← Back to search

Bandon Community Hospital Cloghmacsimon Bandon

CONDITIONAL

Planning application 05/5946

Cork - Cork County Council

Proposed Development

Construction of extension to hospital to consist of waiting and reception area

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    18 Aug 2005

  2. Decision due

    12 Oct 2005

  3. Decision: CONDITIONAL

    12 Oct 2005

  4. Grant issued

    17 Nov 2005

Application Details

Location
Bandon Community Hospital Cloghmacsimon Bandon
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
18 August 2005
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
12 October 2005
Grant Date
17 November 2005

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

13m
12/6182CONDITIONAL18 Oct 2012

Erection of a firewater storage tank 5120mm in diameter and 4200mm high on the Watergate Centre site adjoining Bandon Community Hospital. Extension of road to the firewater storage tank and modifications to the Bandon Community Hospital car park, dismantling of existing cold water storage tank and tower, construction of a new platform over the existing toilet extension to house the new cold water storage tank to the rear of Community Hospital. Retention and relocation of a shed on the Community Hospital site and another shed on the Watergate Centre site.

Bandon Community Hospital Watergate Centre Cloghmacsimon Bandon

31m
08/7259CONDITIONAL12 Jun 2008

Construction of 20 bed care module with assisted en-suites and associated support facilities, new service block accommodating kitchen, mortuary, stores, laundry room, changing facilities and associated service facilities including a substation, switch room and boiler room and new vehicular entrance and construction of site access road and associated site works to include landscaping, upgrading and extending existing car parking facilties and upgrading of existing drainage to facilitate separation of surface and foul water prior to discharge from site

Community Hospital Cloghmacsimon Bandon

31m
08/6516INCOMPLETED APPLICATION2 May 2008

Construction of 1) 20 bed care module with assisted en-suites and associated support facilities. 2) Service block accommodating kitchen, mortuary, stores, laundry room, changing facilities and associated service facilities also including a sub-station, switch room and boiler room and 3) vew vehicular entrance and construction site access road from the Bandon inner relier road (in preparation for its use as the long term public access upon completion of a master plan for the entire site) with associated site works all complete with landscaping including upgrading and extending the existing car parking facilities and the upgrading of existing drainage to facilitate the separation of surface and foul water prior to discharge from the site

Bandon Community Hospital Cloghmacsimon Bandon

49m
15/5142CONDITIONAL29 May 2015

Demolition of part of the south east wing and adjoining annex to the rear of the hospital, together with sections of the old boundary walls, and construction of (1) a new 25 bed care module with assisted ensuites, associated support and service facilities including a switch room and boiler room, (2) conversion of existing ward area to ancillary and lounge day room accommodation together with the remodelling of the main entrance area to include a new external canopy, (3) installation of a firewater storage tank 5.2m diameter and 2.75m high, and (4) a new internal only vehicular access road to provide access to the rear (South) with associated site works. The works will be completed with landscaping including the upgrading and extensions of the existing car parking facilities plus the upgrading of existing drainage to facilitate the separation of surface and foul water prior to discharge from site

Bandon Community Hospital Cloghmacsimon Bandon

77m
11/4598CONDITIONAL25 Mar 2011

Retention of existing single storey extension to rear and permuission for construction of single storey extension to rear of dwellinghouse with associated site works

No. 21 Ardan na nOglach Cloghmacsimon Td. Bandon, Co Cork

119m
18/4529CONDITIONAL5 Mar 2018

Construct an extension to existing dwellinghouse and carry out associated site works

5 Ardan Cloghmacsimon Bandon Co. Cork

151m
07/11113REFUSED20 Sept 2007

Retention of change of use from chicken house to warehouse for storage of goods for distribution to discount shops & associated site works.

Cloghmacsimon Bandon

151m
08/5731CONDITIONAL28 Mar 2008

Retention of change of use of chicken house to warehouse for storage of goods for distribution to Discount Shops and retention of 2 no. offices and toilet unit and associated site works

Cloghmacsimon Bandon

158m
14/5718CONDITIONAL12 Aug 2014

Erection of porch to front of existing dwellinghouse

12 Ardan na n-Oglach Cloghmacsimon Bandon

178m
09/4391CONDITIONAL10 Feb 2009

Demolition of 3 no. sheds (269.4sqm total area), construction of retail warehouse and associated storage area with 2 no. office units above, all over two storeys, 2 no. semi-detached three-storey 4-bed residential dwellings, 2 no. bin stores and associated site development works including a new vehicular entrance and 36 no. car parking spaces

Cloghmacsimon Bandon