SD07A/0665
GrantedDublin - South Dublin County Council
Proposed Development
A 'Trade Park' consisting of 35 units in 5 separate blocks and a single office/showroom building (5 units). The units range in scale from 171 sqm (gross floor area) to 1,519 sqm (gross floor area) with a total gross floor of approx. 10,998 sqm, and 336 no. parking spaces. Each trade park unit (in Blocks B to F) shall be for trade park use only comprising storage/enterprise/workshop use and customer service/showroom/sales space for both trade and public customers. Block A (804 sqm) is a signature two storey building comprising of 4 no. units for office and showroom use and a coffee shop of approx. 120 sqm (in Unit 2); Block B (2,130 sqm) is a double height single storey building (including 534 sqm at mezzanine level) comprises of 9 no. units for trade park use; Block C (2,130 sqm) is a double height single storey building (including 534 sqm at mezzanine level) comprises of 9 no. units for trade park use; Block D (1,519 sqm) is a double height single storey unit for trade park use with single storey element to North elevation; Block E (3,195 sqm) is a double height single storey building (including 795 sqm at mezzanine level) and comprises of 15 no. units for trade park use; Block F (1,519 sqm) is a double height single storey unit for trade park use with single storey element to North elevation. The development also includes surface water drainage, 3 no. ESB substations, foul drainage and water supply infrastructure, yard areas, associated landscaping and all ancillary works, on a site of approx 3.54 hectares. Access to the site will be provided from the Northern boundary off the existing roundabout to Kilcarbery Business Park, via the internal road network permitted under Reg. Ref. SD06A/0568.
View the full application file on the council's planning portal →Application Timeline
Application received
15 Aug 2007
Decision due
9 Oct 2007
Decision: Grant Permission
9 Oct 2007
Grant issued
20 Nov 2007
Application Details
- Location
- Profile Park, Nangor Road, Ballybane, Dublin 22
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- South Dublin County Council
- Site Area
- 35400 ha
- Floor Area
- 10998 sq m
Timeline
- Registration Date
- 15 August 2007
- Status
- Officer Allocation
- Decision
- Grant Permission
- Decision Date
- 9 October 2007
- Grant Date
- 20 November 2007
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Amendments to a development granted permission under Reg. Ref. SD21A/0167 for a gas fired power plant in Profile Park, Baldonnel. Permission is sought for revisions to the permitted Above Ground Infrastructure (AGI), associated with Gas Network Ireland’s high-pressure gas supply to the power plant which include: • the provision of an E & I kiosk, a regulators & meters kiosk, a gas analyser kiosk, and revisions to the boiler house kiosk with boiler flues. • the provision of a new stormwater attenuation design to serve the AGI compound; • minor revisions to the permitted internal road to serve the AGI; • minor revisions to the permitted fencing surrounding the Gas Pressure Reduction Skid located to the north of the proposed AGI; and • all associated and ancillary works. No changes are proposed to the gas fired power plant or to the site access permitted under Reg. Ref. SD21A/0167. The development permitted under Reg. Ref. SD21A/0167 includes activities which are subject to an Industrial Emissions Licence (Ref Number P1196-01).
Profile Park, Baldonnell, Dublin 22, D22 C7W4
Construction of a gas fired power plant with an electrical output of up to 125MW with associated balance of plant, equipment and buildings including; an Engine Hall building with a height of 18.9m, comprising 6 gas engines and ancillary infrastructure; an Electrical Annex Building with a height of 18.7m; a Workshop building with a height of 5. 1m; a Tank Farm building with a height of 5.68m; a Security hut with a height of 3.27m; an Exhaust Stack with a height of 31.8m; a Gas AGI including a kiosk with height of 3.3m; Radiator Coolers with a height of 8.46m; 2 electrical transformers with a height of 4.98m; Tanks including 2 x Diesel Oil Storage Tanks (volume of 2500m3 combined); SCR Urea Tank (26m3); Lube Oil Storage Tank (26m3); Lube Oil Maintenance Tank (26m3); Pilot Oil Tank (26m3); Fire Water Storage Tank (1000m3); Effluent Collecting Tank (26m3); Underground Surface Water Attenuation Tank (490m3); 2 new access onto the existing private road network with Profile Park; 12 parking spaces, footpaths, landscaping; fencing and all other associated site development plant and equipment and other works including surface water and foul wastewater drainage. An EIAR was submitted with this application.
