2660506
N/AKerry - Kerry County Council
Proposed Development
REDS III: The development will consist of a 10-year permission for a solar photovoltaic (PV) energy development on a site spanning approximately 138.9 hectares. It will consist of the construction of PV panels mounted on metal frames, 38 inverters, new access tracks, underground cabling, perimeter fencing with CCTV cameras and access gates, 4 temporary construction compounds, drainage infrastructure, landscaping and all ancillary electrical infrastructure and associated works. A separate application for the associated grid route and future 110kV substation will be submitted to An Coimisiún Pleanála (ACP) as these proposed elements fall within the Strategic Infrastructure Development consent process under Section 182A of the Planning and Development Act 2000 (as amended).The Application Site will be accessed from four new access points off the R553, L6029 and L6028 and one existing access point off the L6037. The development is designed to operate for 40 years from the date of commissioning. A Natura Impact Statement (NIS) will accompany the planning application.
View the full application file on the council's planning portal →Application Details
- Location
- situated on land within the townlands of Inch East Garryard Carhoonaknock West Shrone Middle Derra East and Derra West , Civil Parish of Galey , County Kerry
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Kerry County Council
- Site Area
- 138.9 ha
Timeline
- Registration Date
- 5 June 2026
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
RETAIN DOMESTIC GARAGE/UTILITY STORE WITH A LOFT AT FIRST FLOOR LEVEL ALSO TO RETAIN TURF SHED
DERRA WEST , LISTOWEL , CO KERRY
CONSTRUCT A WASTE RECOVERY FACILITY FOR THE IMPORTATION OF WASTE MATERIAL COMPRISING OF SOIL AND STONE (17 05 04) TO RAISE AN AGRICULTURAL FIELD IN ORDER TO IMPROVE THE AGRICULTURAL OUTPUT OF THE FIELD. A NATURA IMPACT STATEMENT (NIS) HAS BE PREPARED AND WILL BE SUBMITTED WITH THIS APPLICATION
DERRA WEST , LISTOWEL , CO KERRY
RETAIN AN EXISTING ACCESS AND PLANNING PERMISSION TO UPGRADE THIS ACCESS
DERRA WEST , LISTOWEL , CO KERRY
TO RETAIN DWELLING HOUSE AND ALL OUT BUILDINGS AND SHEDS AS CONSTRUCTED WITHIN REVISED SITE BOUNDARIES AND PERMISSION TO DECOMMISSION EXISTING WASTE WATER TREATMENT SYSTEM AND INSTALL NEW WASTE WATER TREATMENT SYSTEM ON SITE
DERRA WEST , LISTOWEL , CO KERRY
ERECT AN EASY FEED SYSTEM WITH AN UNDERGROUND SLURRY TANK ON HER FARMYARD
HERMITAGE FARM , DIRHA WEST , LISTOWEL
RETAIN AND COMPLETE AGRICULTURAL SHED ON HIS LAND HOLDING
DERRA EAST , LISTOWEL , CO KERRY
(a) Retain a stone area on his land holding (b) retain entrance and Planning Permission to erect an agricultural storage shed for storing fodder
Derra West , Listowel , Co. Kerry
RETAIN THEIR DOMESTIC GARAGE/UTILITY STORE AS CONSTRUCTED TO THE REAR OF THEIR SITE
DERRA WEST , LISTOWEL , CO KERRY
(A) BUILD A DWELLING HOUSE AND WASTE WATER TREATMENT UNIT AND SOIL POLISHING FILTER ALL ASSOCIATED SITE WORKS, (B) TO BUILD A DETACHED DOMESTIC GARAGE AND ASSOCIATED SITE WORKS ALL AT SITE 11 AND (C) TO COMPLETE EXISTING ESTATE ROAD, FOOTPATH AND SITE SERVICES
DERRA EAST , LISTOWEL , CO KERRY
RETAIN EXISTING VIEWING STAND AND MACHINERY SHELTER, ALL ON THEIR LAND
DERRA EAST , LISTOWEL , CO KERRY
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?