Proposed Development
Provision of roads and services infrastructure to facilitate the future development of a business park, to be known as 'Profile Park' on these lands. The development includes the provision of 1,675 metres of internal distributor roads consisting of 267 metres to dual carriageway standard (at the main entrance) with a further 1,408 metres to single carriageway standard and one internal roundabout. The development also includes surface water drainage, foul drainage and water supply infrastructure, associated landscaping and all ancillary works, on a site of 39.84 hectares. Access to the site will be provided at the northern boundary off the existing roundabout to Kilcarbery Business Park. This application is accompanied by an Environmental Impact Statement.
View the full application file on the council's planning portal →Application Timeline
Further information requested
28 Aug 2006
Application received
3 Nov 2006
Further information received
3 Nov 2006
Decision due
30 Nov 2006
Decision: Grant Permission
30 Nov 2006
Grant issued
19 Jan 2007
Application Details
- Location
- Nangor Road, Ballybane, Clondalkin, Dublin 22.
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- South Dublin County Council
- Site Area
- 39.84 ha
Timeline
- Registration Date
- 3 November 2006
- Status
- Officer Allocation
- Decision
- Grant Permission
- Decision Date
- 30 November 2006
- Grant Date
- 19 January 2007
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Provision of roads and services infrastructure to facilitate the future development of a business park, to be known as 'Profile Park' on these lands. The development includes the provision of 1,675 metres of internal distributor roads consisting of 267 metres to dual carriageway standard (at the main entrance) with a further 1,408 metres to single carriageway standard and one internal roundabout. The development also includes surface water drainage, foul drainage and water supply infrastructure, associated landscaping and all ancillary works, on a site of 39.84 hectares. Access to the site will be provided at the northern boundary off the existing roundabout to Kilcarbery Business Park. This application is accompanied by an Environmental Impact Statement.
Nangor Road, Ballybane, Clondalkin, Dublin 22.
A 'Trade Park' consisting of 35 units in 5 separate blocks and a single office/showroom building (5 units). The units range in scale from 171 sqm (gross floor area) to 1,519 sqm (gross floor area) with a total gross floor of approx. 10,998 sqm, and 336 no. parking spaces. Each trade park unit (in Blocks B to F) shall be for trade park use only comprising storage/enterprise/workshop use and customer service/showroom/sales space for both trade and public customers. Block A (804 sqm) is a signature two storey building comprising of 4 no. units for office and showroom use and a coffee shop of approx. 120 sqm (in Unit 2); Block B (2,130 sqm) is a double height single storey building (including 534 sqm at mezzanine level) comprises of 9 no. units for trade park use; Block C (2,130 sqm) is a double height single storey building (including 534 sqm at mezzanine level) comprises of 9 no. units for trade park use; Block D (1,519 sqm) is a double height single storey unit for trade park use with single storey element to North elevation; Block E (3,195 sqm) is a double height single storey building (including 795 sqm at mezzanine level) and comprises of 15 no. units for trade park use; Block F (1,519 sqm) is a double height single storey unit for trade park use with single storey element to North elevation. The development also includes surface water drainage, 3 no. ESB substations, foul drainage and water supply infrastructure, yard areas, associated landscaping and all ancillary works, on a site of approx 3.54 hectares. Access to the site will be provided from the Northern boundary off the existing roundabout to Kilcarbery Business Park, via the internal road network permitted under Reg. Ref. SD06A/0568.
