Proposed Development
A 10 YEAR PLANNING PERMISSION FOR A LONG DURATION ENERGY STORAGE FACILITY CONSISTING OF: INSTALLATION AND OPERATION OF 1 NO. BATTERY ENERGY STORAGE SYSTEM COMPOUND CONTAINING BATTERY ENERGY STORAGE CONTAINERS, 1 NO. ELECTRICAL SUBSTATION AND COMPOUND, CONNECTION TO THE NATIONAL GRID SYSTEM VIA 50M OF UNDERGROUND CABLE TO THE ESB CROCKAHENNY 38KV SUBSTATION, ELECTRICAL TRANSFORMERS AND INVERTER UNITS, UNDERGROUND CABLING AND DUCTING, BOUNDARY FENCING, SECURITY ENTRANCE GATES, CCTV, INTERNAL ACCESS ROAD, ASSOCIATED ANCILLARY SITE DEVELOPMENT, LANDSCAPING AND REINSTATEMENT WORKS. THE OPERATIONAL LIFESPAN OF THE DEVELOPMENT WILL BE 35 YEARS AND THE SITE OF THE PROPOSED DEVELOPMENT HAS A TOTAL AREA OF C. 0.54 HECTARES. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
View the full application file on the council's planning portal →Application Details
- Location
- CROCKAHENNY , INISHOWEN , CO. DONEGAL
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Donegal County Council
- Site Area
- 0.54 ha
Timeline
- Registration Date
- 18 March 2026
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
A 10 YEAR PLANNING PERMISSION FOR A LONG DURATION ENERGY STORAGE FACILITY CONSISTING OF: INSTALLATION AND OPERATION OF 1 NO. BATTERY ENERGY STORAGE SYSTEM COMPOUND CONTAINING BATTERY ENERGY STORAGE CONTAINERS, 1 NO. ELECTRICAL SUBSTATION AND COMPOUND, CONNECTION TO THE NATIONAL GRID SYSTEM VIA 50M OF UNDERGROUND CABLE TO THE ESB CROCKAHENNY 38KV SUBSTATION, ELECTRICAL TRANSFORMERS AND INVERTER UNITS, UNDERGROUND CABLING AND DUCTING, BOUNDARY FENCING, SECURITY ENTRANCE GATES, CCTV, INTERNAL ACCESS ROAD, ASSOCIATED ANCILLARY SITE DEVELOPMENT, LANDSCAPING AND REINSTATEMENT WORKS. THE OPERATIONAL LIFESPAN OF THE DEVELOPMENT WILL BE 35 YEARS AND THE SITE OF THE PROPOSED DEVELOPMENT HAS A TOTAL AREA OF C. 0.54 HECTARES. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
CROCKAHENNY , INISHOWEN , CO. DONEGAL
A 10 YEAR PLANNING PERMISSION WITH A 35 YEAR OPERATIONAL LIFESPAN FOR DEVELOPMENT OF THE FOLLOWING: (1) INSTALLATION AND OPERATION OF 1NO. BATTERY ENERGY STORAGE SYSTEM COMPOUND CONTAINING BATTERY ENERGY STORAGE CONTAINERS, (2) 1NO. ELECTRICAL SUBSTATION AND COMPOUND, (3) CONNECTION TO NATIONAL GRID SYSTEM VIA 50M OF UNDERGROUND CABLE TO THE ESB CROCKAHENNY 38kV SUBSTATION, (4) ELECTRICAL TRANSFORMERS AND INVERTER UNITS, UNDERGROUND CABLING AND DUCTING, BOUNDARY FENCING, SECURITY ENTRANCE GATES AND CCTV, (5) INTERNAL ACCESS ROAD, (6) ASSOCIATED ANCILLARY SITE DEVELOPMENT, LANDSCAPING AND REINSTATEMENT WORKS. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
CROCKAHENNY , INISHOWEN , CO. DONEGAL
