Hollyhill Industrial Estate , Tadhg Barry Road , Holyhill
CONDITIONALPlanning application 1938804
Cork - Cork City Council
Proposed Development
Permission for modifications to the elevation of an existing building and all ancillary site development works at Hollyhill Industrial Estate, Tadhg Barry Road, Holyhill, Cork. The proposed modifications consist of upgrades to the elevation of an existing office building including the addition of new windows at ground and first floor levels facing into the existing service yard. Permission is also sought for the retention of modifications to two loading bays including a ground floor extension and associated modifications to the elevations.
View the full application file on the council's planning portal →Application Timeline
Application received
17 Oct 2019
Decision: CONDITIONAL
10 Dec 2019
Decision due
11 Dec 2019
Grant issued
24 Jan 2020
Application Details
- Location
- Hollyhill Industrial Estate , Tadhg Barry Road , Holyhill
- Applicant
- N/A
- Application Type
- RETENTION
- Planning Authority
- Cork City Council
Timeline
- Registration Date
- 17 October 2019
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 10 December 2019
- Grant Date
- 24 January 2020
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission for the construction of a new substation building within the existing car park to cater for additional electric car charging points at the Hollyhill Industrial Estate
Hollyhill Industrial Estate , Tadhg Barry Road , Hollyhill
Permission for the construction of 2 no. plant buildings, 2 no. oil tanks and all associated site development works at Hollyhill Industrial Estate, Tadhg Barry Road, Hollyhill, Cork. The proposed plant buildings will be located within the existing service yard and will accommodate back-up generators, a medium voltage switchroom and a control room.
Hollyhill Industrial Estate , Tadhg Barry Road , Hollyhill
Permission for alterations within the existing lower service yard consisting of the construction of a 110.5m2 single storey extension with a rooftop plant enclosure to an existing production building and all ancillary site development works.
Hollyhill Industrial Estate , Tadgh Barry Road , Holyhill
Permission for the construction of an equipment storage building and all ancillary site development works.
Hollyhill Industrial Estate , Hollyhill , Cork
Permission for an extension to the entrance lobby of an existing office building and all ancillary site development works.
Hollyhill Industrial Estate , Tadhg Barry Road , Holyhill
Retention permission for development of this site at: 113 Ardcullen, Hollyhill, Co.Cork, T23H96V. The development consists of : Permission for the retention of (1) A single storey portico with lean-to roof to front of existing dwelling, and (2) A decorative stone cladding finish to front elevation at ground floor level to existing dwelling.
113 Ardcullen , Hollyhill , Co.Cork
Permission is sought for the erection of 1. Lean-to and Roof Mounted Solar Panels to the South East Elevation of Existing Unit and associated service gantry. 2. New deck with perimeter railing to accommodate Geodome satellite receivers to Existing Roof of Existing Unit and associated site works.
Unit 8 , Hollyhill Industrial Estate , Hollyhill
permission for 1) the erection of two roof mounted insulated chimneys 2)two diesel storage tanks each with a capacity of 10000 litres 3)two water storage tanks each with the capacity of 10000 litres 4) one bund area consisting of a total capacity of 11000 litres. additionally permission is sought for the retention of 1) external plant room 2) a low height wall with fencing a service footpath and electrical and data groundworks on the northwest elevation 3) roof mounted solar panels on the southeast elevation 4) four roof mounted air inlet vents and minor alterations to the fenestration on the northeast elevation
Unit 8 , Hollyhill Industrial Estate , Hollyhill
Permission for modifications to the existing warehouse building and all ancillary site development works at the Former Banta site, Hollymount Industrial Estate, Hollyhill, Cork. The proposed development consists of a change of use of part of the existing warehouse building to use as a testing and measurement facility with ancillary office use and modifications to the building consisting of: the construction of a new mezzanine floor; and modifications to the façade including (1) New windows at first floor level, relocation of doors and opening; and (2) The installation of extract fans and associated ducts. The proposed site development works include: (a) The removal of 1 no. existing shelter; (b) The relocation of an existing generator; (c) Installation of a bicycle rack; (d) The construction of an external plant enclosure comprising of a back up generator with associated diesel tank, air chiller with associated circulation pumps, 2 no. air handling units, 4 no. external condenser units and gas storage tanks; and (e) An external plant enclosure comprising of an air handling unit.
The Former Banta Site , Hollymount Industrial Estate , Hollyhill
permission is sought by Eamon Long and Company T/A Earthmoving Wear Parts Ltd. for (a) subdivision of existing Industrial Unit into three smaller Industrial Units, (b) alterations to elevations associated with the above subdivision including removal of false front façade and recladding of original façade, (c) additional vehicular entrance to west boundary corner, (d) signage to front elevation, all to existing detached industrial unit
industrial Unit at Hollymount Industrial Estate , Hollyhill , Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?