← Back to search

Coolcour Macroom

CONDITIONAL

Planning application 06/8853

Cork - Cork County Council

Proposed Development

Extension to dwellinghouse

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    13 Jul 2006

  2. Decision: CONDITIONAL

    22 Nov 2006

  3. Decision due

    23 Nov 2006

  4. Grant issued

    2 Jan 2007

Application Details

Location
Coolcour Macroom
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
13 July 2006Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
22 November 2006
Grant Date
2 January 2007

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

449m
04/6290CONDITIONAL17 Aug 2004

Conversion of vehicle storage and car sales building to form a new vehicle showroom display area, with walls, roofing, glazing, additional extension of service facilities to include hand over canopies, additional customer parking and external display of used vehicles, re-cladding of existing petrol forecourt shop to match new development and erection of new boundary walls and footways to forecourt area of site and demolition of derelict bungalow

Coolcour Macroom

449m
05/4838CONDITIONAL7 Jul 2005

Construction of cleaning canopy and valeting building

Coolcour Macroom

496m
16/7229CONDITIONAL21 Dec 2016

Construction of 2 number commercial units consisting of: meat storage/processing building incorporating stores, freezer room, cutting room, loading area, demo room, W.C’s, administration and offices, car-parking together with all ancillary site works.

Coolcower Industrial Estate Coolcower Macroom Co. Cork

600m
04/8986CONDITIONAL7 Dec 2004

Factory building with offices and dispatch area to manufacture timber framed buildings including site develoment works, services and construction of access road

Coolcour Macroom

626m
04/2522REFUSED15 Apr 2004

Dwellinghouse

Ummera Macroom

648m
11/54014UNCONDITIONAL14 Oct 2011

Dwelling

Sleaveen East Macroom Co.Cork

648m
06/54038CONDITIONAL12 Jul 2006

Dwelling

Sleaveen East Macroom

771m
04/54013CONDITIONAL26 Apr 2004

To Construct 5 No. Two Storey Dwellings with Retaining Wall to Riverbank and Associated Site Works.

Sleaveen East Macroom

1.2km
15/5447CONDITIONAL2 Jul 2015

Erection of a loose cattle shed, roofed manure pit, cattle handling area, underground effluent tank, isolation unit and associated site works

Farranavarrigane Macroom Co. Cork

1.2km
22/4630CONDITIONAL23 Mar 2022

Upgrade works at the wastewater treatment plant which will consist of 1. Construction of a new storm overflow and flow splitting chamber, inlet works including grit removal system and full flow to treatment pumping station, 2 no. new integrated fixed-film activated sludge reactor tanks (Aeration Tanks), 2 no. final settlement tanks, final water sampling manhole while retaining the existing outfall to the River Sullane, return and waste activated sludge pumping stations, chemical building including lime and ferric sulphate dosing systems with bunded chemical storage tanks, 1no. storm water storage tank equipped with storm water pumps, 1 no. sludge picket fence thickener, odour control system, a sheet pile flood protection wall within the site boundary, boundary treatments include a weld mesh security fence, new internal access road and public lighting. 2. Construction of a new control and administration building. 3.Decommissioning of the existing wastewater treatment plant, equipment and associated structures as part of the upgrade works. 4. Construction of a 42 kWp photovoltaic (PV) solar panels on ground mounted frames on the north western area of the site. The PV panel shall be used to supplement the energy demands of the proposed WwTP and will be arranged with a panel area of 185sqm approximately. 5. Establishment of a designated area to be utilized by Cork County Council Roads Department and construction of a new entrance point. 6. All associated site development works above and below ground. A Natura Impact Statement (NIS) will be submitted to the planning authority with the application.

Wastewater Treatment Plant (WwTP) Macroom Sleveen East Co. Cork