SD08A/0731
GrantedDublin - South Dublin County Council
Proposed Development
Installation of an ESB 38kV Overhead Line Switching Compound at Roadstone Belgard Quarry Lands, in the part of the Quarry Lands which are located in the Townland of Cheeverstown, Barony of Upper Cross, Dublin 24. The location of the proposed Compound will be east of the recently commissioned New Outer Ring Road R136, Cheeverstown N7 to N81 and the east of the existing Screening Bund, which follows the route of the Outer Ring Road, in Belgard Quarry Lands Cheeverstown Townland, and will be adjacent to, and will be accessed from, the new Belgard Quarry entrance Road, off the above mentioned Outer Ring Road. The Compound will contain three no. 38kV 12 Metre Line Termination Masts and two no. Double Wood Portals. LBFM Switchgear will be installed at the top of the Double Wood Portals. The proposed Compund will measure 80 metres X 30 metres and will require the installation of a 2.4 metre High Palisade Fence, with gates for ESB access. The 38kV Overhead Line Switching Compound will be required to facilitate undergrounding of a section of the Grange Castle-Saggart/Tee Cheeverstown 38kV Line, while still maintaining a 38kV switching Facility for ESB Control of the circuit.
View the full application file on the council's planning portal →Application Timeline
Application received
21 Oct 2008
Decision due
15 Dec 2008
Decision: Grant Permission
15 Dec 2008
Grant issued
10 Feb 2009
Application Details
- Location
- East Of R136 Outer Ring Road, Cheeverstown N7 To N81
- Applicant
- N/A
- Application Type
- Permission
- Planning Authority
- South Dublin County Council
- Site Area
- 2400 ha
Timeline
- Registration Date
- 21 October 2008
- Status
- Decision
- Decision
- Grant Permission
- Decision Date
- 15 December 2008
- Grant Date
- 10 February 2009
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
The development of a plant for the manufacture of precast concrete products with associated offices (approximate gross floor area of 4831sq.m); batching plant incorporating cement silo and aggregate storage bins; 30 car parking spaces and associated site and landscaping works. The highest point of the development will be 17m above ground level. Access to the site will be provided from existing entrances off the Naas Road and Cookstown Road at
Fortunestown, Dublin 24.
The establishment of an asphalt plant and ancillary site facilities at the site stated above. The proposed asphalt plant has a maximum of height of 20 metres, includes a number of different components and has a total area of ca. 311.5sq.m. The proposed ancillary facilities include 4 no. portacabin site offices; a wheelwash facility, a weighbridge facility; a staff car-parking area; a hard-stand area: an ESB station, an internal road and an effluent treatment and disposal system. It is proposed to operate the asphalt plant 24 hours a day, seven days a week. Application is made operate the plant for a 30 year period
Belgard Quarry, Cheeverstown, Tallaght, Dublin 24.
Improvement of the sightlines on the northern side of the main entrance off the R136 Cheeverstown Road, including removal of a section of the existing boundary wall; construction of a new section of boundary wall (same height and materials as the existing wall); landscaping and all ancillary works within a c. 0.145 hectare application area at the existing quarry.
Cheeverstown Road, Belgard Quarry, Fortunestown, Tallaght, Dublin 24
(a) new site access onto outer ring road; (b) 850m of new internal roadway; (c) provision of office, canteen and toilet facilies (270m2); (d) provision of security hut with associated toilet facility (20m2); (e) provision of 1 no. wheelwash; (f) provision of 3 no. weighbridges; (g) provision of 1 no oil interceptor; (h) provision of septic tank and associated percolation area; (i) provision of 20 no. car parking spaces; (j) public information signage; (k) canopy over docket exit area; (l) site landscaping.
Belgard Quarry, Cheeverstown Townland, Tallaght, Dublin 24
(a) new site access onto outer ring road; (b) 850m of new internal roadway; (c) provision of office, canteen and toilet facilies (270sq.m.); (d) provision of security hut with associated toilet facility (20sq.m.); (e) provision of 1 no. wheelwash; (f) provision of 3 no. weighbridges; (g) provision of 1 no oil interceptor; (h) provision of septic tank and associated percolation area; (i) provision of 20 no. car parking spaces; (j) public information signage; (k) canopy over docket exit area; (l) site landscaping.
Belgard Quarry, Cheeverstown Townland, Tallaght, Dublin 24
To construct one 12m 38kV line termination mast. This work is required to underground a section of the Grangecastle Saggart (tee to Cheeverstown) 38kV line.
Eastern edge of proposed Outer Ring Road Extension (N7-N81) approx. 230m nth of junction with the Embankment Rd, (proposed LUAS extension), in the townland of Cheeverstown, Barony Of Newcastle, Dublin
Partial Change of use from warehouse to office use with floor area of 551sq.m; Addition of mezzanine level with a floor area of 133sq.m; Addition of staircase from warehouse to mezzanine level to include all associated site works to facilitate the development.
Unit 2B, South West Business Park, Cheeverstown, Citywest, Dublin 24
Permission for partial change of use from Warehouse to Office use at ground floor level with floor area of 297 sq.m; extension for office use at first floor level with floor area of 256 sq.m; addition of staircase from warehouse to first floor level; to include all associated site works to facilitate the development. Amendment to previously approved planning permission (Ref. No. SD22A/0465) to remove the 133 sq.m Mezzanine level in the description of the development and submitted plans and particulars at Unit 2B, South West Business Park, Cheeverstown, Citywest, Dublin 24.
Unit 2B, South West Business Park, Cheeverstown, Citywest, Dublin 24
Permission for alterations to existing building (unit 1) to the southwest elevation, namely, 2no. additional dock levellers and re-location of 1 existing roller door and all associated site works
Unit 1, South West Business Park, Cheeverstown, Dublin, D24 Y24D
Recovery of pre-sorted construction and demolition waste (namely concrete, bricks, tiles and ceramics, asphalt and topsoil) on a 3.9 hectare site within its existing landholding. Construction of an internal access road within Belgard Quarry, hardstanding area for stockpiling and waste recovery and waste inspection area (200m2). Provision is also made for portakabin office (39m2). Operations to be carried out include crushing and stockpiling of material using mobile plant.
Belgard Quarry, Cheeverstown, Co. Dublin.
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?