← Back to search

Derrygrogan Little and Derrygrogan Big , Tullamore , Co. Offaly

N/A

Planning application 2660048

Offaly - Offaly County Council

Proposed Development

Planning permission for a period of 10 years to construct and complete a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III) with a total site area of c. 28.1 hectares, to include solar PV ground mounted support structures, string inverters, transformer stations, electrical cabling and ducting, internal access tracks and hardstanding areas, perimeter fencing and access gate, CCTV, a temporary construction compound and other ancillary infrastructure including drainage, additional landscaping and habitat enhancement as required and associated site development works relating to the access of the site. The solar farm will be operational for 40 years in the townlands of Derrygrogan Little and Derrygrogan Big, Tullamore, Co. Offaly. A Natura Impact Statement (NIS) has been submitted with this application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    29 Jan 2026

  2. Decision due

    25 Mar 2026

Application Details

Location
Derrygrogan Little and Derrygrogan Big , Tullamore , Co. Offaly
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Offaly County Council
Site Area
28.1 ha

Timeline

Registration Date
29 January 2026
Status
INCOMPLETED APPLICATION
Decision
N/A
Decision Due
25 March 2026

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
2660216N/A23 Apr 2026

(RED III) a period of 10 years to construct and complete a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III) with a total site area of c. 28.1 hectares, to include solar PV ground mounted support structures, string inverters, transformer stations, electrical cabling and ducting, internal access tracks and hardstanding areas, perimeter fencing and access gate, CCTV, a temporary construction compound and other ancillary infrastructure including drainage, additional landscaping and habitat enhancement as required and associated site development works relating to the access of the site. The solar farm will be operational for 40 years in the townlands of Derrygrogan Little and Derrygrogan Big, Tullamore, Co. Offaly. A Natura Impact Statement (NIS) has been submitted with this application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Derrygrogan Little and Derrygrogan Big , Tullamore , Co. Offaly

0m
2660233N/A30 Apr 2026

(RED 111) a period of 10 years to construct and complete a Solar PV development (i.e. a relevant solar energy development as per the Renewable Energy Directive III) with a total site area of c. 28.1 hectares, to include solar PV ground mounted support structures, string inverters, transformer stations, electrical cabling and ducting, internal access tracks and hardstanding areas, perimeter fencing and access gate, CCTV, a temporary construction compound and other ancillary infrastructure including drainage, additional landscaping and habitat enhancement as required and associated site development works relating to the access of the site. The solar farm will be operational for 40 years in the townlands of Derrygrogan Little and Derrygrogan Big, Tullamore, Co. Offaly. A Natura Impact Statement (NIS) has been submitted with this application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Derrygrogan Little and Derrygrogan Big , Tullamore , Co. Offaly

0m
2660065N/A10 Feb 2026

a period of 10 years to construct and complete a Solar PV development (RED III) (i.e. a relevant solar energy development as per the Renewable Energy Directive III) with a total site area of c. 28.1 hectares, to include solar PV ground mounted support structures, string inverters, transformer stations, electrical cabling and ducting, internal access tracks and hardstanding areas, perimeter fencing and access gate, CCTV, a temporary construction compound and other ancillary infrastructure including drainage, additional landscaping and habitat enhancement as required and associated site development works relating to the access of the site. The solar farm will be operational for 40 years in the townlands of Derrygrogan Little and Derrygrogan Big, Tullamore, Co. Offaly. A Natura Impact Statement (NIS) has been submitted with this application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply

Derrygrogan Little and Derrygrogan Big , Tullamore , Co. Offaly

0m
2560667N/A19 Dec 2025

a period of 10 years to construct and complete a Solar PV development with a total site area of c. 28.1 hectares, to include solar PV ground mounted support structures, string inverters, transformer stations, electrical cabling and ducting, internal access tracks and hardstanding areas, perimeter fencing and access gate, CCTV, a temporary construction compound and other ancillary infrastructure including drainage, additional landscaping and habitat enhancement as required and associated site development works relating to the access of the site. The solar farm will be operational for 40 years in the townlands of Derrygrogan Little and Derrygrogan Big, Tullamore, Co. Offaly. A Natura Impact Statement (NIS) has been submitted with this application.

