ED13/0036
Withdraw the ApplicationDublin - South Dublin County Council
Proposed Development
The use of the site and all buildings and structures thereon for the purposes of storage, display and selling of accident damaged vehicles, including an ancillary element of servicing by means of de-pollution of such vehicles, and the delivery or collection therof by customers who have purchased such vehicles. The proposed use is consistent with the existant permission and established use of the site and is not a material change of use and therefore is not a development which rquires planning permission.
View the full application file on the council's planning portal →Application Timeline
Application received
12 Sept 2013
Decision: Withdraw the Application
2 Oct 2013
Decision due
9 Oct 2013
Application Details
- Location
- Kingswood Road, Brownsbarn, Dublin 22
- Applicant
- N/A
- Application Type
- Declaration of Exemption Sect. 5
- Planning Authority
- South Dublin County Council
- Site Area
- 78.1411539788443 ha
Timeline
- Registration Date
- 12 September 2013
- Status
- Decision
- Decision
- Withdraw the Application
- Decision Date
- 2 October 2013
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Two storey and a single storey structure for the provision of plant, fuel storage and the construction of an ESB sub station adjacent to the existing Industrial Unit, Citywest Business Park, Naas Road, Dublin 24 to include modifications to the existing service area and the installation of vehicle barriers.
Citywest Business Park, Naas Road, Dublin 24
Erection of two surface mounted external signs
Unit 4058, Citywest Campus, Brownsbarn, Naas Rd., Dublin 24.
Erection of two-storey head office and light industrial facility and associated site development works with access from new interchange on Naas Road, Brownsbarn, Dublin 24 at Citywest Campus.
Naas Road, Brownsbarn, Dublin 24.
Installation of a rooftop solar photovoltaic system on the roof of the existing building within the FAAC Electronics Limited premises. The development will have an approximate capacity of 307.2 kWp, comprising approximately 640 photovoltaic panels, within a site application area of approximately 0.669 hectares, together with associated mounting systems, electrical cabling, connection to the existing on-site electrical infrastructure, ancillary electrical equipment and all associated site development works. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413), and it is important to note that the planning application may be subject to Section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with Section 34D(b), the provisions of Article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.
4055, Kingswood Avenue, Citywest Business Campus, Dublin 24, D24 HX79
New production/warehouse space, ancillary offices, ESB substation, associated car parking and site development works.
Site 4055, Kingswood Avenue, Citywest Business Campus, Dublin 24.
Advance facility including two storey offices for industrial and related uses, ESB Sub-station and associated site development works with access from new interchange on Naas Road at Citywest Campus.
Citywest Business Campus, Brownsbarn, Naas Road, Dublin 24.
A 659sq. m warehouse extension with associated site works.
Unit 4048, Kingswood Avenue, Citywest Business Park, Dublin 24
A 659 sq. m warehouse extension with associated site works
Unit 4048, Kingswood Avenue, Citywest Business Park, Dublin 24
Construction of a new showroom, warehouse / production space, ancillary offices, associated car parking and site development works.
Site 4048 Citywest Business Campus, Brownsbarn, Naas Road, Dulin 24.
Industrial unit consisting of a single storey (including part mezzanine level) distribution warehouse (16,413sq.m.) along with a 3 storey component catering for office use (4,282sq.m.). The height of the proposed development is 115.115mOD to parapet of warehouse component, with a projecting louvre over warehouse at 116.4mOD, and 114.2mOD to parapet of office component. There are 2 no. projecting stairwells and a plant room attached to the office element with a parapet level of 115.75mOD. Vehicular access to the site will be at the existing Kingswood Road roundabout with a secondary vehicular access point onto Kingswood Road at the north-east corner of the development site. The proposed development also includes for 6 no. depressed loading docks, on-grade personnel and vehicular access doors, external sprinkler tank and pump house with 2 no. external compactors, a bank of external AC chillers, single storey security hut (6sq.m.) at vehicular entrance to the development at the Kingswood Road roundabout, all necessary access roads, service yards, landscaping, surface water attenuation, car parking, all associated site development and infrastructural works and utilities all on a site area of approx. 4.83ha.
Kingswood Road, Citywest Business Campus, Naas Road, Dublin 24.