ED19/0011
Declared ExemptDublin - South Dublin County Council
Proposed Development
Thermal upgrade, window change,external wall finishes change, insertion of roller shutter doors & associated works.
View the full application file on the council's planning portal →Application Timeline
Application received
25 Apr 2019
Decision due
22 May 2019
Decision: Declared Exempt
22 May 2019
Application Details
- Location
- JFK Industrial Estate, Bluebell, Dublin 12
- Applicant
- N/A
- Application Type
- Declaration of Exemption Sect. 5
- Planning Authority
- South Dublin County Council
- Site Area
- 78.1411539786961 ha
Timeline
- Registration Date
- 25 April 2019
- Status
- Decision
- Decision
- Declared Exempt
- Decision Date
- 22 May 2019
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The proposed BOC operation would comprise internal/ external storage and distribution of BOC Gases products. In addition, an element of direct retail/ trade sales would be conducted using the existing trade counter.
Unit 10, John F. Kennedy Drive, John F. Kennedy Industrial Estate, Dublin 12
Change of use of land and building to allow for the storage (internal and external), distribution and direct trade/retail sale of gas and gear products; customer engineering services workshop; new roller shutter on rear elevation; new window and door security shutters; new vehicle gates; new security screens along existing southern boundary fencing; new 63sq.m single storey external storage container; external open storage areas; vehicular parking and all associated works.
Unit 10, John F. Kennedy Drive, John F. Kennedy Industrial Estate, Dublin 12
Extending existing enclosed yard by providing a gate at existing vehicular entrance at JFK Avenue, replacing part of existing low boundary wall with new low wall and fence along JFK avenue, and along adjoining property, revising existing parking layout and providing 10 additional car spaces.
Unit 10, John F. Kennedy Drive, Naas Road, Dublin 12.
Removal of an existing totem signage pole and installation of a new three-sided, 3.34 metre tall, partially internally illuminated totem sign. Five non-illuminated new fascia signs on the south elevation of Unit 10 and all associated works.
Unit 10, John F Kennedy Avenue, John F Kennedy Industrial Estate, Dublin, D12 NX74
Demolition of existing single storey office building (330sq.m) attached to side and front of existing service workshop building and construction of new replacement single storey office extension (170sq.m) to side and front of existing service workshop building, construction of a new single storey service bay extension (100sq.m) to north side of existing service workshop building, recladding the front of the existing service workshop building including raising height of existing parapet, forming 1 door ope with roller shutter door and 1 fire exit door to front of existing service workshop building and forming 3 door opes with roller shutter doors and 1 fire exit door to rear of existing service workshop building, with attached illuminated building sign and ancillary site works including the relocation of existing site entrance.
Unit 10, John F. Kennedy Drive, Naas Road, Dublin 12.
Extension to industrial unit.
John F. Kennedy Drive, Naas Road, Dublin 12.
Permission is being sought for works comprising the removal and replacement of two existing underground fuel storage tanks with a new 40,000 litre underground fuel storage tank, the decommissioning of a separate existing 70,000 litre underground fuel storage tank, the installation of a new 11,000 litre Class 1 forecourt separator with coalescing filter; along with all other associated site development, enabling and drainage works; Permission is also sought to retain the existing 24-hour fuel retail card facility and associated overground Adblue fuel tank.
Unit 10, John F. Kennedy Drive, John F. Kennedy Industrial Estate, Dublin 12
1) The erection of a 2.3m high black palisade fence to the north, east and part of the west boundaries 2) Remove the foyer and rebuild a new one: a sloping roof with a height not exceeding 3380mm, a width of 3680mm, and a depth of 2630mm 3) Within the company courtyard, approximately 700 square meters of asphalt pavement is laid around the main building 4) Erecting company signage on the main building overall size 0.9m x 18.75m 5) Add 19 No. street lights within the company forecourt 6) Install two electric gates 7) Add metal lines above the roof of the main building 8) Repainting exterior wall paint 9) Replace all doors and windows of the main building, the outer frame color of doors and windows is gun grey 10) On the southeast side of the main building, establish a 4700mm wide and 3100mm high billboard.
JFK Enterprise Centre, Bluebell, Dublin 12, D12 F229.
Installation of roof mounted solar photovoltaic panels to include all ancillary works and services.
Unit 2E, John F Kennedy Avenue, John F Kennedy Industrial Estate, Dublin 12.
Proposed refurbishment and alterations of existing industrial premises to include raising and replacement of existing asbestos roofing with profiled metal roof sheeting, use of profiled metal cladding to raise sides, front and end walls and new external signage at unit 2E.
Unit 2E, John F Kennedy Avenue, John F Kennedy Industrial Estate, Dublin 12.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?