Derrygrogan Little and Derrygrogan Big , Tullamore , Co. Offaly

611m
20660N/A22 Dec 2020

CONSTRUCTION OF A STOREY AND HALF EXTENSION (127.8 SQ. M) TO THE REAR (NORTHWEST) AND SINGLE STOREY EXTENSION (11.2 SQ. M) TO THE SIDE (SOUTHWEST) OF THE EXISTING DWELLING. PERMISSION IS SOUGHT FOR ALTERATIONS TO THE EXISTING DWELLINGS ROOF LINE PROFILE AND WINDOWS ON ALL ELEVATIONS OF THE EXISTING DWELLING. PERMISSION IS ALSO SOUGHT TO CLOSE THE EXISTING DOMESTIC ENTRANCE AND TO UPGRADE EXISTING NORTHEAST ENTRANCE FOR DOMESTIC USE ONTO PUBLIC ROAD. PERMISSION IS ALSO SOUGHT TO DECOMMISSION THE EXISTING SEPTIC TANK AND PERCOLATION AREA AND INSTALL A PACKAGED WASTEWATER TREATMENT SYSTEM AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS

KILMURRY , BALLYCOMMON , CO. OFFALY R35 YA49

611m
18433CONDITIONAL8 Oct 2018

(A) DOMESTIC FUEL SHED (B) A SINGLE STOREY EXTENSION TO THE FRONT OF THE EXISTING DWELLING AND ALL ASSOCIATED SITE WORKS

KILMURRY , TULLAMORE , CO. OFFALY

612m
2149CONDITIONAL8 Feb 2021

CONSTRUCTION OF A STOREY & HALF EXTENSION (127.8 SQ.M) TO THE REAR (NORTHWEST) AND SINGLE STOREY EXTENSION (11.2 SQ.M) TO THE SIDE (SOUTHWEST) OF THE EXISTING DWELLING. PERMISSION IS SOUGHT FOR ALTERATIONS TO THE EXISTING DWELLINGS ROOF LINE PROFILE AND WINDOWS ON ALL ELEVATIONS OF THE EXISTING DWELLING. PERMISSION IS ALSO SOUGHT TO CLOSE THE EXISTING DOMESTIC ENTRANCE AND TO UPGRADE EXISTING NORTHEAST ENTRANCE FOR DOMESTIC USE ONTO THE PUBLIC ROAD. PERMISSION IS ALSO SOUGHT TO DECOMMISSION THE EXISTING SEPTIC TANK AND PERCOLATION AREA AND TO INSTALL A PACKAGED WASTEWATER TREATMENT SYSTEM AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS.

KILMURRY , BALLYCOMMON , CO. OFFALY R35 YA49

776m
24145N/A8 Oct 2024

DWELLING HOUSE WITH REVISED LAYOUT, INCLUDING S 2000 EFFLUENT TREATMENT SYSTEM AND ALL ASSOCIATED SITE WORKS AND PERMISSION TO EXTEND HOUSE

KILMURRAY , CO. OFFALY

776m
2460414CONDITIONAL18 Oct 2024

dwelling house with revised layout, including S 2000 effluent treatment system and all associated site works and permission to extend house.

Kilmurry , Co. , Offaly

1.0km
21684N/A3 Nov 2021

ALTERATION TO PL13/189 AND PL13/206 INCLUDING ALTERATION AND AUGMENTATION TO SLURRY STORAGE FACILITIES, DEMOLITION OF HAYBARN, ADDITIONAL DRY & CUBICLE HOUSING WITH ASSOCIATED SLURRY STORAGE, ALTERATIONS, AUGMENTATION AND REPLACEMENT TO FARM BUILDINGS/ANIMAL HOUSING, ADDITIONAL SILAGE PIT AREA AND ASSOCIATED SITE WORKS TO COMPLY WITH NITRATES DIRECTIVE

RATHDRUM , BALLYCOMMON TULLAMORE , CO. OFFALY

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?