ESB Fermoy North 38kV substation Carrignagroghera Fermoy
INCOMPLETED APPLICATIONPlanning application 05/4761
Cork - Cork County Council
Proposed Development
Erection of 20m high free standing wooden communications structure, carrying antennae and communication dishes with associated equipment cabinets within a 2.4 m high timber compound
Application Details
- Location
- ESB Fermoy North 38kV substation Carrignagroghera Fermoy
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 5 July 2005Other applications received that week
- Status
- INCOMPLETED APPLICATION
- Decision
- Pending
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Construction of retail trade warehouse, distribution and service centre for building and construction materials, furnishings and fittings with associated facilities, security office, signage, car park and associated site works
Carrignagroghera Fermoy
Construction of retail trade warehouse, distribution and service centre for building and construction materials with associated facilities, security office, signage, car park and associated site works
Carrignagroghera Fermoy
Permission for extension to existing warehouse and offices at Fermoy Enterprise Park, Carrignagrohera, Fermoy
Co. Cork
Refurbishment and subdivision of the old Faber Castell building for the development of Industrial Units, change of traffic circulation and car park layout, and ancillary works.
Carrignagroghera
To amalgamate unit 2 and 3 of Faber Castell Business Campus for use as one unit for printing and design works.
Unit 2 and 3 Faber Castell Business Campus Carrignagroghera Td. Fermoy Co. Cork
The construction of motor display canopy, 32.22mts long by 5mts wide and 4.5mts high. The canopy will consist of galvanized steel structure of 5 posts, steel frame and PVC coated textile tarpaulin as roofing material.
Blackwater Motors Dublin Road Carrignagroghera Fermoy Co. Cork
Retention of 48 linear meters of 1 mt high stainless steel bollards that currently form the existing boundary treatment onto the Dublin Road.
Blackwater Motors Dublin Road Carrignagroghera Fermoy Co Cork
Retention of 50 linear meter of stainless steel bollards that currently form the existing boundary treatment onto the Dublin Road
Blackwater Motors Carrignagroghera Dublin Road, Fermoy Co Cork
The construction of a 3-bedroom house on existing farm land
Grange Stud Grange East Fermoy, Co. Cork
Construction of an advance office facility (two storey)
Fermoy Bus.& Tech.PK. Carrignagroghera Fermoy
The submission window has closed
Observations on this application closed on Monday 8 August 2005, five weeks after it was received. The authority cannot accept a late submission.