Proposed Development

The proposed primary school will extend to c3,355sq.m will be 2 storeys in height and will comprise 16 no. classrooms with an additional 2 classroom Special Educational Needs Unit; a General Purpose Hall and all ancillary teacher and pupil amenities and facilities. The proposed development also provides for hard and soft play areas, including 2 no. outdoor ball courts, bicycle parking, staff car parking, vehicle drop off and set down areas. Photovoltaic Panels (PV) are proposed on roofs in addition to EV Charging Points and a packaged Biomass heating plant. The proposed development also provides for all landscaping and boundary treatments and all associated site development works. Access to the site will be via a new junction and access road off Thomas Omer Way. The new access road will run south off Thomas Omer Way and then west into the site. The proposed access road Is in accordance with the Clonburris Strategic Development Zone (SDZ) Planning Scheme and incorporates public lighting, footpaths and cycle tracks. A further pedestrian / cycle only connection to Thomas Omer Way ls also proposed along the western green corridor, west of the proposed school building.

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    20 Jan 2023

  2. Decision: Grant Permission

    16 Feb 2023

  3. Grant issued

    16 Feb 2023

  4. Decision due

    17 Feb 2023

Application Details

Location
Thomas Omer Way, Balgaddy, Lucan, Dublin
Applicant
N/A
Application Type
SDZ Application
Planning Authority
South Dublin County Council
Site Area
19100 ha
Floor Area
3355 sq m

Timeline

Registration Date
20 January 2023
Status
Final Grant
Decision
Grant Permission
Decision Date
16 February 2023
Grant Date
16 February 2023
Permission Expires
15 February 2028

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

19m
SDZ24A/0032WGrant Permission & Grant Retention13 Feb 2025

The development consists of the retention and completion of revisions to a section of the northern site boundary comprising the omission of the pedestrian/cycle access (consisting of ramp and stairs) off Thomas Omer Way and the repositioning of the pedestrian access c. 6 m in an easterly direction to co-join with the permitted vehicular access. The amendments do not involve any changes to the position of the permitted vehicular access itself and the access road remains in accordance with the Clonburris Strategic Development Zone (SDZ) Planning Scheme. Permission is also sought for the relocation of bicycle parking areas within the site; revisions to the permitted boundary treatment along a section of the eastern site boundary; the installation of 3 no. flagpoles in the south-eastern part of the site; and revisions to the site compound including repositioning of bin store area and replacement of previously permitted bio-mass heating with new heat pump and gas storage tank.

Thomas Omer Way,, (east of Kishoge Community College), Balgaddy, Lucan, CO DUBLIN

87m
SDZ24A/0033WGranted6 Dec 2024

The development will consist of works located inside the Clonburris SDZ relating to the Stage 2 roads, public parks/open space areas and services infrastructure works (as part of a separate concurrent application) as per the Clonburris SDZ Planning Scheme (2019) to facilitate the future development of the northern part of the overall SDZ comprising: A) The construction of c. 2.3km of a new Link Street Clonburris Northern Link Street (CNLS) and approximately 800m of side streets including ancillary cycle facilities, pedestrian crossings, traffic signals, footpaths, car parking (79 no. spaces) public lighting as well as services infrastructure (including ESB, Comms, gas main, trunk surface water sewer, and watermain) and ancillary works. B) Provision/upgrade of 12 signalised junctions (5 new and 7 upgraded) as follows: Junction 1: R136 & Adamstown Avenue/Thomas Omer Way, Junction 3: R113 & Thomas Omer Way / Ninth Lock Road, Junction 4: CNLS & R136, Junction 6: CNLS, Junction 8: CNLS & R113, Junction 9: CNLS/Neilstown Road & Ninth Lock, Junction 24: CNLS/Neilstown Road & Ninth Lock, Junction 28: R136 & Adamstown Avenue/Thomas Omer Way, Junction 2: CNLS & Thomas Omer Way, Junction 5: CNLS, Junction 7: CNLS, Junction 27: R136 & Adamstown Avenue/Thomas Omer Way along with minor priority-controlled junctions are proposed along the street alignment to provide access to existing development and future development cells within the Clonburris SDZ. C) Approximately 2 km of upgrade of existing streets, including minor priority-controlled junctions are proposed along the street alignment to provide access to existing development and future development cells within the Clonburris SDZ, including pedestrian crossings. D) Provision of 2 main public parks centrally (Na Cluainte Park North) c. 2.78 ha and in the eastern part of the subject lands (c. 0.77 ha) both to include open water attenuation areas. E) Drainage infrastructure works to include surface water attenuation areas, Sustainable Urban Drainage Systems (SUDs) as well as landscaped areas including attenuation ponds and the provision of underground attenuation. Provision of surface water drainage and waste supply trunk infrastructure within the proposed road corridors; wastewater infrastructure including a foul pumping station (known as pumping station no.3) and foul pipe network within proposed road corridors to facilitate drainage connections to future development within the SDZ lands. The easterly section of the development will collect surface water and discharge into an existing outfall situated within Moorfield Walk whereas the western surface water catchment will connect (as part of a separate concurrent application) to an existing surface water outfall on the Griffeen Road (and ultimately to an existing Griffeen River outfall). F) Provision of trunk watermain infrastructure within the CNLS as well as connections to the permitted watermain infrastructure as part of SDZ20A/0021. G) Permission is also sought for all ancillary site development and landscape works associated with the development, including hard and soft landscaping, (tree pits, boundary treatments, road marking, signage, enabling works and temporary construction works, (including site accommodation, site compounds, and temporary construction boundary fencing) as well as temporary project signage (at 6 no. locations) and provision of underground utility connections under the Dublin - Cork Railway line (at 3 no. locations) and Irish water diversions. This application is being made in accordance with the Clonburris Strategic Development Zone Planning Scheme 2019 and relates to a proposed development within the Clonburris Strategic Development Planning Scheme Area, as defined by Statutory Instrument No. 604 of 2015.

