← Back to search

Matthewstown , Fenor Tramore , Co. Waterford

N/A

Planning application 2560801

Waterford - Waterford City and County Council

Proposed Development

Solar energy development to erect 292.32 kWp of photovoltaic panels on ground mounted steel frames with associated cabling and ducting to service existing building with all associated site works. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413)

View the full application file on the council's planning portal →

Application Details

Location
Matthewstown , Fenor Tramore , Co. Waterford
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Waterford City and County Council
Site Area
0.48 ha

Timeline

Registration Date
12 November 2025
Status
INCOMPLETED APPLICATION
Decision
N/A

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

202m
2660512N/A10 Jul 2026

on a site of approximately 18.75 hectares. The proposed development will consist of the expansion, upgrade and modernisation of an existing EPA licensed pig rearing installation (Licence Ref. P0410-01) as follows: • Construction of 1 no. single-storey pig fattening house (Building 511, maximum height c. 4.5m above ground level) with a gross floor area of approximately 3,763sqm (approximately 106m in length × 35.5m in width overall, including covered walkway), including associated feed storage silos, accommodating approximately 3,698 production pigs; • Provision of roof structures to existing whey storage tanks (Area 802) with a maximum height of approximately 5.93m to 8.99m above ground level; • Decommissioning of the existing open slurry lagoon (Structure 955), including emptying and removal of the existing concrete structure, reinstatement of suitable excavated material on site and removal of any contaminated material, and the construction of 2 no. covered overground slurry storage tanks, comprising: o 1 no. tank (Structure 951) with a capacity of approximately 5,236 cu.m and an overall height of approximately 7.3m above ground level; and o 1 no. tank (Structure 963) with a capacity of approximately 1,428cu.m³and an overall height of approximately 6.0m above ground level; • Provision of 1 no. single-storey dry store building with a floor area of approximately 531sqm and an overall height of approximately 9.83m above ground level; • Provision of a truck wash and wheel wash facility, including associated drainage infrastructure, silt trap and hydrocarbon interceptor; • Installation of slurry handling infrastructure serving the proposed pig fattening house (Building 511), including automatic scraper systems, channels, pumps, sumps and abstraction points; • Implementation of emission control measures, including the upgrade and conversion of Buildings 503–510 from natural to mechanical ventilation and modifications to ventilation infrastructure, including an increase in stack height at Building 204; • Installation of 3 no. new monitoring boreholes and 1 no. new on-site groundwater abstraction (production) well; • Provision of ancillary infrastructure including covered whey storage tanks, a designated carcass storage and collection area incorporating sealed and covered bio secure storage, upgrades to internal roadways and improvements to site drainage infrastructure, including connection to the existing integrated constructed wetland and all associated site

Fenor Pig Farm , Matthewstown , Fenor County Waterford (within the townland of Matthewstown)

202m
2660542N/A21 Jul 2026

development at Fenor Pig Farm, Matthewstown, Fenor, County Waterford(within the townland of Matthewstown), on a site of approximately 18.75 hectares. The proposed development will consist of the expansion, upgrade and modernisation of an existing EPA licensed pig rearing installation (Licence Ref. P0410-01) as follows: • Construction of 1 no. single-storey pig fattening house (Building 511, maximum height c. 4.5m above ground level) with a gross floor area of approximately 3,763sqm (approximately 106m in length × 35.5m in width overall, including covered walkway), including associated feed storage silos, accommodating approximately 3,698 production pigs; • Provision of roof structures to existing whey storage tanks (Area 802) with a maximum height of approximately 5.93m to 8.99m above ground level; • Decommissioning of the existing open slurry lagoon (Structure 955), including emptying and removal of the existing concrete structure, reinstatement of suitable excavated material on site and removal of any contaminated material, and the construction of 2 no. covered overground slurry storage tanks, comprising: o 1 no. tank (Structure 951) with a capacity of approximately 5,236m³ and an overall height of approximately 7.3m above ground level; and o 1 no. tank (Structure 963) with a capacity of approximately 1,428m³and an overall height of approximately 6.0m above ground level; • Provision of 1 no. single-storey dry store building with a floor area of approximately 531sqm and an overall height of approximately 9.83m above ground level; • Provision of a truck wash and wheel wash facility, including associated drainage infrastructure, silt trap and hydrocarbon interceptor; • Installation of slurry handling infrastructure serving the proposed pig fattening house (Building 511), including automatic scraper systems, channels, pumps, sumps and abstraction points; • Implementation of emission control measures, including the upgrade and conversion of Buildings 503–510 from natural to mechanical ventilation and modifications to ventilation infrastructure, including an increase in stack height at Building 204; • Installation of 3 no. new monitoring boreholes and 1 no. new on-site groundwater abstraction (production) well; • Provision of ancillary infrastructure including covered whey storage tanks, a designated carcass storage and collection area incorporating sealed andand covered bio-secure storage, upgrades to internal roadways and yard areas

Fenor Pig Farm , Matthewstown , Fenor County Waterford (within the townland of Matthewstown)

231m
2460405CONDITIONAL17 Jul 2024

construct new Staff Facilities for existing Staff on Fenor Pig Farm, consisting of Reception, Office, Store, Canteen and Changing Rooms (Approx. 13m x 16m x 5m high) and all ancillary and associated Site works.

Hilltop Farm Matthewstown , Fenor Tramore , Co. Waterford

261m
19228CONDITIONAL4 Apr 2019

to replace, upgrade and extend the existing feed milling building, to incorporate roof over existing feed silos and associated site works including a concrete yard and bunded area for existing liquid feed tanks. The site of the proposed development is on an IPPC Licensed facility Ref. No. P0410-01

Matthewson , Fenor , Co. Waterford

764m
2169CONDITIONAL4 Feb 2021

permission for changes to an existing dwelling house to include the conversion of attic space to living accommodation, the provision of new dormer and velux windows and changes to the ground floor layout resulting in minor changes to the facades of the existing dwelling house at

Ballydermody , Fenor , Co Waterford

764m
2168CONDITIONAL4 Feb 2021

for retention permission for changes to an existing dwelling house to include the construction of a side extension, the conversion of an attached garage space to living accommodation, the conversion of attic space to living accommodation and changes to the front façade of the dwelling house at

Ballydermody , Fenor , Co Waterford

770m
191005CONDITIONAL30 Dec 2019

to (1) construct a new roadside entrance and (2) raise levels of existing agricultural lands using clean inert soil and stones (EU Waste Class 17 0504) in order to improve the quality of said lands. An application for a waste disposal permit will be sought post planning

Ballymorris , Fenor , Co. Waterford

770m
18866N/A20 Dec 2018

indefinite retention of raised timber deck with stone facing to front of house

Ballydermody , Dunhill , Co. Waterford

770m
1977CONDITIONAL13 Feb 2019

indefinite retention of raised timber deck with stone facing to front of house

Ballydermody , Dunhill , Co. Waterford

770m
19649CONDITIONAL4 Sept 2019

change of use from storage area to 2 bedrooms and bathroom at first floor and altering 2 first floor gable windows to provide fire escape at residence

Ballydermody , Dunhill , Co. Waterford

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?