SD08A/0169
RefusedDublin - South Dublin County Council
Proposed Development
The demolition of an existing office block with a floor area of 2200m.sq. and the development of a mixed use development with a total gross floor area of 2979m sq. consisting two storey office space over ground floor retail development along with a refuse storage building with a floor area of 38 sq. The proposed development includes 6 no. retail units at ground floor with a total floor area of 1072m sq. and 2 floors of office space with a total area of 1640m sq. located over the retail units. The proposed development includes the relocation of the existing vehicular access along Cookstown Estate Road. The proposed Development will include site landscaping to surface carpark & ancillary site works
View the full application file on the council's planning portal →Application Timeline
Application received
12 Mar 2008
Decision due
6 May 2008
Decision: Refuse Permission
6 May 2008
Application Details
- Location
- Corner of Cookstown Estate Road, Cookstown Industrial Estate, Tallaght, Dublin 24
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- South Dublin County Council
- Site Area
- 4200 ha
- Floor Area
- 2979 sq m
Timeline
- Registration Date
- 12 March 2008
- Status
- Decision
- Decision
- Refuse Permission
- Decision Date
- 6 May 2008
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The demolition of an existing office block with a floor area of 2200sq.m and the construction of a part 4 storey mixed use development with a total gross floor area of 4642.6sq.m made up of the following; 2 no. retail units at ground floor measuring 202.6sq.m, 3 no. office units at ground floor measuring 661.1sq.m, 5 no. office units measuring 2282.8sq.m spread between first, second and penthouse levels. The proposed development also includes the relocation of the existing vehicular access along Cookstown Estate Road and site landscaping to surface carpark & ancillary site works.
Site located at Cookstown Estate Road, Cookstown, Tallaght, Dublin 24
The proposed change of use of an existing commercial storage building into Accommodation for use under SI 605 for International Protection Applicants
Unit 81, Cookstown Estate Road, Cookstown Industrial Estate, South Dublin, D24 WVT4
Mixed use development broken into 4 no. buildings totalling c. 31950.1sq.m. consisting of 217 no. apartment units, retail floor space totalling 3409.5sq.m., office floor space totalling 6939sq.m., a creche, community meeting room and two basement levels providing for 860 car-parking and 322 bicycle spaces. Building 1 consists of a 5 storey mixed use building broken down as follows: 6 no. convenience retail units at ground floor with a gross floor area of 1340sq.m., 1 no. community meeting room at ground floor level with a gross floor area of 34.2sq.m., 1 no. creche with a gross floor area of 387sq.m., 89 apartments over 5 storeys made up of 24 no. 1 bedroom apartments, 54 no. 2 bedroom apartments and 11 no. 3 bedrooms; 6 storey corner office suite with a gross floor area 2658.5sq.m: Building 1 will have a maximum height of 25.5m, vehicular access will be via a new road constructed off Cookstown Estate Road. Building 2 consists of a 5 storey mixed use building broken down as follows: 6 no. retail units at ground floor level with a total gross floor area of 1048sq.m., 1 no. community meeting room at ground floor level with a gross floor area of 26.2sq.m., 47 apartments over 5 storeys made up of 14 no. 1 bedroom, 26 no. 2 bedroom and 7 no. 3 bedroom apartments, 5 no. storey office suite with a gross floor area of 1359sq.m: Building 2 will have a maximum height of 21.5m, vehicular access will be via Cookstown Estate Road. Building 3 consists of a 5 storey residential building made up of 1 no. retail unit at ground floor area with a gross floor area of 136sq.m., 1 no. community meeting room at ground floor area with a gross floor area of 45.2sq.m., 81 apartments over 5 storeys made up of 19 no. 1 bedroom, 46 no. 2 bedroom and 16 no. 3 bedroom apartments; Building 3 will have a maximum height of 19m; vehicular access will be via Cookstown Estate Road. Building 4 consists of a 4 storey office/retail building broken down as follows: 3 no. retail units at ground floor level with a gross floor area of 885.5sq.m., 4 no. storey office suite with a gross floor area of 3346.4sq.m; Building 4 will have a maximum height of 20m, vehicular access will be via a new road constructed off Cookstown Estate Road. Public open space has been designed to cpmplement the surrounding buildings and to provide an aesthetically pleasing and peaceful environment for both private residences and the general public to enjoy and will measure 5269sq.m. The proposed development will include landscaping and ancillary site works and will also consist of the demolition of 5 no. existing industrial units totalling 10117sq.m. This application is accompanied by an Environmental Impact Statement.