Profile Park, Baldonnel, Dublin 22
Provision of roads and services infrastructure to facilitate the future development of a business park, to be known as 'Profile Park' on these lands. The development includes the provision of 1,675 metres of internal distributor roads consisting of 267 metres to dual carriageway standard (at the main entrance) with a further 1,408 metres to single carriageway standard and one internal roundabout. The development also includes surface water drainage, foul drainage and water supply infrastructure, associated landscaping and all ancillary works, on a site of 39.84 hectares. Access to the site will be provided at the northern boundary off the existing roundabout to Kilcarbery Business Park. This application is accompanied by an Environmental Impact Statement.
Nangor Road, Ballybane, Clondalkin, Dublin 22.
Provision of roads and services infrastructure to facilitate the future development of a business park, to be known as 'Profile Park' on these lands. The development includes the provision of 1,675 metres of internal distributor roads consisting of 267 metres to dual carriageway standard (at the main entrance) with a further 1,408 metres to single carriageway standard and one internal roundabout. The development also includes surface water drainage, foul drainage and water supply infrastructure, associated landscaping and all ancillary works, on a site of 39.84 hectares. Access to the site will be provided at the northern boundary off the existing roundabout to Kilcarbery Business Park. This application is accompanied by an Environmental Impact Statement.
Nangor Road, Ballybane, Clondalkin, Dublin 22.
Five storey headquarter office building which includes four storeys of office accommodation with a gross floor area of 2657.31sq.m. over a single storey level of undercroft car parking. The development also includes two no. single storey plant rooms of 69.42sq.m. at roof level. Access to the development is proposed from the Nangor Road via the internal Spine Road within the 'Profile Park' Business Park permitted under Planning Application Reg. Ref. SD06A/0568. The development includes 60 number car parking spaces which will be provided at undercroft level and 40 no. surface car parking spaces which will be provided at podium level above. The development also includes an ESB sub-station, all ancillary services, landscaping and site works on a site of 4899 hectares.
'Profile Park', Nangor Road, Ballybane, Dublin 22
The development will consist of the development of a Regional Network Gateway (RNG) facility (supporting infrastructure for the MS data centres) comprising the following: Demolition of existing, temporary, single storey showroom. Construction of a single storey main building (RNG Building - c.1,297.7 sq.m) with air handling units (AHUs). External plant/equipment yards including 3 no. diesel generators; sprinkler tank and pump house; electrical plant rooms, PV panels. Replacement of existing estate road access with new main access and secondary/emergency access. MV substation (with separate estate road access). Stormwater attenuation pond. Bike parking shelter and bin store. 12 no. car parking spaces (4 of which are EV parking spaces and with 1 accessible parking space). Internal road and footpath layout, perimeter fencing and security gates. Landscaped and planted areas including riparian zones. All associated site development works, site lighting, boundary treatments, services/utilities provision (including underground works), and all other ancillary works. Total gross floor area of the development c.1,536.9 sq.m
Profile Park, New Nangor Road (R134), Clondalkin, Dublin 22
Construct a new access road off the Nangor Road, Clondalkin Dublin 22 as described below:- • Construction of new single and dual carriageway in 2 phases; • Construction of cycletracks and footpaths; • Provision of drainage and associated features; • Provision of public lighting and signing; • Relocation of services where necessary; • Provision of other services where necessary. Plans and particulars of the proposed development are available for inspection at:- South Dublin County Council, County Hall, Tallaght, Dublin 24, between the hours of 9:30am - 12:45pm and 2:00pm - 4:30pm Monday to Thursday and 9.00 am -4.00 pm Friday and South Dublin County Council, Civic Offices, Clondalkin, Dublin 22 between the hours of 9:30am -12:45pm and 2:00pm - 4:30pm Monday to Thursday and 9.30 am -4.00 pm Friday from Monday 16th May 2011-Monday 27th June 2011. Submissions and observations with respect to this matter, dealing with the proper planning and sustainable development of the area, in which the development would be situated, may be made in writing to: The Senior Executive Officer, Corporate Services South Dublin County Council, County Hall, Tallaght, Dublin 24 or by email to : developdept@sdublincoco.ie. Closing date for receipt of submissions is up to and including 12.00 noon on Monday 11th July, 2011.