Within the townlands of Kishoge, Balgaddy, Neillstown and Cappagh, Clondalkin & Lucan, Dublin 22

184m
SD198/0002Part 8 Approved by Council31 Jan 2019

Social Housing Project of 74 units and a community facility on undeveloped lands at Griffeen Avenue, situated between Foxborough Lawn and Tor an Rí Walk consisting of: 22 3-Bedroom houses, 4 person, 2 storey; 4 3-Bedroom houses, 5 person, 2 storey; 21 3-Bedroom houses, 5 person, 2 storey; 9 1-Bedroom Ground Floor Apartments; 9 3-bedroom, Duplex units, 2 Storey (1st and 2nd Floor); 9 Apartments - 2 Bedroom, 3 Person, 3 storey; Community Facility. The works include: New access off Tor an Rí, landscaping works to boundaries and new park/play area, ancillary works to landscape housing areas, and all necessary associated ancillary works on the site and adjacent areas. All units to be minimum A2 BER rated. The housing provision includes ground floor, two/three storey units grouped in terraces. Plans and particulars of the proposed scheme will be available for inspection or purchased at a fee not exceeding the reasonable cost of making a copy for a period of four weeks from Thursday, 31st January 2019 during the public opening hours at the offices of South Dublin County Council, County Hall, Tallaght, Dublin 24. Submissions or observations in relation to the proposed development, dealing with the proper planning and sustainable development of the area in which the development would be situated, may be made as follows: online at https://consult.sdublincoco.ie up to midnight on Thursday, 14th March 2019 or written submissions not later than 5.00pm Thursday, 14th March 2019. Please address your submission to: Senior Executive Officer, Housing Department, South Dublin County Council, County Hall, Tallaght, Dublin 24 (NOTE: Please make your submission by one medium only). Only submissions received by Thursday, 14th March 2019 and addressed as set out above, will be considered. Submissions cannot be accepted in any other format or to any other postal address. Submissions and observations should state the name, address, and, where relevant, details of any organisation, community group or company etc. which you represent.

Griffeen Avenue, Balgaddy, Lucan, Co. Dublin

220m
SD02A/0575Refused3 Oct 2002

Detached dwelling with garage/store on ground floor and Granny Flat on first floor at side.

14, Foxborough Grove, Lucan, Co. Dublin

222m
SD04A/0044Refused23 Jan 2004

2 storey detached 3-bedroom house and associated site works including new access and driveway in existing side garden.

Side Garden, 14, Foxborough Grove, Lucan, Dublin

235m
SD20A/0109Granted7 May 2020

2 storey modular classroom building and a single storey toilet building, steel framed covered walkway structure linking to the existing school, relocation of existing bicycle shelters and all associated site development works.

Kishoge Community College, Thomas Omer Way, Lucan, Co. Dublin

240m
S02A/0150Granted8 Mar 2002

3 bedroomed detached house on land to the side.

13 Foxborough Grove, Lucan, Co. Dublin.

240m
S01A/0549Refused20 Aug 2001

2 no. townhouses (2 storey) on land to the side.

13 Foxborough Grove, Lucan, Co. Dublin.

257m
SD21B/0432Grant Permission & Refuse Permission25 Mar 2022

Two storey extension at side and rear and connection to the existing services thereon consisting of accommodation at the side extension and an increase in the size of kitchen and the size of two existing bedrooms at the rear extension two storey extensions at side and rear and connection to the existing services

1, Foxborough Grove, Lucan, Co. Dublin

261m
SD13A/0042Granted13 May 2013

Construction of 1 no. single storey temporary prefab school building. The school will comprise: 4 no. classrooms with ancillary office areas; playground area and boundary fencing; associated site works; 2 vehicle access points from Griffeen Avenue; on site parking spaces and drop off area on site between Tor an Ri Court and Meile an Ri Green. Significant Additional Information (revised location description) - between Lynch's Lane & Tor an Ri Walk.

Balgaddy, Lucan, Co. Dublin