← Back to search

BALLYDUVANE, BALLYDUVANE,

REFUSED

Planning application 01/1076

Cork - Cork County Council

Application Timeline

  1. Application received

    5 Mar 2001

  2. Decision: REFUSED

    3 May 2001

  3. Decision due

    5 May 2001

Application Details

Location
BALLYDUVANE, BALLYDUVANE,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
5 March 2001
Status
APPLICATION FINALISED
Decision
REFUSED
Decision Date
3 May 2001

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

140m
25/6857Application Withdrawn18 Dec 2025

Permission for construction of three indoor paddle courts within an aluminum framed building covered with white PVC fabric material along with three external decorative flag poles to the front facade of the proposed paddle court building. Permission is also sought for a single storey clubhouse consisting of male and female changing rooms, Cafe with external patio area, drive through shop and a new car park consisting of 30 car parking spaces along with new splayed natural stone entrance gate with a pedestrian access gate from the main footpath along with associated external lighting and landscaping and to install a waste water treatment system and drainage system for the aforementioned development and all associated site works

Ballyduvane, Clonakilty, Co. Cork

140m
25/6434Invalid - Case Closed11 Nov 2025

Construction of 3 indoor paddle courts, within an aluminum framed building covered with white PVC fabric material along with three external decorative flag poles to the front facade of the proposed paddle court building. Permission is also sought for a single storey clubhouse consisting of male and female changing rooms, cafe with external patio area, drive through shop and a new car park consisting of 29 car parking spaces along with new splayed natural stone entrance gate with a pedestrian access gate from the main footpath along with associated external lighting and landscaping and to install a waste water treatment system and drainage system for the aforementioned development and all associated site works.

Ballyduvane, Clonakilty, Co. Cork

195m
06/1792WITHDRAWN1 Sept 2006

Construction of plastics manufacturing factory, ancillary office and all associated site works including 1no. new vehicular entrance, 93no. car parking spaces, 2no. storage tanks, 2no. attenuation tanks, waste water treatment plant and percolation area, signage, landscaping, palisade and metal fencing, 2no. pedestrian gates, footpath and lighting

Ballyduvane Clonakilty

199m
08/47REFUSED11 Jan 2008

Construction of plastic manufacturing factory, ancillary office and associated site development works including treatment unit, storm attenuation system, 2no. overground storage tanks, road side signage and fire water retention tank

Ballyduvane Clonakilty

199m
07/3132INCOMPLETED APPLICATION17 Dec 2007

Construction of plastic manufacturing factory, ancillary office and associated site development works, including treatment unit and storm water attenuation system

Ballyduvane Clonakilty

288m
20/760CONDITIONAL18 Dec 2020

Construction of a single storey bedroom extension to side of existing dwelling house

Ballyduvane Clonakilty Co. Cork

294m
01/1091CONDITIONAL6 Mar 2001

Construction of pitched roof to replace flat roof over extension to dwelling

BALLYDUVANE, BALLYDUVANE,

297m
05/7451CONDITIONAL12 Oct 2005

Development of club complex incorporating 1 no. floodlit and fenced grass pitch with 3 additional grass playing pitches(1 no. fenced), all with high level protective netting, 1 no. fenced synthetic grass all-weather training pitch, two storey clubhouse with members bar and service areas, changing room facilities, meeting rooms, kitchen etc., handball alley and equipment store, covered viewing stand, carparking with provision for overspill carparking on pitch no. 4, proprietary waste treatment unit with percolation area, perimeter amenity walking/jogging track, earth berm for temporarily containing 30,000m.cu of floodwater and new entrance and landscaping

Ahamilla Clonakilty

297m
05/7151INCOMPLETED APPLICATION3 Oct 2005

Development incorporating 1 no. floodlit and fenced grass pitch with 3 no. additional grass pitches with protective netting and 1 no. fenced synthetic all weather pitch, two storey club house, carparking and entrance

Ahamilla Clonakilty

297m
09/42CONDITIONAL22 Jan 2009

Reduction in size of All Weather Pitch previously granted under planning reg: 05/7451 and An Bord Pleanala Ref: PL 04 218341 and erection of pitch lighting; Construction of open air Hurling Alley in lieu of indoor hurling alley previously granted under planning reg: 05/7451 and An Bord Pleanala Ref: PL 04 218341 and provision of 76no. additional parking spaces; Permission for retention of three metre high precast concrete panel boundary fence

Clonakilty GAA Sports Complex Ahamilla & Ballyduvane Clonakilty

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?