4058/24
GRANT PERMISSIONDublin - Dublin City Council
Proposed Development
The development will consist of the installation of a modular substation and ancillary site development works; to facilitate 2 no. shared electric vehicle charging units and 4 no. charging bays and ancillary site works within a partially reconfigured parking area.
Application Timeline
Application received
23 Jul 2024
Decision due
16 Sept 2024
Decision: GRANT PERMISSION
16 Sept 2024
Grant issued
30 Oct 2024
Application Details
- Location
- Supervalu Shopping Centre, Walkinstown Road, Dublin 12, D12XDK2
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- Dublin City Council
- Site Area
- 129 ha
Timeline
- Registration Date
- 23 July 2024
- Status
- Decision Notice Issued
- Decision
- GRANT PERMISSION
- Decision Date
- 16 September 2024
- Grant Date
- 30 October 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The development will consist of the installation of approx. 1020 sq.m of photo-voltaic solar panels onto the existing supermarket roof. The solar panels will be used to create green electricity, all of which will be used by the store.
Supervalu Walkinstown, Walkinstown Avenue, Dublin 12
The construction of a single storey extension to the front of the building, consisting of a front porch and an extension to the front living room
6, Hardebeck Avenue, Walkinstown, Dublin 12
Retention of existing rooflights to front and side elevations and existing attic conversion at 47, Walkinstown Rd, Walkinstown, Dublin 12
47, Walkinstown Road, Walkinstown, Dublin 12, D12
Retention of existing rooflights to front and side elevations and existing attic conversion at 47, Walkinstown Rd, Walkinstown, Dublin 12
47, Walkinstown Road, Walkinstown, Dublin 12
Retention of existing rooflights to front and side elevations and existing attic conversion at 47, Walkinstown Rd, Walkinstown, Dublin 12
47, Walkinstown Road, Dublin 12
The development will consist of the installation of a modular substation and ancillary site development works; to facilitate 2 no. shared electric vehicle charging units and 4 no. charging bays and ancillary site works within a partially reconfigured parking area.
Supervalu Shopping Centre, Walkinstown Road, Dublin 12, D12 XDK2
single-storey extension to front, demolition of existing extension to rear & Chimney and single and double storey extension to rear of existing property and all associated site works
4, Hardebeck Avenue, Walkinstown, Dublin 12, D12 EOY2
RETENTION: The development consists of retention for change of use of attic space to storage space, with new rooflight windows to the front and rear and internal alterations. Retention for the widening of front entrance and relocation of pier and all associated ancillary site works required.
52, Walkinstown Road, Dublin 12, D12 AA42
RETENTION: The development consists of retention for change of use of attic space to storage space, with new rooflight windows to the front and rear and internal alterations. Retention for the widening of front Vehicular entrance and relocation of pier and all associated ancillary site works required.
52, Walkinstown Road, Dublin 12, D12 AA42
The development will consist of i) the demolition of the existing single storey rear playroom extension, external store and garage and ii) the construction of a single storey extension to the side and rear of the existing dwelling, iii) internal alterations and iv) all associated site works.
68, Walkinstown Road, Dublin 12 D12 H6C7
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?