Nangor Road, Clondakin, Dublin 22
Revisions and alterations of the permitted development of a data processing facility under planning Ref: SD12A/0002 on a 3.85 hectare site. The revised application consists of alterations to the DUB14 (previously DUB12) data centre/warehouse structure, granted in the previous application. The alterations to the DUB14 (Previously DUB12) include: (i) 2 data halls 2137 sq.m (increase of 180sq.m), (ii) offices/reception 478sq.m (decrease of 190 sq.m), (iii) support space/staff facilities and internal plant with a floor area of 953sq.m (increase of 84sq.m), (iv) external plant of 1,777sq.m (footprint increase of 35sq.m). The data centre part of the building is single storey reaching a maximum of 8.6 m in height. The plant area is to a maximum of 10.5m high and the office building has been lowered one storey and is 9.1m in height (decrease from 12.3m). The development will be constructed in 5 phases, currently Phases 1 & 2 have been completed with the enabling site works and 2 substations and single warehouse building to the North of the site. The subsequent phases will contain a single warehouse building starting with Phase 3, the application in which this Site Notice relates. A total of 84 (60 at the end of Phase 3) car parking spaces will be provided together with recycling storage and all ancillary services and landscaping. There will be 2 site entrances from vehicular accesses permitted as part of business park infrastructure (SD06A/0568).
Profile Park, Baldonnell, Dublin 22, D22 TY06
Revisions and alterations to the permitted development of a data processing facility under planning reference SD11A/0023 consisting on minor alterations to the four permitted data centre/warehouse structures, additional internal floor areas, alterations to sub-station structures and car park layout to be provided on a phased basis (it is proposed to extend the life of the planning permission to 7 years). The construction of the four data centre/warehouse buildings totals 23278 sq.m. (an increase of 2188sq.m.) and associated site works comprising the following areas: Two Type 'A' buildings each with 1872sq.m. of data halls, 697sq.m. of offices/recption, 1934sq.m. of support space/staff facilities/internal plant giving each a total internal floor area of 4503sq.m. (previously 3582sq.m.) and 1483sq.m. of external plant - total area for both Type 'A' is 11972sq.m. (previously 11094sq.m.); Two Type 'B' buildings each with 1872sq.m. of data halls, 419sq.m. (previously 67sq.m.) of offices/reception; 1879sq.m. support space/staff facilities/internal plant giving a total internal floor area of 4170sq.m. (previously 3005sq.m.) and 1483sq.m. of external plant - total area for both Type 'B' structures is 11306sq.m. (previously 9996sq.m.) The Data Centre part of the building is single storey reacing a maximum of 8.6m in height; the plant area is to a maximum of 10.7m high (increase from 9m) and th etallest building is Type 'A' office building is 12.5m in height (increase from 10m). 4 substations accessed from the estate road to facilitate the development are now proposed; each has an area of 49sq.m. and will be 3.75 metres in height. The development will be constructed in 5 phases initially with the enabling site works and 2 substations; the subsequent phases will contain a single warehouse building starting with the northern-most building. A total of 84 car parking spaces will be provided together with recycling storage and all ancillary services and landscaping. There will be 2 site entrances from vehicular accesses permitted as part of business park infrastructure (SD06A/0568).
Profile Park, Nangor Road, Clondalkin, Dublin 22
Development of a data processing facility on a 4.04ha site consisting of: the construction of four buildings totalling 21090sq.m. and associated site works comprising the following: two 'Type A' buildings each with a data hall (1870sq.m.), offices/reception (607sq.m.), support space/staff facilities and internal plant with a floor area of 3572sq.m. each and external plant 1975sq.m. each (total 'Type A' structures is 11094sq.m.); two 'Type B' buildings each with a data hall (1870sq.m.), reception (67sq.m.), support space/staff facilities and internal plant with a floor area of 3005sq.m. each and external plant of 1993sq.m. each (total Type B structures is 9996sq.m.). The Data Centre part is single storey reaching a maximum of 8.2 metres in height; the plant area is to a maximum of 9.2 metres and the office block is 10 metres in height. A substation to facilitate the development is also proposed with 16sq.m. area and will be 2.6 metres in height. The development will be constructed in two phases with building No.s 3. and 4 built initially. 84 car parking spaces will be provided together with recycling storage. There will be 2 site entrances from the existing crossovers already established as part of business park infrastructure. Surface and foul drainage has been designed to utilize existing sewer system and all retention of surface water and drainage will be in accordance with the agreed design criteria. Lighting and landscaping have been designed with the approved masterplan and site owners.
Profile Park, Nangor Road, Clondalkin, Dublin 22
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?