Site Located at Cookstown Estate Road, Cookstown, Tallaght, Dublin 24.
Change of use, and associated internal works, of part of the existing building (167 sq.m. approx.) from warehouse to part workshop/light industrial (89 sq.m. approx.) and part water sampling hub (78 sq.m. approx.) to facilitate the overall use of the building as an Uisce Éireann Operations Centre; the provision of a window and security shutter on the north eastern façade of the building; the provision of a wash bay and 4 No. materials bunkers in external yard area; 2 No. replacement vehicular gates; a new pedestrian gate; Uisce Éireann signage on front (southwest) elevation; external air handling unit on northwestern side of building; and associated site development and drainage works.
Unit 81 A&B, Cookstown Estate Road, Cookstown Industrial Estate, Tallaght, Dublin 24, D24 YC0F
Alterations and extensions to their existing premises to include replacing and extending the original Warehouse by 90 sq. metres and increasing the eaves heights from 4.5 metres to 9.7 metres, together with a new facade and first floor extension of 24 sq. metres to the existing two-storey Office area, in addition to general internal mezzanine extensions to 70 sq. metes.
Hilary House, Cookstown Industrial Estate, Tallaght, Dublin 24.
Erection of 4.19sq.m. sheet metal signage fixed to south, east and west face of existing 3.975m high 'totem' style concrete structure in south west corner of site; erection of 15.71sq.m. sheet metal signage fixed to existing 5.1m high 'goal post' style structure abutting south east (front) corner of existing building; erection of 18m long x 3m high (54sq.m.) pvc 'banner' style signage fixed to rear (north facing) wall of building; erection of new 1.25m x 1.25m x 3.975m high steel advertising structure in south east corner of site with associated 5.34sq.m. sheet metal signage fixed to south, east and west face of structure.
Unit 5, Cookstown Estate Road, Cookstown Industrial Estate, Tallaght, Dublin 24.
(i) Demolition of the existing industrial and commercial buildings (15,989sq.m); (ii) construction of a mixed-use development featuring: (a) 1104 'build-to-rent' apartments in 4 blocks varying in height from four to eleven storeys. Each apartment has associated private open space in the form of a ground floor terrace or a balcony and has access to internal communal amenity spaces (totalling 2741sqm) and 5,107sqm of external communal amenity space at ground, first floor and roof levels; and (b) 4 commercial units at ground floor level of Blocks B and D (comprising of 2 in Block B accommodating a cafe/restaurant/bar; 1 in Block D accommodating Class 1, 2 and 8 uses as per the Planning and Development Regulations, 2001-2019, as amended; and 1 in Block D to serve the Circle K Belgard petrol station which is to be retained), 1,500sqm of office space across first to sixth floor levels of Block D and a crèche with external play area at ground floor level of Block C. The development is served by a total of 351 parking spaces (including 17 limited mobility parking spaces and 16 car share spaces) and 1860 bicycle spaces (1464 resident spaces and 396 visitor spaces); (iii) road, junction and streetscape upgrade works along First Avenue, Cookstown Road and Old Belgard Road, including the installation a signalised junction at the intersection of First Avenue and Cookstown Road and Old Belgard Road and Cookstown Road; (iv) construction of 3 new roads and 1 pedestrian/cycle link to the Belgard Luas Stop; (v) construction of a 1,688sqm landscaped public plaza with an outdoor flexible events space in the south-western corner of the site; and (vi) associated site and infrastructural works are also proposed which include: foul and surface water drainage; attenuation tanks; lighting; landscaping; boundary fences; plant areas; ESB substations; internal hard landscaping, including footpaths and street furniture; and all associated site development works. Any person may, within the period of 5 weeks beginning on the date of receipt by An Bord Pleanála of the application and on payment of the prescribed fee of €20 (except for certain prescribed bodies), make a submission or observations in writing to An Bord Pleanála, 64 Marlborough Street, Dublin 1 or online at www.pleanala.ie. Any enquiries relating to the application process should be directed to the Strategic Housing Development Section of An Bord Pleanála (Tel. 01-8588100).
