Proposed Development

the construction of a single storey energy substation building and all ancillary site development works. The development also includes a temporary compound to house a transformer which will be relocated into the proposed energy substation building upon completion

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    28 May 2026

  2. Further information requested

    22 Jul 2026

Application Details

Location
University Hospital Kerry , Cloon More Tralee , Co. Kerry
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Kerry County Council
Site Area
0.364 ha

Timeline

Registration Date
28 May 2026
Status
FURTHER INFORMATION
Decision
N/A

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

104m
191064CONDITIONAL15 Oct 2019

CONSTRUCT A NEW SINGLE STOREY ROOF LEVEL EXTENSION COMPRISING NEW LABORATORIES AND LABORATORY SUPPORT ACCOMMODATION, LOCATED AT FIRST FLOOR LEVEL, ON AN EXISTING ROOF ABOVE AN EXISTING SINGLE STOREY PORTION OF THE EXISTING HOSPITAL, AND WILL INCLUDE A NEW STAIRS EXTENDING THROUGH EXISTING ACCOMMODATION AT GROUND FLOOR LEVEL, NEW CIRULATION LINKAGES TO EXISTING ACCOMMODATION AT FIRST FLOOR LEVEL, TOGETHER WITH THE UPGRADING AND RECLADDING OF PART OF THE EXISTING SINGLE STOREY FRONTAGE OF THE HOSPITAL, INCLUDING THE EXISTING MAIN ENTRANCE AT GROUND FLOOR LEVEL, TOGETHER WITH ASSOCIATED LOCALISED DEMOLITIONS AND NEW SITE WORKS AND SERVICES

UNIVERSITY HOSPITAL KERRY , CLOON MORE , TRALEE

127m
2560224CONDITIONAL26 Mar 2025

The construction of a vertical extension to a single storey portion of the existing building to provide for a three-storey in-patient ward. The development also includes internal and external alterations, the provision of internal and external plant room and plant area, solar panels at roof level, and all ancillary site development works.

University Hospital Kerry , Tralee , Co. Kerry

132m
211456CONDITIONAL15 Dec 2021

A) RETAIN EXTENSION AS CONSTRUCTED AND B) PERMISSION TO ALTER EXTENSION ALONG WITH ASSOCIATED SITE WORKS

NO. 107 NEW MARIAN PARK , TRALEE , CO KERRY

133m
191198REFUSED26 Nov 2019

RETAIN EXTENSION TO EXISTING HOUSE

107 NEW MARIAN PARK , TRALEE , CO KERRY

182m
21470CONDITIONAL29 Apr 2021

CONSTRUCT A NEW SINGLE STOREY EXTENSION TO THE EXISTING OPERATING THEATRES DEPARTMENT ON THE ADJACENT ROOF AREA PLUS THE CONSTRUCTION OF A NEW THREE STOREY BLOCK TO ACCOMMODATE NEW PLANT ROOMS AT FIRST AND SECOND FLOOR LEVELS TO SERVE THE EXPANDED DEPARTMENT, OVER A NEW UNDER-CROFT AREA AT GROUND FLOOR LEVEL AVAILABLE FOR THE FUTURE EXPANSION AND INSTALLATION OF PHOTOVOLTAIC PANELS AT ROOF LEVEL, PLUS LOCALISED ALTERATIONS TO THE EXISTING OPERATING DEPARTMENT TO INCLUDE LOCALISED UPGRADE OF EXTERNAL CLADDING. ACCESS TO THE NEW DEVELOPMENT WILL BE THROUGH THE EXISTING THEATRES DEPARTMENT AND THE EXISTING HOSPITAL STREET. THE PROPOSAL INCLUDES THE DEVELOPMENT OF A NEW LIFT INSTALLATION, ESCAPE STAIRS, AND EXTERNAL PLANT COMPOUNDAT FIRST FLOOR LEVEL AT UNIVERSITY HOSPITAL KERRY , RATHASS, TRALEE

RATHASS , TRALEE

190m
2484N/A29 Feb 2024

ADDITION OF AN ADDITIONAL STORY/FLOOR TO A PRE-EXISTING SINGEL STOREY STRUCTURE TO THE REAR OF THE DWELLING COMPLETE WITH AN A-FRAMED ROOF

52 OLD MARIAN PARK , TRALEE , CO KERRY

190m
24219CONDITIONAL30 May 2024

CHANGE OF USE OF EXISTING MODELLING AND STONE CASTING WORKSHOP AND STORES TO A RESIDENTIAL DWELLING AND ASSOCIATED SITE WORKS

Farranreagh , Knightstown , Valencia Island

190m
2460219CONDITIONAL17 Apr 2024

THE DEVELOPMENT WILL CONSIST OF THE ADDITION OF AN ADDITIONAL STORY/FLOOR TO A PRE EXISTING SINGLE STORY STRUCTURE TO THE REAR OF THE DWELLING - COMPLETE WITH AN A-FRAMED ROOF

52 Old Marian Park , Tralee , Kerry

215m
23949CONDITIONAL30 Aug 2023

DEMOLISH AN EXISTING 30M HIGH REDUNDANT CHIMNEY STACK, PERMISSION FOR CONSTRUCTION OF AN ESB SUBSTATION, SWITCHROOM, MAINTENANCE STORE, FUEL STORE, ENCLOSED GENERATOR COMPOUND, LPG STORAGE TANK, PEDESTRIAN CROSSING, PEDESTRIAN ENTRANCE AND AMBULANCE ENTRANCE ON THE CLASH BALLYMULLEN RELIEF ROAD, ERECTION OF SECURITY FENCING, ERECTION OF ACCESS CONTROL BARRIERS/GATES, REALIGNMENT OF INTERNAL CIRCULATION FOOTPATHS AND ASSOCIATED SITE WORKS

UNIVERSITY HOSPITAL KERRY , CLOON MORE , TRALEE CO KERRY

223m
1749CONDITIONAL24 Jan 2017

FOR EXTENSION AND ALTERATIONS TO MORTUARY WITHIN THE GROUNDS OF UNIVERSITY HOSPITAL KERRY. THE WORKS WILL INCLUDE THE FOLLOWING: CONSTRUCTION OF A NEW SINGLE STOREY MORTUARY, CONTAINING FAMILY ROOM AND WAITING AREA, INTERNAL ALTERATIONS TO EXISTING LAYOUT, REPLACEMENT OF EXTERNAL WINDOWS, WALL MOUNTED BUILDING SIGNAGE, ALTERATIONS TO DROP-OFF AREA, ANCILLARY SITE WORKS AND ALL ASSOCIATED EXTERNAL WORKS

UNIVERSITY HOSPITAL KERRY , TRALEE , CO KERRY

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?