A PERIOD OF 10 YEARS FOR A LONG DURATION ENERGY STORAGE FACILITY WHICH WILL CONSIST OF THE FOLLOWING ELEMENTS: INSTALLATION AND OPERATION OF 1 NO. ENERGY STORAGE SYSTEM COMPOUND CONTAINING ENERGY STORAGE CONTAINERS, CONNECTED TO THE NATIONAL GRID SYSTEM VIA C. 50M OF UNDERGROUND CABLE TO THE CUSTOMER SUBSTATION, UPGRADES TO THE EXISTING CUSTOMER SUBSTATION, ELECTRICAL TRANSFORMERS AND INVERTER UNITS, UNDERGROUND CABLING AND DUCTING, BOUNDARY FENCING, SECURITY ENTRANCE GATES, CCTV, INTERNAL ACCESS ROADS, ANCILLARY SITE DEVELOPMENT, LANDSCAPING AND REINSTATEMENT WORKS. THE OPERATIONAL LIFESPAN OF THE DEVELOPMENT WILL BE 35 YEARS AND THE SITE OF THE PROPOSED DEVELOPMENT HAS A TOTAL AREA OF C. 0.54 HECTARES. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
CROCKAHENNY , INISHOWEN , CO. DONEGAL
A PERIOD OF 10 YEARS FOR THE PROPOSED DEVELOPMENT WHICH WILL CONSIST OF THE FOLLOWING ELEMENTS: INSTALLATION AND OPERATION OF 1 NO. NEW 38KV SUBSTATION, INCLUDING A NEW 38KV BUILDING AND COMPOUND, 38KV ESB LINE BAY, RELOCATION OF THE EXISTING 38KV CABLE MAST, UPGRADES TO THE EXISTING CUSTOMER SUBSTATION AND 38KV LINE, C. 50M OF UNDERGROUND CABLE TO THE CUSTOMER SUBSTATION, ELECTRICAL EQUIPMENT, UNDERGROUND CABLING AND DUCTING, BOUNDARY FENCING, SECURITY ENTRANCE GATES, CCTV, INTERNAL ACCESS ROADS, ANCILLARY SITE DEVELOPMENT, LANDSCAPING AND REINSTATEMENT WORKS. THE OPERATIONAL LIFESPAN OF THE DEVELOPMENT WILL BE 35 YEARS. THE SITE OF THE PROPOSED DEVELOPMENT HAS A TOTAL AREA OF C. 0.54 HECTARES. THIS DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
CROCKAHENNY , INISHOWEN , CO. DONEGAL
CONSTRUCTION OF A NEW DWELLING HOUSE TOGETHER WITH INSTALLATION OF ONSITE SEPTIC TANK
CROCKAHENNY , ILLIES , BUNCRANA
CONSTRUCTION OF A NEW DWELLING HOUSE TOGETHER WITH INSTALLATION OF AN ONSITE SEPTIC TANK
CROCKAHENNY , ILLIES , BUNCRANA
CONSTRUCTION OF A NEW DWELLING HOUSE TOGETHER WITH INSTALLATION OF AN ONSITE SEPTIC TANK
CROCKAHENNY , ILLIES , BUNCRANA
CONSTRUCTION OF A NEW DWELLING HOUSE TOGETHER WITH INSTALLATION OF AN ONSITE SEPTIC TANK
CROCKAHENNY , ILLIES , BUNCRANA
ERECTION OF A DWELLING WITH EFFLUENT TREATMENT SYSTEM, DOMESTIC GARAGE AND ALL ASSOCIATED SITE DEVELOPMENT WORKS
CROCKAHENNY , ILLIES , CO DONEGAL
A 10-YEAR PLANNING PERMISSION FOR THE CONSTRUCTION OF TWO WIND TURBINES WITHIN THE LANDHOLDING OF THE CROCKAHENNY WINDFARM AND ALL ASSOCIATED WORKS INCLUDING TWO WIND TURBINES THAT WILL HAVE AN OVERALL BLADE TIP HEIGHT OF UP TO 135 METRES; SITE WORKS INCLUDING THE CONSTRUCTION OF WIND TURBINE FOUNDATIONS, TURBINE HARD STANDINGS AND ASSEMBLY AREAS WITH ASSOCIATED DRAINAGE; A PROPOSED 38 KV ELECTRICAL SUBSTATION TO REPLACE THE EXISTING ELECTRICAL SUBSTATION AND CONTINUED USE OF THE EXISTING ELECTRICAL COMPOUND; TWO EXTENSIONS OF EXISTING ACCESS TRACKS WITHIN THE SITE; INSTALLATION OF UNDERGROUND ELECTRICAL CABLE IN EXISTING ELECTRICAL DUCTS AND ALL ASSOCIATED SITE DEVELOPMENT AND ANCILLARY WORKS. THE PROPOSED WIND TURBINES WILL CONNECT TO THE PROPOSED SUBSTATION AND WILL AVAIL OF THE EXISTING TRACKS AND ENTRANCE. THE PROPOSED DEVELOPMENT WILL HAVE A 30 YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING. THE DEVELOPMENT IS COVERED BY THE PROVISIONS OF THE (RED III) RENEWABLE ENERGY DIRECTIVE III (DIRECTIVE (EU) 2023/2413)
CROCKAHENNY , LEAMACROSSAN HILL , INISHOWEN
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?