The Register of Planning Applications · Éire

Monday 31 August 2026

← Back to search

2560520

REFUSED

Clare - Clare County Council

Proposed Development

for the development of Illaunbaun Wind Farm in the townlands of Tooreen, Slievenalicka, Illaunbaun, Drumbaun & Lackamore (although no infrastructure will be sited within Lackamore townland), County Clare. The development will consist of: • Construction of 5 wind turbines with a maximum overall blade tip height of 150 m. • Construction of associated turbine foundations, crane pad hardstand and assembly areas. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbines to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction & operation of the wind farm. • Two borrow pits. • Three peat repository areas for peat & spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent & Temporary tree felling to accommodate the construction & operation. • Signages and • All associated site development works. This application is seeking 10-year planning permission, along with a 35-year operational life for the wind farm from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes x No The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) & Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the planning authority with the application.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    27 Aug 2025

  2. Decision due

    4 Dec 2025

  3. Decision: REFUSED

    4 Dec 2025

  4. Appeal submitted

    9 Jan 2026

Application Details

Location
Tooreen , Slievenalicka Illaunbaun , Drumbaun and Lackamore Co Clare
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Clare County Council
Site Area
37.6 ha

Timeline

Registration Date
27 August 2025
Status
APPEALED
Decision
REFUSED
Decision Date
4 December 2025

An Coimisiún Pleanála Appeal

Appeal Reference
PL-500605-CE-26
Submitted
9 January 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

309m
2660207REFUSED31 Mar 2026

for the development of the Slievenalicka wind turbine in the townlands of Tooreen, Slievenalicka, Drumbaun & Lackamore (although no infrastructure will be sited within Lackamore townland), County Clare. The development will consist of: • Construction of 1 wind turbine with a maximum overall blade tip height of 150m. • Construction of associated turbine foundations, crane pad hardstand and assembly areas. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbines to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction & operation of the wind farm. • Two borrow pits. • One peat repository area for peat & spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent & Temporary tree felling to accommodate the construction & operation. • Signages and • All associated site development works. This application is seeking 10-year planning permission, along with a 35-year operational life for the wind farm from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413). The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) has been prepared in respect of the planning application and will be submitted to the Planning Authority with the application

Tooreen , Slievenalicka , Drumbaun & Lackamore

328m
2560578REFUSED19 Sept 2025

for the development at this site in the townlands of Slievenalicka, Illaunbaun, Drumbaun and Lackamore (although no infrastructure will be sited within Lackamore townland), Co. Clare. The development will consist of: • Construction of 1 wind turbine with a maximum overall blade tip height of 150m. • Construction of associated turbine foundation, crane pad hardstand and assembly area. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbine to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction and operation of the turbine. • Two borrow pits. • One peat repository area for peat and spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent and Temporary tree felling to accommodate the construction and operation of the turbine. • Signages. • All associated site development works. This application is seeking a 10-year planning permission, together with a 35-year operational life for the wind turbine from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes. The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) and Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the Planning Authority with the application

Slievenalicka , Illaunbaun Drumbaun , and Lackamore

974m
18521CONDITIONAL28 Jun 2018

to construct an extension on the Northwest side of the existing school consisting of a G.P. Hall and ancillary site works

Slievenalicka , Miltown Malbay , Co Clare

1.0km
19718CONDITIONAL12 Sept 2019

to upgrade an existing agricultural entrance to a Forest Road Bellmouth to facilitate timber harvesting, haulage operations and associated site works to existing forestry lands

Tooreen , Miltown Malbay , Ennis

1.0km
17415CONDITIONAL29 May 2017

To RETAIN 2 No French doors and existing balcony to rear elevation and to install a new balcony to rear of dwelling.

Slievenalicka , Miltown Malbay , Co Clare

1.1km
2460252CONDITIONAL30 May 2024

to extend and renovate the existing dwelling house along with elevation changes to the house and to construct a new wastewater treatment system along with all associated site works and services

Tooreen , Miltown Malbay , Co. Clare.

1.2km
17292CONDITIONAL20 Apr 2017

to construct a dwelling house, garage, proprietary waste water treatment system and ancillary site works

Slievenalicka , Miltown Malbay , Co. Clare

1.2km
17274REFUSED18 Apr 2017

to construct a dwelling house and proprietary waste water treatment system along with ancillary site works

Lackamore , Lahinch , Co. Clare

1.3km
20793CONDITIONAL30 Oct 2020

the development will consist of the replacement of existing substandard dwelling with a new dwelling house and the replacement of existing septic tank with a proprietary wastewater treatment system and polishing filter together with ancillary works

Slievenalicka , Miltown Malbay , Co Clare

1.3km
17150CONDITIONAL2 Mar 2017

to construct a single storey extension to the western side of existing dwelling house along with ancillary site works

Slievenalicka , Miltown Malbay , Co. Clare

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?