Proposed Development
Blasting at existing quarry
Application Timeline
Application received
11 Jul 2003
Decision: CONDITIONAL
3 Sept 2003
Decision due
4 Sept 2003
Grant issued
9 Oct 2003
Application Details
- Location
- BALLYHANDLE, BALLYHANDLE,
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 11 July 2003
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 3 September 2003
- Grant Date
- 9 October 2003
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
A 10 Year Planning Permission for 100% Carbon Negative Renewable Energy c.600 panel, 420 kilowatt (c.1875m2) ground mounted solar PV array and all associated works
Ballyhandle Quarry, Ballyhandle, Crossbarry, Cork, T12DK46
A 10 Year Planning Permission for a 100% Carbon Negative Renewable Energy c.600 panel, 420 Kilo Watts (c.1875m2) ground mounted solar PV array and all associated works. This development is covered by the provisions of the Renewable Energy Directive III (Directive(EU)2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development regulations 2001 to 2025 shall apply.
Ballyhandle, Crossbarry, Co. Cork, T12DK46
A 10 Year planning permission for 100% Carbon Negative Renewable Energy c.600 panel, 420 Kilo Watt (c.1875m2) Ground mounted solar PV array and all associated works. This development is covered by the provisions of the renewable energy directive III (Directive(EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisionS of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.
Ballyhandle Quarry, Ballyhandle, Innishannon, Cork, T12DK46
A 10 Year planning permission for a 100% carbon negative renewable energy c.600 Panel, 420 Kilo Watt (c1875m2) ground mounted solar PV array and all associated works. This development is covered by the provisions of the Renewable Energy Directive III (Directive(EU)2023/2024) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development regulations 2001 to 2025 shall apply.
Ballyhandle Quarry, Ballyhandle, Innishannon, Co. Cork, T12DK46
Permission for a 100% carbon negative renewable energy c.600 panel, 420 kilo watt (c.1875m2) ground mounted solar PV array and all associated works
Ballyhandle Crossbarry Co.Cork
Concrete products batching plant including provision of truck wash-out facility, site office, including canteen & washrom facility, 4 no. car parking spaces, aggregate storage, septic tank and percolation area.
Ballyhandle, Crossbarry
The development will consist of continued use and extension (c.6 hectares) of the existing quarry over a total extraction area of c.10 hectares and to a final floor level of c.57mOD; screening berms; final restoration; and related ancillary works; all within an overall application area of c.12.6 hectares.
Ballyhandle Quarry Ballyhandle Crossbarry, Co. Cork
Installation & operation of an asphalt plant with an overall stack height of 27 meters, aggregate storage area , washing and screening facility, settlement lagoons and fuel storage
Ballyhandle Quarry Ballyhandle Crossbarry
Permission to waive Condition No. 3 of planning ref: 05/5026 to allow for the continuance of use for the duration of quarry extraction operations at the site, of the existing asphalt plant previously permitted under planning ref: No. 05/5026 with associated aggregate storage areas and settlement lagoons within an overall application area of c.2.75 hectares. Planning ref: 05/5026 was previously permitted for the installation and operation of an asphalt plant (with an overall stack height of 27 meters).
Ballyhandle Quarry Crossbarry Co. Cork
Permission to waive Condition No. 3 of planning ref: 05/5026 to allow for the continuance of use for the duration of quarry extraction operations at the site, of the existing asphalt plant previously permitted under planning ref: No. 05/5026 with associated aggregate storage areas and settlement lagoons within an overall application area of c.2.75 hectares. Planning ref: 05/5026 was previously permitted for the installation and operation of an asphalt plant (with an overall stack height of 27 meters).
Ballyhandle Quarry Crossbarry Co. Cork
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?