← Back to search

Coomleagh East Bantry

CONDITIONAL

Planning application 05/6090

Cork - Cork County Council

Proposed Development

Erection of temporary 50m high wind monitoring pole

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    24 Aug 2005

  2. Decision due

    18 Oct 2005

  3. Decision: CONDITIONAL

    18 Oct 2005

Application Details

Location
Coomleagh East Bantry
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
24 August 2005
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
18 October 2005

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

0m
05/5388INCOMPLETED APPLICATION27 Jul 2005

Erection of temporary 50m high wind monitoring pole

Coomleagh Bantry

392m
99/1708REFUSED7 Apr 1999

Windfarm to include 20 no. turbines, meteorological mast, control building,notice board, access tracks, upgrading of laneway & ancillary works

COOMLEAGH EAST, COOMLEAGH EAST,

872m
99/5557REFUSED14 Oct 1999

Windfarm to include 7 no. turbines, meteorological mast, control building,notice board, access tracks, upgrading of laneway & ancillary works

COOMLEAGH EAST, COOMLEAGH EAST,

1.3km
99/1228CONDITIONAL12 Mar 1999

Erection of a 40m wind measurement pole

COUSANE, COUSANE,

1.4km
20/523CONDITIONAL28 Sept 2020

Full Planning Permission for a) relocation of entrance to dwelling as granted under planning application number 13/544 b) closure of existing entrance to dwelling as granted under planning application number 13/544 c) all associated siteworks

Cousane Kealkill Bantry Co. Cork

1.4km
13/544CONDITIONAL20 Sept 2013

Construction of dwelling house and all associated site works

Cousane Kealkill Bantry Co Cork

1.4km
08/1913INCOMPLETED APPLICATION24 Oct 2008

Erection of wind farm comprising 5 wind turbines with towers up to 46m in height and rotor diameter up to 62m and ancillary equipment for generation of electricity with control building and substation and 40m wind monitoring mast

Goulacullin Dunmanway

1.4km
02/5124CONDITIONAL21 Nov 2002

Windfarm to include 5 no. turbines, ancillary equipment for generation of electricity, control buildings, substation & 40m wind monitoring mast

GOULACULLIN, GOULACULLIN,

1.5km
99/5076REFUSED17 Sept 1999

Erection of a windfarm comprising of 12 no. wind turbines & ancillary equipment for generation of electricity & control building

GOULACULLIN, GOULACULLIN,

1.5km
07/454CONDITIONAL19 Feb 2007

Extension to farm shed for housing cattle and below ground slatted tank

Cousane Kealkill