2660207
REFUSEDClare - Clare County Council
Proposed Development
for the development of the Slievenalicka wind turbine in the townlands of Tooreen, Slievenalicka, Drumbaun & Lackamore (although no infrastructure will be sited within Lackamore townland), County Clare. The development will consist of: • Construction of 1 wind turbine with a maximum overall blade tip height of 150m. • Construction of associated turbine foundations, crane pad hardstand and assembly areas. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbines to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction & operation of the wind farm. • Two borrow pits. • One peat repository area for peat & spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent & Temporary tree felling to accommodate the construction & operation. • Signages and • All associated site development works. This application is seeking 10-year planning permission, along with a 35-year operational life for the wind farm from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413). The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) has been prepared in respect of the planning application and will be submitted to the Planning Authority with the application
View the full application file on the council's planning portal →Application Timeline
Application received
31 Mar 2026
Decision: REFUSED
3 Jul 2026
Decision due
6 Jul 2026
Appeal submitted
20 Jul 2026
Application Details
- Location
- Tooreen , Slievenalicka , Drumbaun & Lackamore
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Clare County Council
- Site Area
- 23.07 ha
Timeline
- Registration Date
- 31 March 2026
- Status
- APPEALED
- Decision
- REFUSED
- Decision Date
- 3 July 2026
An Coimisiún Pleanála Appeal
- Appeal Reference
- PL-501735-CE-26
- Submitted
- 20 July 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
for the development at this site in the townlands of Slievenalicka, Illaunbaun, Drumbaun and Lackamore (although no infrastructure will be sited within Lackamore townland), Co. Clare. The development will consist of: • Construction of 1 wind turbine with a maximum overall blade tip height of 150m. • Construction of associated turbine foundation, crane pad hardstand and assembly area. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbine to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction and operation of the turbine. • Two borrow pits. • One peat repository area for peat and spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent and Temporary tree felling to accommodate the construction and operation of the turbine. • Signages. • All associated site development works. This application is seeking a 10-year planning permission, together with a 35-year operational life for the wind turbine from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes. The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) and Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the Planning Authority with the application
Slievenalicka , Illaunbaun Drumbaun , and Lackamore
for the development of Illaunbaun Wind Farm in the townlands of Tooreen, Slievenalicka, Illaunbaun, Drumbaun & Lackamore (although no infrastructure will be sited within Lackamore townland), County Clare. The development will consist of: • Construction of 5 wind turbines with a maximum overall blade tip height of 150 m. • Construction of associated turbine foundations, crane pad hardstand and assembly areas. • Construction of one permanent 38 kV electrical on-site substation with one control building with welfare facilities, all associated electrical switchgear, security fencing, underground cabling, drainage infrastructure, and all ancillary works. • All associated internal underground electrical and communications cabling connecting the wind turbines to the on-site Substation. • Upgrade of existing tracks, roads and provision of new site access roads to facilitate construction & operation of the wind farm. • Two borrow pits. • Three peat repository areas for peat & spoil management. • Construction of one temporary construction compound. • Development of internal site drainage. • Permanent & Temporary tree felling to accommodate the construction & operation. • Signages and • All associated site development works. This application is seeking 10-year planning permission, along with a 35-year operational life for the wind farm from the date of its commissioning. The development is covered by the provisions of the Renewable Energy Directive III (Directive 2023/2413) Yes x No The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice is issued in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. An Environmental Impact Assessment Report (EIAR) & Screening for Appropriate Assessment have been prepared in respect of the planning application and will be submitted to the planning authority with the application.
Tooreen , Slievenalicka Illaunbaun , Drumbaun and Lackamore Co Clare
to construct an extension on the Northwest side of the existing school consisting of a G.P. Hall and ancillary site works
Slievenalicka , Miltown Malbay , Co Clare
To RETAIN 2 No French doors and existing balcony to rear elevation and to install a new balcony to rear of dwelling.
Slievenalicka , Miltown Malbay , Co Clare
to construct a dwelling house, garage, proprietary waste water treatment system and ancillary site works
Slievenalicka , Miltown Malbay , Co. Clare
to construct a single storey extension to the western side of existing dwelling house along with ancillary site works
Slievenalicka , Miltown Malbay , Co. Clare
to construct a single storey extension to the western side of existing dwelling house along with ancillary site works
Slievenalicka , Miltown Malbay , Co. Clare
to construct a single storey extension to the western side of existing dwelling house along with ancillary site works
Slievenalicka , Milown Malbay , Co. Clare
to demolish an exiting extension and construct a new single story extension to the rear of dwelling house along with ancillary site works
Slievenalicka , Miltown Malbay , Co Clare
for the development which will consist of the erection of a 2.39m high paladin fence measuring 30.4m in length and located along the northwestern boundary of Rockmount Water Treatment Plant
Leeds (townland) , Miltown Malbay , Co Clare
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?