Profile Park, Nangor Road, Ballybane, Dublin 22
1 no detached logistics / distribution warehouse unit with ancillary offices (total floor area c.1842 m.sq.m) and associated site works including storm - water , attenuation, water services and boundary fencing
Profile Park, Nangor Road, Ballybane, Clondalkin, Dublin 22
Amendments to a development granted permission under Reg. Ref. SD21A/0167 for a gas fired power plant in Profile Park, Baldonnel. Permission is sought for revisions to the permitted Above Ground Infrastructure (AGI), associated with Gas Network Ireland’s high-pressure gas supply to the power plant which include: • the provision of an E & I kiosk, a regulators & meters kiosk, a gas analyser kiosk, and revisions to the boiler house kiosk with boiler flues. • the provision of a new stormwater attenuation design to serve the AGI compound; • minor revisions to the permitted internal road to serve the AGI; • minor revisions to the permitted fencing surrounding the Gas Pressure Reduction Skid located to the north of the proposed AGI; and • all associated and ancillary works. No changes are proposed to the gas fired power plant or to the site access permitted under Reg. Ref. SD21A/0167. The development permitted under Reg. Ref. SD21A/0167 includes activities which are subject to an Industrial Emissions Licence (Ref Number P1196-01).
Profile Park, Baldonnell, Dublin 22, D22 C7W4
Construction of a gas fired power plant with an electrical output of up to 125MW with associated balance of plant, equipment and buildings including; an Engine Hall building with a height of 18.9m, comprising 6 gas engines and ancillary infrastructure; an Electrical Annex Building with a height of 18.7m; a Workshop building with a height of 5. 1m; a Tank Farm building with a height of 5.68m; a Security hut with a height of 3.27m; an Exhaust Stack with a height of 31.8m; a Gas AGI including a kiosk with height of 3.3m; Radiator Coolers with a height of 8.46m; 2 electrical transformers with a height of 4.98m; Tanks including 2 x Diesel Oil Storage Tanks (volume of 2500m3 combined); SCR Urea Tank (26m3); Lube Oil Storage Tank (26m3); Lube Oil Maintenance Tank (26m3); Pilot Oil Tank (26m3); Fire Water Storage Tank (1000m3); Effluent Collecting Tank (26m3); Underground Surface Water Attenuation Tank (490m3); 2 new access onto the existing private road network with Profile Park; 12 parking spaces, footpaths, landscaping; fencing and all other associated site development plant and equipment and other works including surface water and foul wastewater drainage. An EIAR was submitted with this application.
Profile Park, Baldonnel, Dublin 22
New 8m diameter sprinkler tank (8.5m in height) and pump house (floor area 30sq.m) to the rear of existing semi detached warehouse unit and associated site works on prviously approved development Reg. Ref. SD08A/0052 on a 0.45 Ha site.
Profile Park, Nangor Road, Ballybane, Dublin 22
We, Vantage Data Centers DUB11 Ltd. are applying for permission for development at this site on lands to the south of the New Nangor Road (R134), Dublin 22; and on land within the townland of Ballybane within Profile Park, Clondalkin, Dublin 22. The development will consist of an amendment and modification of the permitted Gas Networks Ireland (GNI compound that was granted as part of, and under SDCC Planning Ref. SD21A/0241 that will include: - Replacement of the permitted vehicular access to the GNI compound from within the data centre campus to being directly off Legacy Drive that will include a modified internal access road; - New internal layout of the GNI compound that will include the replacement of the permitted boiler kiosk (42sqm), skid kiosk (89sqm) and analyser kiosk (3sqm); with a single storey boiler house kiosk (19.7sqm); single storey regulators / meters kiosk (36.8sqm); single storey electrical kiosk (14.6sqm); as well as all associated infrastructure and ancillary works; and - 3 no. floodlighting columns (each 8.537m in height) within the GNI compound that will be surrounded by a 3m high fence and vehicle gates.
