Proposed Development
Dwellinghouse (change of plan)
Application Timeline
Application received
20 Mar 2003
Decision due
14 May 2003
Decision: CONDITIONAL
14 May 2003
Grant issued
19 Jun 2003
Application Details
- Location
- KILBEG NORTH, KILBEG NORTH,
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 20 March 2003Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 14 May 2003
- Grant Date
- 19 June 2003
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of extension (for use as DPD parcel sorting unit) to side of Unit 9 (currently being used as DPD parcel sorting unit).
Kilbrogan Business Park Kilbrogan Bandon Co. Cork
Demolition of part of front (western elevation) of existing two-storey section of industrial food processing building and demolition of existing detached security building and construction of new two-storey extension to front (western elevation) of existing building to accommodate enlarged reception, circulation areas, office and meeting room accommodation and staff amenity areas at ground and first floor levels, enlarged dry-goods storage area, new roof to existing loading bays, new loading bay on southern elevation, new detached security building, eight new visitor car parking spaces, with all associated site development works and boundary treatments including new fencing to car park area and landscaping
ABP Bandon Kilbrogan Bandon
Residential development - 42 no. dwellinghouses
Knockbrogan Bandon
2 no. dwellinghouses and relocation of existing foul sewer pump sump and surface water retention tank
Knockbrogan Bandon
Construction of single storey extension to side of existing shop/retail premises.
Main Cork Road Ballylangley Bandon Co. Cork
(a)retail store extension to the north of the existing building consisting of a ground floor shop extension and first floor office extension, (b) store extension to the west of the existing building and (c) extension and modifications to the existing car parking area to the north of the building along with all associated site works.
Bandon Co-Op Retail Centre Kilbrogan Bandon Co. Cork
Alterations to development previously permitted under Planning Reg. No. 08/6664, comprising of the construction of wholesale warehouse & business services development. Alterations consist of the construction of a single storey drive-thru restaurant, provision of 35 no. car parking spaces, landscaping & signage & all associated site works
Glasslinn Road Ballylangley Bandon
Alterations to part of permission granted under Pl. Reg. No. 08/6664 comprising of the construction of wholesale warehouse and business services development, to provide for the omission of Block E (5 no. units) and the construction of a single storey drive-thru restaurant, provision for 35 no. car parking spaces, landscaping, signage and associated site works
Glasslinn Road Ballylangley Bandon
Dwellinghouse and garage
Kilbeg North Bandon
Development of a 2.1 acre site for construction of single storey gym with external amenity space & children's play area, single storey drive-thru restaurant, provision of 80no. surface car parking spaces, relocation of site entrance, ESB substation & all associated site works, landscaping, lighting & signage
Glasslin Road Ballylangley Bandon