Application received
14 Jun 2004
Decision: CONDITIONAL
12 Aug 2004
Decision due
13 Aug 2004
Grant issued
17 Sept 2004
Application Details
- Location
- Moneyflugh Inniscarra
- Applicant
- N/A
- Application Type
- APPROVAL
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 14 June 2004Other applications received that week
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 12 August 2004
- Grant Date
- 17 September 2004
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Permission to construct a slatted tank and ancillary works.
Bridgestown , Inniscarra , Co.Cork
Dormer type dwelling
Bridgestown Inniscarra
Permission...for the construction of a dwelling house, a garage for domestic purpose, to install a domestic waste water treatment system and to carry out all associated site works.
Moneyflugh , Inniscarra
Permission for the construction of a dwelling house, a garage for domestic purpose, to install a domestic waster water treatment system and to carry out all associated site works.
Moneyflugh , Inniscarra , Cork
The construction of a three-bedroom bungalow dwelling, new vehicular entrance, wastewater treatment system, landscaping and ancillary works necessary to facilitate the development
Bridgestown Inniscarra Co.Cork
Two storey extension to side of dwelling, single storey annex incorporating carport and garage to rear, enlargement of site, landscaping and ancillary site development works
Ardrum View Bridgestown Inniscarra
Alterations, bay window ,two storey extension to side of dwelling and construction of single storey annex incorporating carport and garage to rear ,upgrading of site entrance and enlargement of site including landscaping and ancillary site works
Ardrum View Bridgestown Inniscarra
Construct a dwellinghouse
Bridgestown , Inishcarra , Co.Cork
To construct a new dwelling house.
Bridgestown , Inishcarra , Co. Cork
Permission for a solar farm consisting of circa 85,000sq.m of solar panels on ground mounted frames, 1 no. single storey substation, 6 no. single storey electrical inverter/transformer stations, battery storage module and associated equipment container, security fencing, satellite pole, CCTV, and all associated ancillary development works. Construction and operational access to the proposed development will be provided via an existing entrance from the R618 to the south. The operational lifespan of the solar farm will be 35 years.
Garravagh , Inniscarra , Co. Cork