Proposed Development
retain the works carried out to include the extraction and storage of stone from part of the existing quarry identified as the extracted area comprising of approximately 0.65 Ha. of the quarry site area of 2.39Ha. Permission is sought for the following : 1. Continuation of the extraction of stone over the same area (0.65ha) and the proposed new extended area comprising of 0.85 Ha. 2. Continuation of the processing and storage of the stone over a period of 10 years not exceeding 30,000 tons annually. 3. Installation of new drainage to sediment ponds with discharge to ground water. 4. Installation of a wheel wash and weighbridge on site. 5. Installation of welfare facility unit, a site office and staff car parking. 6. All ancillary site works at Rossmore, Co. Laois 7. An Appropriate Assessment Screening and an Environmental Impact Assessment Screening Report is included with the application It is proposed to restore the quarry to farmland or forestry on completion.
View the full application file on the council's planning portal →Application Timeline
Application received
30 Jul 2026
Decision due (upcoming)
23 Sept 2026
Application Details
- Location
- Rossmore , Laois , Co. Laois
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Laois County Council
- Site Area
- 2.39 ha
Timeline
- Registration Date
- 30 July 2026
- Status
- NEW APPLICATION
- Decision
- N/A
- Decision Due
- 23 September 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Retain works carried out to include the extraction and storage of stone from part of an existing quarry and permission sought for the continuation over the same area and a proposed new extended area
Rossmore , Co. Laois
Retain works carried out to include the extraction and storage of stone from part of an existing quarry and permission sought for the continuation over the same area and a proposed new extended area
Rossmore , Laois , Co. Laois
include the extraction and storage of stone from part of the existing quarry identified as the extracted area comprising of approximately 0.65 Ha. of the quarry site area of 2.39Ha. Permission is sought for the following : 1. Continuation of the extraction of stone over the same area (0.65ha) and the proposed new extended area comprising of 0.85 Ha. 2. Continuation of the processing and storage of the stone over a period of 10 years not exceeding 30,000 tons annually. 3. Installation of new drainage to sediment ponds with discharge to ground water. 4. Installation of a wheel wash and weighbridge on site. 5. Installation of welfare facility unit, a site office and staff car parking. 6. All ancillary site works at Rossmore, Co. Laois 7. An Appropriate Assessment Screening and an Environmental Impact Assessment Screening Report is included with the application It is proposed to restore the quarry to farmland or forestry on completion.
Rossmore , Laois , Co. Laois
works carried out to include the extraction and storage of stone from part of the existing quarry identified as the extracted area comprising of approximately 0.65 Ha. of the quarry site area of 2.39Ha. Permission is sought for the following : 1. Continuation of the extraction of stone over the same area (0.65ha) and the proposed new extended area comprising of 0.85 Ha. 2. Continuation of the processing and storage of the stone over a period of 10 years not exceeding 30,000 tons annually. 3. Installation of new drainage to sediment ponds with discharge to ground water. 4. Installation of a wheel wash and weighbridge on site. 5. Installation of welfare facility unit, a site office and staff car parking. 6. All ancillary site works at Rossmore, Co. Laois 7. An Appropriate Assessment Screening and an Environmental Impact Assessment Screening Report is included with the application It is proposed to restore the quarry to farmland or forestry on completion.
Rossmore , Laois , Co. Laois
carry out amendments to the consented (but not yet constructed) substation development permitted as part of Laois County Council Planning Reference 20/281 comprising a Revised 38kV Substation and Compound Area including a single storey control building (c5.3m height and c162sqm) and all associated electrical infrastructure and apparatus, New and Upgraded Site Entrance and Access Road and associated ancillary site development works
Rossmore , n/a , Co. Laois
Amend the consented (but not yet constructed) substation development permitted as part of Laois County Council Planning Reference 20/281 comprising a Revised 38kV Substation and Compound Area including a single storey control building (c5.3m height and c162sqm) and all associated electrical infrastructure and apparatus, New and Upgraded Site Entrance and Access Road and associated ancillary site development works.
Rossmore , n/a , Co. Laois
construct a single storey dwelling, new entrance, wastewater treatment system and percolation area, bored well and all associated site works
Upper Rossmore , Co. Laois
to construct a dormer style dwelling, attached single storey open double garage, new entrance, waste water treatment system and percolation area, bored well, and all associated site works
Upper Rossmore , Co. Laois
Construct a dormer style dwelling, attached single storey open double garage, new entrance, waste water treatment system and percolation area, bored well, and all associated site works.
Upper Rossmore , Co. Laois , Co. Laois
construct a dormer style dwelling, attached single storey open double garage, new entrance, waste water treatment system and percolation area, bored well, and all associated site works
Upper Rossmore , Co. Laois
Affected by this application?
Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.
Make a Submission or ObjectionPlanning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?