Proposed Development
RED III application for a 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening report
View the full application file on the council's planning portal →Application Details
- Location
- Powerstown Demesne and Burgagery Lands-East , Clonmel , Co. Tipperary
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 15.9 ha
Timeline
- Registration Date
- 29 August 2025
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
REDIII 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening Report.
Powerstown Demesne and Burgagery Lands-East , Clonmel , Co. Tipperary
RED III, A 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening Report
Powerstown Demesne and Burgagery Lands-East , Clonmel , Co. Tipperary
a 10-year planning permission for a solar energy development with a total site area of 15.9 hectares comprising (i) photovoltaic solar panels on mounting frames; (ii) electrical transformer stations; (iii) underground electrical and communications cabling; (iv) upgraded and new on-site access tracks; (v) security fencing and gates; (vi) pole-mounted security cameras; and (vii) all associated and ancillary site development, landscaping and reinstatement works. The operational lifetime of the proposed development is 35-years. The planning application is accompanied by an Appropriate Assessment Screening Report
Powerstown Demesne and Burgagery Lands-East , Clonmel , Co. Tipperary
3 no. horse stables and tack room and for Planning Permission for change of use of stables for use as domestic house stores
Powerstown , Clonmel , Co. Tipperary
3 no. horse stables and tack room and for Planning Permission for change of use of stables for use as domestic house stores
Powerstown Demesne , Clonmel , Co. Tipperary
conservatory as constructed to my bungalow residence
Powerstown , Clonmel , Co. Tipperary
conservatory as constructed to my bungalow residence
Powerstown Demesne , Clonmel , Co. Tipperary
the construction of two above ground water reservoirs, a new well, and all associated site development works
Clonmel Racecourse Powerstown Park , Powerstown Clonmel , Co. Tipperary
the construction of a new single-storey warehouse incorporating 2 no. dock levellers with canopy over, underground storm attenuation system and all associated site works
Powerstown , Clonmel , Co. Tipperary
the alterations to previously granted permission (PD. Ref: 2460001), for increase in height of 2.5m to warehouse building as granted, together with all associated site development works
Glenpatrick Spring Water Ltd. , Powerstown , Clonmel Co. Tipperary
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?