTRANCE AND ACCESS TRACK TO SERVE THE ALREADY CONSENTED DEVELOPMENT REFS; PL2/16/246 & 19/194
CLONIN , CO. OFFALY
AN ENERGY STORAGE FACILITY DESIGNED TO PROVIDE SYSTEM SUPPORT SERVICES TO THE ELECTRICITY GRID ON A 2.7-HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (i) AN OPEN AREA BATTERY ENERGY STORAGE SYSTEM (BESS) COMPOUND (AREA OF 3,407 SQM) CONTAINING 16 NO. BATTERY ENCLOSURES (13.716M LONG X 2.90M WIDE X 3.796M HIGH), 16 NO. MEDIUM VOLTAGE POWER STATION (MVPS) ENCLOSURES (12.192M LONG X 2.438M WIDE X 3.396M HIGH), (ii) SYNCHRONOUS CONDENSER COMPOUND (AREA OF 4,706SQM) CONTAINING SYNCHRONOUS CONDENSER BUILDING (30.0M LONG X 18.0M WIDE X 12.15M HIGH), CONTROLS BUILDING (12.486M LONG 12.192M WIDE X 4.865M HIGH), ASSOCIATED BUNDED TRANSFORMERS AND ELECTRICAL PLANT, (iii) ELECTRICAL SUBSTATION (AREA OF 2,325SQM) CONTAINING CUSTOMER BUILDING (10.032M LONG X 7.627M WIDE X 6.169M HIGH), EIRGRID BUILDING (13.507M LONG X 12.509M WIDE X 7.577M HIGH), AND ELECTRICAL PLANT AND BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT TO THE EXISITING DERRYION 110KV SUBSTATION LOCATED ON LANDS ADJOINING THE SITE TO THE SOUTH , (iv) CONTROL BUILDING (17.075M LONG X 5.830M WIDE X 5.960M HIGH), AND (v) ALL ANCILLARY DEVELOPMENT, INCLUDING; LIGHTING MAST PROTECTION, PERIMETER PALISADE FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUSINESS PARK PROVIDING ACCESS TO THE R400, LANDSCAPING, LIGHTING,CAR PARKING, INTERNAL ACCESS ROADS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER. A NATURA IMPACT STATEMENT (NIS) HAS BEEN PREPARED AND ACCOMPANIES THIS PLANNING APPLICATION
COOLCOR AND CLONIN , RHODE , CO. OFFALY