S00A/0116

Granted

Dublin - South Dublin County Council

Proposed Development

Installation of a 30,000 litre underground diesel fuel storage tank including associated pipework and concrete slab over.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    25 Feb 2000

  2. Decision due

    19 Apr 2000

  3. Decision: Grant Permission

    19 Apr 2000

  4. Grant issued

    2 Jun 2000

Application Details

Location
Parkmore Service Station, (in front of Lenwood C&C Ltd.), Longmile Road, Dublin , 12.
Applicant
N/A
Application Type
Permission
Planning Authority
South Dublin County Council
Site Area
388.846836104324 ha
Floor Area
21 sq m

Timeline

Registration Date
25 February 2000
Status
Decision
Decision
Grant Permission
Decision Date
19 April 2000
Grant Date
2 June 2000

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

21m
SD20A/0166Refused9 Jul 2020

Permission for 3 years for a temporary cafe/retail unit on a vacant plot of land on Long Mile Road. The development will consist of one converted bus two storeys in height. Related works include new paving and the construction of a new fence and gates.

Long Mile Road, Drimnagh, Dublin 12, D12Y11H

21m
SD20A/0257Refuse Permission for Retention14 Oct 2020

Retention of erection of fence and gate enclosing lands with vehicular access to the Long Mile Road.

Long Mile Road, Drimnagh, Dublin 12

22m
SD21A/0081Refuse Permission for Retention1 Apr 2021

Retention of constructed fence and boundaries and the relocation of existing access gate.

Long Mile Road, Drimnagh, Dublin 12, D12Y11H

22m
SD21A/0350Grant Permission & Grant Retention6 May 2022

Retention of constructed fence and boundaries and the relocation of existing access gate to revised location and proposed use of space as an allotment.

Long Mile Road, Drimnagh, Dublin 12

62m
S00A/0334Granted18 Sept 2000

Change of use from general showrooms, offices and warehouse to car showrooms, offices and car repair workshop with a revised front elevation.

Unit 20, Parkmore Industrial Estate, Longmile Road, Dublin 12.

86m
S00A/0049Seek Clarification of Additional Information9 Aug 2000

Additional office space at first floor and office space at second floor level within existing premises and six windows to the rear.

Unit 2, Longmile Business Centre, Longmile Road, Dublin 12.

111m
LRD25A/0002WGranted5 Jun 2025

The development will comprise the following: Demolition of existing commercial/industrial buildings on site (c.6,711 sq.m in total). Provision of a mixed use, residential and commercial/employment development (c.49,275 sq.m GFA excluding undercroft) within 4 no. blocks ranging in height from 6 to 10 storeys. The development will provide 436 no. apartments (all with individual private open spaces) consisting of: 2 no. studios, 180 no. 1-beds, 158 no. 2-beds and 96 no. 3-beds. The development will also include: internal residential amenity spaces (c.375.3 sq.m in total); community library (c.352.1 sq.m); creche (c.359.1 sq.m), and 4 no. commercial/employment units (c.1,226.6 sq.m) comprising 2 office/co-working units (c.435.8 sq.m in total), medical centre (with ancillary pharmacy)(c.674.1 sq.m) and café (c.116.7 sq.m). • Block A - 9 to 10 storeys in height and will provide 81 no. residential units. • Block B - 9 to 10 storeys in height and will provide 137 no. residential units • Block C - 8 to 10 storeys in height and will provide 85 no. residential units • Block D - 6 storeys in height and will provide 133 no. residential units. Upgrades to the western side of the Parkmore Estate Road and along the Long Mile Road and Robinhood Road to provide a variety of pedestrian/ cyclist access points to the development and with vehicular access provided from the Estate Road with associated upgrades to the Estate entrance. The development will also include 173 no. car parking spaces within 2 no. undercroft car parks on site and including 12 no. parking spaces (for the commercial units) along the Long Mile Road frontage. Provision of 1,040 cycle parking spaces. Provision of public and communal open spaces, landscaping, boundary treatments, plant areas, waste management areas, and services provision (including ESB substations), and all associated works required to enable this development including connection to the Uisce Eireann network. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development.

Units 16-21A-B, Parkmore Industrial Estate, Longmile Road, Walkinstown, Dublin 12

111m
S00A/0739Granted11 Jan 2001

Improved loading and office facilities including alterations to front and rear elevations and other peripheral works

Units 18,19 Parkmore Industrial Estate, Long Mile Road, D12.

130m
SD06A/0255Granted20 Jun 2006

1st floor mezzanine extension for ancillary storage in warehouse area of existing industrial (storage/distribution) unit.

Unit 11B, Parkmore Industrial Estate, Longmile Road, Dublin 12.

142m
S02A/0116Granted27 Feb 2002

Retention of mezzanine floor.

11E Parkmore Industrial Estate, Longmile Road, Dublin 12.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?