Proposed Development
Extension to office accomodation block
Application Timeline
Application received
4 Jul 2003
Decision due
28 Aug 2003
Decision: CONDITIONAL
28 Aug 2003
Grant issued
3 Oct 2003
Application Details
- Location
- RAHEENS EAST, RAHEENS EAST,
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 4 July 2003
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 28 August 2003
- Grant Date
- 3 October 2003
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of a single storey laboratory extension, a single storey administration office block extension, ancillary car-parking spaces and associated site works on an Integrated Pollution Control (IPC) licensed site
Raheens East Ringaskiddy Co. Cork
The installation of a solar photovoltaic (PV) Array (Proposed Area = 1132m2) on the roof of an existing single storey warehouse building with new external vertical access ladder to south elevation at the existing facility and associated site works on an Integrated Pollution Control (IPC Reg. No. P0476) licensed site for Recordati Ireland Ltd.
Raheens East Ringaskiddy Co. Cork
Bulk solvent storage and drum filling facility inside an existing disused water storage tank
Raheens East Ringaskiddy
A BioPark and all ancillary site development works including landscaping, fencing and signage. The proposed BioPark consists of 4 no. 2-storey bio-manufacturing buildings, 4 no. 2-storey administration/laboratory buildings with roof top plant room, a 2 storey warehouse building with 6 storey storage tower, a 2 storey hydration facility building, a 2 storey central utilities building with external boiler flues, and a 2 storey canteen and administration building with roof top plant room and service yard. The bio-manufacturing, administration/laboratory, hydration facility and central utilities buildings are all connected to the central warehouse building via 2 no. 1-2 storey spine buildings. The proposed site development works include a security building, pump house, water chiller tower, the relocation of overhead wires, 4 no. generators, ESB compound, water balancing tank farm, fire water tank, utility water tank, Bord Gais compound, internal access roads, car parking and a fire water retention pond. Primary access to the proposed development is from the R613 with a secondary access via an existing entrance from the L2496.
Barnahely Raheens East Ringaskiddy Co. Cork
Permission for the erection of an IDA Ireland branded Totem sign at the site entrance and associated works at Raheens East, Loughbeg, Ringaskiddy, Co. Cork. The sign will be located within IDA Ireland lands as indicated in the drawings and particulars.
IDA Ireland Raheens East, Loughbeg Ringaskiddy Co. Cork
Permission for the erection of an IDA branded totem sign at the site entrance and associated works on Curraghbinny Road. The sign will be located within IDA lands as indicated in the drawings and particulars.
Industrial Development Agency (IDA) Ireland Loughbeg Raheens East Ringaskiddy Co Cork
Development at this site of c.8.98 ha at Barnahely, Ringaskiddy, Co. Cork. The proposed development seeks to provide site development works for future industrial development including site excavation, regrading of existing levels, undergrounding of existing electrical cables, landscaping and boundary treatment works. The proposed development also makes provision for a temporary construction access from the adjacent public road and a temporary perimeter surface water drainage system.
Barnahely Ringaskiddy Co. Cork
Construction of 84 no. space extension to existing car park, realignment of existing adjacent site road to accommodate car park extension, provision of associated drainage, lighting and landscaping
Raheens Ringaskiddy
Construction of a below ground foul pumping station incorporating a below ground emergency storage tank, a below ground storm water pumping station, a 3.1m high control building and ESB substation, a 2.65m high chemical dosing unit, provision of a 2.15m high standby generator with acoustic barrier, a 1.5m high air handling unit with acoustic barrier, a 4m high mobile lifting gantry and a 2.4m high security fence along with indigenous plant screening. Pipework associated with the development includes a foul rising main along the R613, local roads and green fields from the foul pumping station to the Shanbally WWTP (c. 3km) as well as 3 no. short sections of pipeline (c. 136.5m in total) associated with the storm water pumping station and foul pumping station. Installation of 2 no. new reinforced concrete manhole chambers on existing pipelines will also be required. The development will also consist of all associated site work and site excavation works both above and below ground for the pumping stations, pipelines. The works will include the demolition of a derelict bungalow at proposed pumping stations site.
Shanbally, Raheens, Coolmore, Barnahely Raheens East Ringaskiddy Co. Cork
Single storey extension to existing NIPBI laboratory, 2 no. extensions to single storey NIPBI offices, external rooftop plant and all associated on-site infrastructure
Raheens Ringaskiddy
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?