Proposed Development

Erection of 40m high mast for wind measurement

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    31 Jan 2000

  2. Decision: CONDITIONAL

    29 Mar 2000

  3. Decision due

    31 Mar 2000

  4. Grant issued

    2 May 2000

Application Details

Location
BALLYBANE EAST, BALLYBANE EAST,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
31 January 2000Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
29 March 2000
Grant Date
2 May 2000

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

255m
00/4594REFUSED28 Jul 2000

Construction of windfarm consisting of 11 no. wind turbines,electrical substation upgrading of entrance, site tracks & associated works

BALLYBANE EAST, BALLYBANE EAST,

315m
22/800INCOMPLETED APPLICATION23 Dec 2022

A wind farm with an operational lifespan of 30 years, from commissioning, which will connect to the national grid. The proposed wind farm will consist of 7 no. wind turbines with blade tip heights of up to a maximum of 150 metres, and associated foundations and hardstand areas. The proposed development includes a site substation compound with security fencing and a single storey control building and associated loop-in infrastructure to tie into an existing 38kV overhead transmission line, underground cabling, drainage and service infrastructure, bored well, 1 no. permanent meteorological mast of 92 metres in height, tree felling and a temporary construction compound. The development includes landscaping and all associated ancillary development works. Vehicular access will be via an upgraded existing site entrance off the L8456 local road with provision made for the upgrade of existing on-site tracks and the construction of new on-site access roads. It will also include widening of two junctions along the turbine delivery route. The first is at the N71 - R592 junction in Knockroe townland, east of Ballydehob. These works will consist of the temporary removal of a section of masonry wall, public street lighting stanchion, gate, gate posts, trees and earthen berm and the raising of levels with engineered fill to that of the adjacent N71. The second is at the N71 - L8456 junction in Shronagree townland. These works will consist of the lowering of ground levels to that of the adjacent N71 and L8456 and the removal of traffic signage. Both locations to be restored following turbine delivery. An Environmental Impact Assessment Report (EIAR) and a Natural Impact Statement (NIS) have been prepared and will be submitted to the Planning Authority with the application.

Shronagree Ballybane East & Knockroe townlands Ballydehob and Letterlicky Middle Bantry, Co. Cork

315m
23/70INCOMPLETED APPLICATION16 Feb 2023

A wind farm with an operational lifespan of 30 years, from commissioning, which will connect to the national grid. The proposed wind farm will consist of 7 no. wind turbines with blade tip heights of up to a maximum of 150 metres, and associated foundations and hardstand areas. The proposed development includes a site substation compound with security fencing and a single storey control building and associated loop-in infrastructure to tie into an existing 38kV overhead transmission line, underground cabling, drainage and service infrastructure, bored well, 1 no. permanent meteorological mast of 92 metres in height, tree felling and a temporary construction compound. The development includes landscaping and all associated ancillary development works. Vehicular access will be via an upgraded existing site entrance off the L8456 local road with provision made for the upgrade of existing on-site tracks and the construction of new on-site access roads. It will also include widening of two junctions along the turbine delivery route. The first is at the N71 - R592 junction in Knockroe townland, east of Ballydehob. These works will consist of the temporary removal of a section of masonry wall, public street lighting stanchion, gate, gate posts, trees and earthern berm and the raising of levels with engineered fill to that of the adjacent N71. The second is at the N71 - L8456 junction in Shronagree townland. These works will consist of the lowering of ground levels to that of the adjacent N71 and L8456 and the removal of traffic signage. Both locations to be restored following turbine delivery. An Environmental Impact Assessment Report (EIAR) and a Natural Impact Statement (NIS) have been prepared and will be submitted to the Planning Authority with the application.

Shronagree Ballybane East and Knockroe townlands Ballydehob and Letterlicky Middle Bantry, Co. Cork

1.0km
19/398WITHDRAWN12 Jun 2019

The development consists of an existing 30m high telecommunications support structure, antennas, equipment container and associated equipment within a fenced compound and access track. The development forms part of Vodafone Ireland Ltd's existing GSM and 3G Broadband telecommunications network (previous ref. 08/536)

Shronagree Td., Bantry Co. Cork

1.0km
16/734INCOMPLETED APPLICATION30 Nov 2016

Permission for retention (previous Ref No. 08/536) for an existing development. The development consists of an existing 30 metre high telecommunications support structure, antennas, equipment container and associated equipment within a fenced compound and access track. The development forms part of Vodafone Ireland Limited's existing GSM and 3G Broadband telecommunications network

Shronagree Bantry Co. Cork

1.0km
08/536CONDITIONAL25 Mar 2008

Retention of existing 30m high telecommunications support structure, antennas, equipment container and associated equipment within fenced compound and access track and development forms part of Vodafone Ireland's existing GSM and 3G broadband telecommunications network

Shronagree Bantry

1.0km
07/2385INCOMPLETED APPLICATION10 Sept 2007

Retention of existing 30m high telecommunications support structure, antennas, equipment container and associated equipment within fenced compound and access track which forms part of Vodafone Ireland Ltd's existing GSM and 3G Broadband telecommunications network

Shronagree Bantry

1.0km
07/1166INCOMPLETED APPLICATION30 Apr 2007

Retention of existing 30m high telecommunications support structure, antennas, equipment container and associated equipment within fenced compound and access track which forms part of Vodafone Ireland Ltd's existing GSM and 3G Broadband telecommunications network

Shronagree Bantry

1.0km
07/1614INCOMPLETED APPLICATION19 Jun 2007

Retention of existing 30m high telecommunications support structure, antennas, equipment container and associated equipment within fenced compound and access track which forms part of Vodafone Ireland Ltd's existing GSM and 3G Broadband telecommunications network

Shronagree Bantry

1.1km
08/1522INCOMPLETED APPLICATION15 Aug 2008

Dwellinghouse, septic tank and associated site development works

Derryvahalla Bantry

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?