To erect a natural gas pressure reduction station consisting of 3 no. buildings, associated pipework and fencing.

View the full application file on the council's planning portal →

Application Timeline

  1. Further information requested

    25 Nov 1999

  2. Application received

    21 Jan 2000

  3. Further information received

    21 Jan 2000

  4. Decision: Grant Permission

    14 Mar 2000

  5. Decision due

    16 Mar 2000

  6. Grant issued

    26 Apr 2000

Application Details

Location
Bord Gais Eireann, Citywest Business Campus, Naas Road, Dublin 24.
Applicant
N/A
Application Type
Permission
Planning Authority
South Dublin County Council
Site Area
7033 ha
Floor Area
94 sq m

Timeline

Registration Date
21 January 2000
Status
Decision
Decision
Grant Permission
Decision Date
14 March 2000
Grant Date
26 April 2000

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

46m
SD19A/0006Granted10 Jan 2019

Replacement of approx. 206m of existing 2.4m high chain-link fencing and installation of approx. 217m of additional fencing with 3m high security fencing, including associated access / emergency gates and all associated site works at an existing above ground Natural Gas installation.

Cheeverstown, Brownsbarn, Dublin 24

46m
SD18A/0392Invalid - Site Notice19 Nov 2018

Replacement of approximately 260m of existing 2.4m high chain-link fencing and installation of approximately 217m of additional fencing with 3m high security fencing, including associated access/emergency gates and all associated site works at an existing above ground Natural Gas Installation.

Cheeverstown, Brownsbarn, Dublin 24

64m
S00A/0853Granted11 Dec 2000

4 bedroomed terraced dwelling to the side of and within the curtilage

40 Hillcrest Lawns, Lucan, Co. Dublin.

75m
SD15A/0044Granted3 Mar 2015

Construction of 1 single storey boiler house with a floor area of 10.5sq.m; associated ground works will also be required to facilitate the works.

Brownsbarn AGI, Kingswood Avenue, Citywest Business Park, Naas Road, Dublin 24.

76m
S00A/0843Granted8 Dec 2000

Erection of 110Kv substation building, to house transformers ,associated switchgear and control equipment with separate toilet and wash hand basin, all located in a fence compound with an entrance from a new access road off Kingswood Road.

Kingswood Road,City West Business Park,Naas Road,Dublin 24.

80m
S00A/0730Granted20 Oct 2000

Construction of a mezzanine floor over the production warehouse area, amendments to facades, construction of service yard, wall and gates, plant and equipment housing, ESB switch and transformer rooms, relocation of entrance to site northwards and Signage on a site with a Notification of Decision to Grant Register Reference S00A/0357 at site

4031/33 Citywest Business Campus, Brownsbarn, Naas Road, D24

99m
SD17A/0441Granted11 Dec 2017

New secure fencing & gates to perimeter of the site plus internal alterations to car park & service road plus associated site development works. All of the above on a site of 1.89HA.

4033, Citywest Avenue, Citywest Business Park, Dublin 24

99m
SD18A/0253Granted16 Jul 2018

New external plant and equipment zone to the side of the existing building & include some louvre screening plus associated site development works, all on a site of 1.892Ha.

4033, Citywest Avenue, Citywest Business Park, Dublin 24

102m
SD14A/0182Granted28 Aug 2014

Construction of 3 no. single storey Boiler Houses; Boiler House no. 1 has a floor area of 50sq.m; Boiler House no. 2 has a floor area of 50sq.m; Boiler House no. 3 has a floor area of 10.5sq.m; associated ground works will also be required to facilitate the works.

Brownsbarn AGI, Kingswood Avenue, Citywest Business Park, Naas Road, Dublin 24.

106m
SD22A/0013Granted24 Mar 2022

The installation of an energy storage unit at an existing data centre facility. The development involves the placement of three ISO 40ft. shipping containers containing back up storage units at Keppel Data Centre, Citywest Avenue, Citywest Business Park, Dublin 24

4033, Citywest Avenue, Citywest Business Park, Dublin 24

Planning a project of your own?