3687/23

GRANT RETENTION PERMISSIO

Dublin - Dublin City Council

Proposed Development

RETENTION: The development consists of retention for change of use of attic space to storage space, with new rooflight windows to the front and rear and internal alterations. Retention for the widening of front Vehicular entrance and relocation of pier and all associated ancillary site works required.

Application Timeline

  1. Application received

    4 May 2023

  2. Decision due

    28 Jun 2023

  3. Decision: GRANT RETENTION PERMISSIO

    28 Jun 2023

  4. Grant issued

    9 Aug 2023

Application Details

Location
52, Walkinstown Road, Dublin 12, D12 AA42
Applicant
N/A
Application Type
Retention Permission
Planning Authority
Dublin City Council
Site Area
307 ha

Timeline

Registration Date
4 May 2023
Status
Decision Notice Issued
Decision
GRANT RETENTION PERMISSIO
Decision Date
28 June 2023
Grant Date
9 August 2023

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
3535/23APPLICATION DECLARED INVA11 Apr 2023

RETENTION: The development consists of retention for change of use of attic space to storage space, with new rooflight windows to the front and rear and internal alterations. Retention for the widening of front entrance and relocation of pier and all associated ancillary site works required.

52, Walkinstown Road, Dublin 12, D12 AA42

61m
WEB1590/23GRANT PERMISSION20 Jul 2023

The development will consist of i) the demolition of the existing single storey rear playroom extension, external store and garage and ii) the construction of a single storey extension to the side and rear of the existing dwelling, iii) internal alterations and iv) all associated site works.

68, Walkinstown Road, Dublin 12 D12 H6C7

61m
WEB1541/23APPLICATION DECLARED INVA28 Jun 2023

The development will consist of i) the demolition of the existing single storey rear playroom extension, external store and garage and ii) the construction of a single storey extension to the side and rear of the existing dwelling, iii) internal alterations and iv) all associated site works

68, Walkinstown Road, Walkinstown, Dublin 12 D12 H6C7

61m
WEB1220/24GRANT PERMISSION27 Feb 2024

The development will consist of i) the construction of a first-floor side extension with flat roof, ii) the reduction in size of the previously granted single storey rear extension granted under planning reference WEB1590/23 and iii) all associated site works

68, Walkinstown Road, Dublin 12

66m
WEB1027/20APPLICATION DECLARED INVA17 Jan 2020

Retention of existing rooflights to front and side elevations and existing attic conversion at 47, Walkinstown Rd, Walkinstown, Dublin 12

47, Walkinstown Road, Walkinstown, Dublin 12, D12

66m
WEB1038/20GRANT RETENTION PERMISSIO24 Jan 2020

Retention of existing rooflights to front and side elevations and existing attic conversion at 47, Walkinstown Rd, Walkinstown, Dublin 12

47, Walkinstown Road, Walkinstown, Dublin 12

66m
WEB1004/20APPLICATION DECLARED INVA2 Jan 2020

Retention of existing rooflights to front and side elevations and existing attic conversion at 47, Walkinstown Rd, Walkinstown, Dublin 12

47, Walkinstown Road, Dublin 12

80m
4212/23GRANT PERMISSION25 Jul 2023

The development will consist of the installation of approx. 1020 sq.m of photo-voltaic solar panels onto the existing supermarket roof. The solar panels will be used to create green electricity, all of which will be used by the store.

Supervalu Walkinstown, Walkinstown Avenue, Dublin 12

80m
4058/24GRANT PERMISSION23 Jul 2024

The development will consist of the installation of a modular substation and ancillary site development works; to facilitate 2 no. shared electric vehicle charging units and 4 no. charging bays and ancillary site works within a partially reconfigured parking area.

Supervalu Shopping Centre, Walkinstown Road, Dublin 12, D12XDK2

108m
4014/24APPLICATION DECLARED INVA12 Jul 2024

The development will consist of the installation of a modular substation and ancillary site development works; to facilitate 2 no. shared electric vehicle charging units and 4 no. charging bays and ancillary site works within a partially reconfigured parking area.

Supervalu Shopping Centre, Walkinstown Road, Dublin 12, D12 XDK2

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?