Lands to the west of Old Belgard Road and north, south and west of Cookstown Road, Cookstown Industrial Estate, Dublin 24
Change of use from light industrial to indoor gymnastics sports facility with internal amendments and all associated site works.
Unit 1C, Cookstown Industiral Estate, Tallaght, Dublin 24
Demolition of all existing 1-3 storey industrial/commercial structures and small cafe on site totalling c.5,500sq.m in area; Construction of a 1-5 storey Transitional Care Facility (step-up/step-down) providing 131 bedspaces over partial basement (total floor area c.6,743sq.m) with central courtyard ( c.519sq.m ); The basement consists of a sprinkler tank and pump rooms, water tank room, plant room and workshop; Provision of dining and kitchen areas, siting/family rooms, activity rooms, coffee dock, hair salon, oratory, lobbies/reception areas, ancillary offices and staff areas, stores, toilets, shower/changing facilities, ESB substation, generator, switchroom, service yard and waste areas serving the facility; Lobbies, stair/lifts, photovoltaic panels and green roofs throughout; Partial provision of the pocket park identified in the Tallaght LAP (c.1,286sqm); New vehicular access from First Avenue and egress onto Cookstown Road via a one-way system through the subject site; Entrance signage on the eastern elevation of the proposed facility; All associated site development works, services provision, connection to the water supply, foul and surface water networks on First A venue and Cookstown Road including partial diversion of the foul line to the north east of the site at First A venue, temporary foul pump station, attenuation/bioretention systems, vehicular and pedestrian access including internal road and footpaths, interim pedestrian facilities/public realm upgrade works, landscape and boundary treatment works, tree removal, bicycle storage (76 total spaces), car parking (32 total spaces), set-down parking spaces, 1 ambulance set-down space serving the facility and delivery/loading areas to First A venue.
Unit 21, First Avenue, Cookstown Industrial Estate, Dublin 24
Demolition of all existing 1-3 storey industrial / commercial structures and small café on site totalling c.5,500sqm in area; - Construction of a deck-access apartment development comprising 123 residential units arranged in 2 no. blocks (Block A 5 to 7 storeys and Block B 5 to 6 storeys) with a total floor area of c.9,806sqm including the proposed bike shelter (c.93sqm) and excluding deck access (c.901sqm); -Commercial floor space located at ground floor level facing Cookstown Road in Residential Block A (c.421sq.m); - The residential development consists of 58 no. 1 bed/2 person units, 12 no. 2 bed/3 person units and 53 no. 2 bed/4 person units with north, south, east and west facing balconies throughout and residents amenity area at ground floor level; -Central communal open space (c.1,303sq.m); -Provision of an ESB substation, switchboards, waste areas, water tanks and generator serving Blocks A and B; -Lobbies, stair/lifts, photovoltaic panels and green roofs throughout; -Partial provision of the pocket park identified in the Tallaght LAP (c.1,286sq.m); -New vehicular access from First Avenue and egress onto Cookstown Road via a one way system through the subject site; -All associated site development works, services provision, connection to the water supply, foul and surface water networks on First Avenue and Cookstown Road including partial diversion of the foul line to the north east of the site at First Avenue, temporary foul pump station. attenuation/bioretention systems, vehicular and pedestrian access including internal road and footpaths, pedestrian facilities/public realm upgrade works, landscape and boundary treatment works, tree removal, bicycle storage (302 no. total spaces) comprising 276 no. spaces (serving proposed mixed use development) and 26 no. spaces (serving concurrent transitional care facility application), car parking (32 no. total spaces) comprising 15 no. spaces (serving proposed mixed use development) and 17 no. spaces (serving concurrent transitional care facility application), 2 no loading bays (one each on First Avenue and Cookstown Road), 2 no. setdown/loading areas to the internal road and 1 no. ambulance setdown space serving the adjacent concurrent proposed Transitional Care Facility. The concurrent application has been made to South Dublin County Council regarding a 131 bed Transitional Care Facility on the western portion of the site (SDCC Ref SD22A/0361 refers) currently under appeal to An Bord Pleanála (ABP Ref 317394).
Unit 21, First Avenue, Cookstown Industrial Estate, Dublin 24
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?