← Back to search

GLASHABOY SOUTH, GLASHABOY SOUTH,

CONDITIONAL

Planning application 03/2829

Cork - Cork County Council

Proposed Development

Extension to dwelling and detached domestic garage

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    11 Jun 2003

  2. Decision due

    5 Aug 2003

  3. Decision: CONDITIONAL

    5 Aug 2003

  4. Grant issued

    10 Sept 2003

Application Details

Location
GLASHABOY SOUTH, GLASHABOY SOUTH,
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
11 June 2003Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
5 August 2003
Grant Date
10 September 2003

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

144m
03/2647CONDITIONAL30 May 2003

Dwellinghouse and garage

GLASHABOY SOUTH, GLASHABOY SOUTH,

259m
20/4044CONDITIONAL17 Jan 2020

To construct a dwellinghouse, garage, on-site waste water treatment system and all associated site works

Glashaboy North Carrignavar Co. Cork

262m
19/4662REFUSED19 Mar 2019

To construct a two-storey dwellinghouse, garage, site works, waste water treatment system and percolation area, bore well and all ancillary works.

Glashaboy North Carrignavar Co. Cork

353m
22/6418WITHDRAWN27 Oct 2022

For the importation of clean inert soil and stone for the raising of an agricultural field in order to improve the agricultural output of the field and the construction of a new entrance and temporary haul road

Glashaboy South Carrignavar Co.Cork

353m
23/6297WITHDRAWN17 Nov 2023

Permission for the importation of clean inert soil & stone for the raising of an agricultural field in order to improve the agricultural output of the field and the construction of a new entrance and temporary haul road

Glashaboy South Carrignavar Co.Cork

354m
25/4017CONDITIONAL13 Jan 2025

Permission for the importation of clean inert soil & stone for the raising of an agricultural field in order to improve the agricultural output of the field and the construction of a new entrance and temporary haul road

Glashaboy South Carrignavar Co.Cork

360m
07/8977CONDITIONAL25 Jun 2007

Dwellinghouse and garage

Glashaboy South Carrignavar

360m
07/8008INCOMPLETED APPLICATION22 May 2007

Dwellinghouse and garage

Glashaboy South Carrignavar

360m
07/5057REFUSED14 Feb 2007

Dwellinghouse

Glashaboy South Carrignavar

360m
10/8369CONDITIONAL3 Nov 2010

Construction of two storey dwellinghouse, septic tank and all associated site works

Glashaboy South Carrignavar Co Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?