← Back to search

Gooldshill Mallow

CONDITIONAL

Planning application 04/4771

Cork - Cork County Council

Application Timeline

  1. Application received

    29 Jun 2004

  2. Decision due

    23 Aug 2004

  3. Decision: CONDITIONAL

    23 Aug 2004

  4. Grant issued

    28 Sept 2004

Application Details

Location
Gooldshill Mallow
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
29 June 2004Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
23 August 2004
Grant Date
28 September 2004

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

226m
07/11985CONDITIONAL26 Oct 2007

Construction of 3 no. office buildings comprising of 1 no. three storey building with roof top plant and subdivided into 5 no. units for separate usage (Building No. 1), 1 no. three storey building with roof top plant and subdivided into 6 no. units for separate usage (Building No. 2) and 1 no. two storey building with roof top plant for one usage (Building No. 3), construction of double height car park and all ancillary site works

Mallow Business Park Gooldshill Mallow

511m
07/55018WITHDRAWN23 Mar 2007

Erection of Bulk Silo, Associated Tanks & Boiler, Concrete Yard at rear & side of building.

Quartertown Ind Est Mallow Co Cork

605m
08/55019CONDITIONAL4 Apr 2008

the construction of 2 no. soccer pitches, dressing room area, new parking area and all associated services in accordance with plans and particulars submitted

Ballydahin Td., Mallow Co. Cork.

618m
15/6362CONDITIONAL21 Oct 2015

Retention of refurbishment of front façade of existing office building and retention of change of use of part of the ground floor from office use to a confectionery processing area, and Permission for the following: (1) extension to existing confectionary processing area that is being retained in order to increase the confectionary processing area to facilitate the storage of finished goods and packaging, (2) removal of existing external fire escape staircase to the side of existing office building and construction of a new extension incorporating a new external staircase, (3) construction of a new site entrance for the improvement of traffic flow to and from the facility, and (4) erection of a new telecommunications mast that is to be located on the proposed new extension and all associated site works and services

Gooldshill Mallow Co. Cork

635m
08/55029CONDITIONAL19 May 2008

Permission for manufacturing and storage warehouse facility and associated site works

I.D.A. Industrial Estate Quartertown Mallow Co. Cork.

695m
21/6798Conditional Permission15 Oct 2021

Erect 2,390.00m2 or 484.20 kW of photovoltaic panels on the roofs of the building in the Cold Store with all associated site works

Lyonara Cold Store R638 Gooldshill Mallow

705m
06/10129CONDITIONAL29 Aug 2006

Construction of garden store/utility room

Quartertown Lower Mallow

708m
24/6514Conditional Permission23 Dec 2024

Permission for the construction of 1 No. new light engineering high bay manufacturing & assembly workshop and 1 No. light engineering storage building adjacent to existing light engineering manufacturing buildings and all associated works.

Quartertown Industrial Estate Quartertown Lower Mallow Co. Cork

713m
10/55026WITHDRAWN31 May 2010

Consturction of a toilet building within their existing allotment area adjacent to the Hi-Cone building as well as the laying of a new sewer through the Hi-Cone site to connect to the existing public sewer on the adjacent industrial estate road

Quartertown Lower Mallow Co. Cork.

725m
06/55006CONDITIONAL3 Feb 2006

1) construction of warehouse building 2) extension of existing warehouse building and carrying out of all associated site works

Quartertown Ind Est Quartertown Lower Mallow Co. Cork.

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?