IN THE TOWNLAND OF CLARA , NEAR CLARA , CO OFFALY
CONDITIONALPlanning application 18314
Offaly - Offaly County Council
Proposed Development
DEVELOPMENT OF A SOLAR FARM. THE PROPOSED SOLAR FARM WILL COMPRISE THE CONSTRUCTION AND OPERATION OF SOLAR PV ARRAYS MOUNTED ON METAL FRAMES ON AN APPROX 29.7HA SITE, INCLUSIVE OF A SINGLE ELECTRICAL CONTROL BUILDING, UP TO 8 INVERTER UNITS, A TEMPORARY CONSTRUCTION AREA AND ANCILLARY FACILITIES, BOUNDARY SECURITY FENCE WITH CCTV UNITS, AN ACCESS TRACK, ALL ASSOCIATED WORKS (INCLUSIVE OF GROSS FLOOR SPACE OF PROPOSED WORKS UP TO 213.6SQM). THE APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL REPORT AND STAGE 1 SCREENING FOR APPROPRIATE ASSESSMENT
View the full application file on the council's planning portal →Application Timeline
Application received
19 Jul 2018
Further information requested
11 Sept 2018
Further information received
23 Nov 2018
Decision: CONDITIONAL
19 Dec 2018
Decision due
20 Dec 2018
Grant issued
4 Feb 2019
Application Details
- Location
- IN THE TOWNLAND OF CLARA , NEAR CLARA , CO OFFALY
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Offaly County Council
- Site Area
- 29.7 ha
Timeline
- Registration Date
- 19 July 2018
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 19 December 2018
- Grant Date
- 4 February 2019
- Permission Expires
- 3 February 2024
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
the development and operation of a c. 14MW solar photovoltaic (PV) farm at this 29.75ha site located off Curragh Road (L20171) in the townland of Clara, near Clara, Co. Offaly. The application seeks a 10-year permission with an operational lifetime of 35 years. The development will consist of: • Approximately 38,000 panels on ground mounted metal frames, with a maximum height above ground of 3.17 metres, including string inverters mounted to the rear of the panels; • 1 no. 38kV substation including 1 no. MV switch room, IPP control room, 1 no. ESB switch room, and associated electrical infrastructure; • 3 no. transformer units; • Underground cabling and ducting; • 1 no. temporary construction compound and ancillary facilities for the duration of the construction phase of the project; • Perimeter Fencing; • CCTV; • Site access provided from existing site access off Curragh Road (L20171), internal tracks, site landscaping and all associated site enabling and site development works. This planning application is accompanied by a Natura Impact Statement (NIS).
Townland of Clara , near Clara , Co. Offaly
The application seeks a 10-year permission with an operational lifetime of 35 years. The development will consist of: • Approximately 38,000 panels on ground mounted metal frames, with a maximum height above ground of 3.17 metres, including string inverters mounted to the rear of the panels; • 1 no. 38kV substation including 1 no. MV switch room, IPP control room, 1 no. ESB switch room, and associated electrical infrastructure; • 3 no. transformer units; • Underground cabling and ducting; • 1 no. temporary construction compound and ancillary facilities for the duration of the construction phase of the project; • Perimeter Fencing; • CCTV; • Site access provided from existing site access of Curagh Road (L20171), internal tracks, site landscaping and all associated site enabling and site development works. This planning application is accompanied by a Natura Impact Statement (NIS).
Ballyboughlin , Clara , Co. Offaly
THE CONSTRUCTION OF A NEW POLYTUNNEL (CIRCA. 1370 M2) AND ALL ASSOCIATED SITE WORKS AND SERVICES. THE PROPOSED DEVELOPMENT IS WITHIN THE CURTILAGE OF A PROTECTED STRUCTURE RPS 12-61, NIAH 14908002
ASHMOUNT HOUSE , BALLYBOUGHLIN , CLARA CO. OFFALY R35 XV29
CONSTRUCTION OF A TWO-STOREY DWELLING (268.4SQ M) & DOMESTIC GARAGE (27SQ M) AND FOR A NEW DOMESTIC ENTRANCE ONTO THE PUBLIC ROADWAY. PERMISSION IS ALSO SOUGHT FOR THE INSTALLATION OF A PACKAGED WASTEWATER TREATMENT SYSTEM AND PERCOLATION AREA AND ALL ASSOCIATED SITE WORKS
RAHEEN , CLARA , CO. OFFALY
Construct a four bedroom dwelling with garage. The application will also include a new domestic entrance and boundary treatments, effluent treatment system, percolation area, associated site-works landscaping and drainage.
Raheen , Clara , Co Offaly
Construction of a four bedroom dwelling with garage. The application will also include a new domestic entrance and boundary treatments, effluent treatment system, percolation area, associated site-works landscaping and drainage.
Raheen , Clara , Co Offaly
AN EXISTING SHED COMPRISING FUEL STORE AND GARDEN TOOL STORE TOGETHER WITH ALL ASSOCIATED SITE DEVELOPMENT WORKS
RAHEEN , CLARA , CO OFFALY
DOMESTIC SHED/GARAGE AT THE REAR OF THE DWELLING HOUSE
RAHEEN , CLARA , CO. OFFALY
retrofit, extend and alter existing dwelling and all associated site works. Permission is also sought for a new waste water treatment system and percolating area
Raheen , Clara , Co.Offaly
construction of a new dwelling, garage, new wastewater treatment system and polishing filter all associated site works
Raheen , Clara , Co. Offaly
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?