the construction of a seven storey over basement Hotel of approximately 31,955 sqm, providing 250 no. bedrooms (approximately 1000 no. bedspaces) at first to fifth floor levels, accessed from the established internal Tayto Park access road. The proposed hotel incorporates a Leisure Centre of 3,382 sqm at ground floor and mezzanine level, a dedicated Function/Conference area of 2,359 sqm at ground floor; a Spa and Therapy Centre of 530 sqm at first and second floor level; 2 no. Sky Lounges of 702 sqm at sixth floor level and all associated and ancillary stores, services and circulation space. The ground floor level provides a main entrance porch, foyer and lounge areas; a main lounge and bar; 3 no. main dining rooms and 2 no. ancillary dining rooms providing 2 no. restaurants for fine dining and general dining; 3 no. kitchens and associated stores; a servery area; a single shop/kiosk unit (23 sqm); plant; an ESB substation and a service corridor to the rear. Ancillary and associated storage and staff facilities including a staff room, toilet facilities, changing facilities and a dedicated kitchen are located at mezzanine level above the kitchens at ground floor level. The basement level provides associated plant and storage space for the Hotel and Leisure Club with vehicular access to the basement via a service ramp from the proposed surface car parking area. The Function/Conference area incorporates 3 no. reception areas and bars and a dedicated entrance. The proposed Leisure Centre consists of a dedicated landscaped entrance; foyer; adult and family changing areas; a junior play and acitivity area; a parents' lounge and viewing area; a family leisure pool including flume slide; a 30m exercise pool; 2 no. wet lounges; a Jacuzzi; Sauna, Steam and Plunge Pool rooms; and a gym incorporating a studio room and cardio vascular room at ground floor level along with a weights area at mezzanine level. Ancillary and associated office suites for the hotel are located adjacent to the weights area at mezzanine level. The proposed development also includes the provision of an attenuation pond of 3,145 sqm surface area; 2 no. vehicular bridges and 1 no. pedestrian bridge over the River Hurley (incorporating the existing bridge); internal roads and junctions with the established internal access road; hardstanding service yard to the rear; vehicular set down areas at the hotel entrance; 40 no. surface car parking spaces associated ..........

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    24 May 2017

  2. Further information requested

    14 Jul 2017

  3. Application withdrawn

    8 May 2018

Application Details

Location
Tayto Park Visitor Centre , Kilbrew Ashbourne , Co. Meath
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Meath County Council
Site Area
5.47 ha

Timeline

Registration Date
24 May 2017
Status
WITHDRAWN
Decision
N/A
Withdrawn
8 May 2018

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

92m
221541REFUSED28 Nov 2022

erection of a 21m monopole telecommunications support structure together with antennae, dishes and associated telecommunications equipment, all enclosed in security fencing and to extend the access track. Significant further information/revised plans submitted on this application

Tayto Park Visitor Centre , Kilbrew , Ashbourne Co Meath

316m
AA181453CONDITIONAL6 Dec 2018

the construction of a new rollercoaster attraction incorporating 2 separate rollercoaster rides with a combined ride length of approximately 972m and a maximum height of 31 m above ground level; rollercoaster station structures; ancillary buildings including a toilet block (80 sqm Gross Floor Area (GFA), a photo shop (8 sqm GFA), a ground shop (30 sqm GFA), 2 no. concession stands (12.8 sqm GFA each) and an ESB substation (14 sqm GFA); 2 no. pedestrian bridges over the Hurley River; internal paths and roadways connecting to existing Tayto Park infrastructure; drainage infrastruture; landscaping; and, all associated and ancillary plant and development works on a site area of 4.53 ha.This application is accompanied by an Environmental Impact Assessment Report (EIAR)

Tayto Park Visitor Centre , Kilbrew , Ashbourne Co. Meath

385m
AA180563CONDITIONAL31 May 2018

a part storey and a half, part single storey dwelling house, detached garage, new wastewater treatment system and percolation area, and all associated site development works. Significant further information/revised plans submitted on this application

Kilbrew , Ashbourne , Co. Meath

389m
23616CONDITIONAL12 Jun 2023

outline permission for a detached storey and a half dwelling house, detached garage, wastewater treatment unit and percolation area, new vehicular entrance gateway, access road, along with all associated services, service connections, landscape and site development works

Kilbrew , Ashbourne , Co Meath

397m
221219REFUSED16 Sept 2022

outline permission for a detached storey and a half dwelling house, detached garage, wastewater treatment unit and percolation area, new vehicular entrance gateway, access road, along with all associated services, service connections landscape and site development works

Kilbrew , Ashbourne , Co. Meath

398m
23357CONDITIONAL3 Apr 2023

permission is sought for new single storey extension to the north facade (76sq.m) to consist of new entrance/reception area, minor ground floor internal reconfiguration, minor first floor internal reconfiguration, additional roof lights, replacement of existing treatment system for new to comply with EPA 2021 and all associated site works. A protected structure 'Kilbrew House' lies within the applicants site boundary (ref. NO. mh-039-102). Significant further information/revised plans submitted on this application

Kilbrew Recouperation & Nursing Care , Ashbourne , Co. Meath

398m
AA201677REFUSED10 Nov 2020

the provision of a dwelling and garage with wastewater treatment system and associated site works

Kilbrew , Curragha , Ashbourne Co. Meath

401m
23166N/A21 Feb 2023

the development will consist of outline permission for a detached storey and a half dwelling house, detached garage, wastewater treatment unit and percolationarea, new vehicular entrance getway, access road, along with all associated services, service connections, landscape and site development works

Kilbrew , Ashbourne , Co. Meath

401m
23945CONDITIONAL4 Oct 2023

a detached storey and a half dwelling house with first floor terrace to the rear, detached garage, wastewater treatment unit and percolation area, new vehicular entrance gateway, access road, along with all associated services, service connections, landscape and site development works

Kilbrew , Ashbourne , Co. Meath

407m
AA171289CONDITIONAL6 Nov 2017

the development consists of the retention of 2 no. groundwater abstraction wells; a building of 40 sqm GFA, containing a water treatment system and pumping plant; 3 no. vented storage tanks and all associated and ancillary infrastructure and site development works

Tayto Park Visitor Centre , Kilbrew , Ashbourne Co. Meath

Affected by this application?

Submissions can be made for 5 weeks from the date the application was received. Only material planning grounds count. Build a valid submission letter in minutes.

Make a Submission or Objection

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?