Lands south of the New Nangor Road (R134), Profile Park, Dublin 22
Revisions and alterations of the permitted development of a data processing facility under planning Ref: SD12A/0002 on a 3.85 hectare site. The revised application consists of alterations to the DUB14 (previously DUB12) data centre/warehouse structure, granted in the previous application. The alterations to the DUB14 (Previously DUB12) include: (i) 2 data halls 2137 sq.m (increase of 180sq.m), (ii) offices/reception 478sq.m (decrease of 190 sq.m), (iii) support space/staff facilities and internal plant with a floor area of 953sq.m (increase of 84sq.m), (iv) external plant of 1,777sq.m (footprint increase of 35sq.m). The data centre part of the building is single storey reaching a maximum of 8.6 m in height. The plant area is to a maximum of 10.5m high and the office building has been lowered one storey and is 9.1m in height (decrease from 12.3m). The development will be constructed in 5 phases, currently Phases 1 & 2 have been completed with the enabling site works and 2 substations and single warehouse building to the North of the site. The subsequent phases will contain a single warehouse building starting with Phase 3, the application in which this Site Notice relates. A total of 84 (60 at the end of Phase 3) car parking spaces will be provided together with recycling storage and all ancillary services and landscaping. There will be 2 site entrances from vehicular accesses permitted as part of business park infrastructure (SD06A/0568).
Profile Park, Baldonnell, Dublin 22, D22 TY06
Revisions and alterations to the permitted development of a data processing facility under planning reference SD11A/0023 consisting on minor alterations to the four permitted data centre/warehouse structures, additional internal floor areas, alterations to sub-station structures and car park layout to be provided on a phased basis (it is proposed to extend the life of the planning permission to 7 years). The construction of the four data centre/warehouse buildings totals 23278 sq.m. (an increase of 2188sq.m.) and associated site works comprising the following areas: Two Type 'A' buildings each with 1872sq.m. of data halls, 697sq.m. of offices/recption, 1934sq.m. of support space/staff facilities/internal plant giving each a total internal floor area of 4503sq.m. (previously 3582sq.m.) and 1483sq.m. of external plant - total area for both Type 'A' is 11972sq.m. (previously 11094sq.m.); Two Type 'B' buildings each with 1872sq.m. of data halls, 419sq.m. (previously 67sq.m.) of offices/reception; 1879sq.m. support space/staff facilities/internal plant giving a total internal floor area of 4170sq.m. (previously 3005sq.m.) and 1483sq.m. of external plant - total area for both Type 'B' structures is 11306sq.m. (previously 9996sq.m.) The Data Centre part of the building is single storey reacing a maximum of 8.6m in height; the plant area is to a maximum of 10.7m high (increase from 9m) and th etallest building is Type 'A' office building is 12.5m in height (increase from 10m). 4 substations accessed from the estate road to facilitate the development are now proposed; each has an area of 49sq.m. and will be 3.75 metres in height. The development will be constructed in 5 phases initially with the enabling site works and 2 substations; the subsequent phases will contain a single warehouse building starting with the northern-most building. A total of 84 car parking spaces will be provided together with recycling storage and all ancillary services and landscaping. There will be 2 site entrances from vehicular accesses permitted as part of business park infrastructure (SD06A/0568).
Profile Park, Nangor Road, Clondalkin, Dublin 22
Development of a data processing facility on a 4.04ha site consisting of: the construction of four buildings totalling 21090sq.m. and associated site works comprising the following: two 'Type A' buildings each with a data hall (1870sq.m.), offices/reception (607sq.m.), support space/staff facilities and internal plant with a floor area of 3572sq.m. each and external plant 1975sq.m. each (total 'Type A' structures is 11094sq.m.); two 'Type B' buildings each with a data hall (1870sq.m.), reception (67sq.m.), support space/staff facilities and internal plant with a floor area of 3005sq.m. each and external plant of 1993sq.m. each (total Type B structures is 9996sq.m.). The Data Centre part is single storey reaching a maximum of 8.2 metres in height; the plant area is to a maximum of 9.2 metres and the office block is 10 metres in height. A substation to facilitate the development is also proposed with 16sq.m. area and will be 2.6 metres in height. The development will be constructed in two phases with building No.s 3. and 4 built initially. 84 car parking spaces will be provided together with recycling storage. There will be 2 site entrances from the existing crossovers already established as part of business park infrastructure. Surface and foul drainage has been designed to utilize existing sewer system and all retention of surface water and drainage will be in accordance with the agreed design criteria. Lighting and landscaping have been designed with the approved masterplan and site owners.
Profile Park, Nangor Road, Clondalkin, Dublin 22