  1. Application received

    5 Feb 2004

  2. Decision due

    31 Mar 2004

  3. Decision: CONDITIONAL

    31 Mar 2004

  4. Grant issued

    6 May 2004

Application Details

Location
Derrycreeveen Bere Island
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
5 February 2004Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
31 March 2004
Grant Date
6 May 2004

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

133m
09/115WITHDRAWN10 Feb 2009

Alterations to site boundaries as per granted under planning reg: 08/95; Permission for minor elevation changes relating to window pattern of dwelling as per granted under planning reg: 08/95

Derrycreeveen Bere Island

196m
17/629CONDITIONAL25 Sept 2017

Construction of dwelling house, installation of waste water treatment system and all associated site works.

Derrycreeveen Bere Island Co. Cork

631m
00/4286CONDITIONAL14 Jul 2000

Dwellinghouse

DERRYCREEVEEN, DERRYCREEVEEN,

874m
01/2280CONDITIONAL24 Apr 2001

Demolition of ruin & construction of dwelling

DERRYCREEVEEN, DERRYCREEVEEN,

914m
04/5950CONDITIONAL4 Aug 2004

Dwellinghouse

Derrycreeveen Bere Island

929m
99/1770CONDITIONAL9 Apr 1999

Dormer dwelling & garage (change of plan)

WEST END, WEST END, DERRYCREEVEEN,

1.0km
24/200WITHDRAWN25 Apr 2024

Install a wastewater treatment system to serve dwelling and all associated site works

Derrycreeveen Bere Island Beara Co. Cork

1.0km
24/140INCOMPLETED APPLICATION26 Mar 2024

Permission to install a wastewater treatment system and all associated site works

Derrycreeveen Bere Island Beara Co. Cork

1.1km
07/2793CONDITIONAL5 Nov 2007

Construct new MV electrical Substation Building

Dinish Island Castletownbere

1.2km
19/454CONDITIONAL5 Jul 2019

A new fuel tank compound (to replace existing fuel tank area on Dinish Island and Castletownbere mainland quay) to accommodate 6 no. bunded oil tanks (130,000 litre capacity each), 2 no. supply lines to connect fuel tanks to permitted new quay and onwards to existing quay, ancillary surface water drainage system, and ancillary site development works including areas of hardstand, public lighting and boundary fencing. All on a site of 0.42 ha approx.

Dinish Island Castletownbere Co. Cork

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?