Munster Joinery Lacka Cross Lackanastooka Ballydesmond

CONDITIONAL

Planning application 07/7041

Cork - Cork County Council

Proposed Development

Retention of 2 no. extensions to softwood processing building and extension to main joinery building for the purpose of increasing production

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    16 Apr 2007

  2. Decision due

    10 Jun 2007

  3. Decision: CONDITIONAL

    11 Jun 2007

  4. Grant issued

    12 Jul 2007

Application Details

Location
Munster Joinery Lacka Cross Lackanastooka Ballydesmond
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
16 April 2007
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
11 June 2007
Grant Date
12 July 2007

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

28m
07/5953INCOMPLETED APPLICATION13 Mar 2007

Retention of 2 no. extensions to softwood processing building and extension to main joinery building at window and door manufacturing facility

Munster Joinery Lacka Cross Lackanastooka Ballydesmond

60m
14/6456INCOMPLETED APPLICATION18 Nov 2014

Amendments to the previously granted planning application, Ref. No. 08/10253. The works will consist of replacing 4 no. roller shutter doors with 2 no. wider roller shutter doors and relocating the two existing personal access doors on the north elevation. Providing a new personal access door on the north elevation. Relocating the existing roller shutter door and two personal access doors on the east elevation. A new access parking bay to be provided in front of the relocated roller shutter door on the east elevation. And all ancillary site works

Lacka Cross Lackanastooka Ballydesmond

62m
07/10705CONDITIONAL3 Sept 2007

Construction of extension to main Joinery Building to increase the production area and relocation of existing compressed air facility

Munster Joinery Lacka Cross Lackanastooka Ballydesmond

63m
12/4150CONDITIONAL3 Feb 2012

A 457m2 extension to the Aluclad building. The building extension will be used to provide additional floor space for the production of Aluclad windows and doors. The proposed works will also necessitate the deconstruction of 2 no. wood drying kilns to clear the area for the proposed extension.

Lacka Cross Lackanastooka Ballydesmond Co. Cork

63m
11/6702INCOMPLETED APPLICATION23 Dec 2011

Construction of 457sqm extension to the Aluclad building. The building extension will be used to provide additional floor space for the production of Aluclad windows & doors. The proposed works will also necessitate the deconstruction of 2no. wood drying kilns to clear the area for the proposed extension

Lacka Cross Lackanastooka Ballydesmond

63m
12/4096INCOMPLETED APPLICATION26 Jan 2012

Construction of a 457m2 extension to the Aluclad building. The building extension will be used to provide additional floor space for the production of Aluclad windows and doors

Lacka Cross Lackanastooka Ballydesmond Co. Cork

65m
07/5189CONDITIONAL19 Feb 2007

Construction of extension to softwood processing building for increased production and provision of office space

Munster Joinery Lacka Cross Lackanastooka Ballydesmond

65m
18/6914CONDITIONAL2 Nov 2018

Construction of an extension to an existing canteen adjacent to the Softwood Building at the facility. The total floor area of the works is 135sq.m over two floors. A Natura Impact Statement will be submitted to the Planning Authority with this application.

Lacka Cross Lackanastooka Ballydesmond Co. Cork

69m
24/4237INCOMPLETED APPLICATION14 Feb 2024

Permission for the installation of 1 no. full retention separator, complete with ancillary works at the Gairdini facility. A Natura Impact Statement (NIS) will be submitted to the planning authority with this application.

Lackanastooka Ballydesmond Co Cork

69m
24/4591CONDITIONAL8 Apr 2024

Permission for the installation of 1 no. full retention separator, complete with ancillary works at the Gairdini Facility. This application relates to a development which comprises or is for the purposes of an activity requiring an integrated pollution control licence issued by the Environmental Protection Agency (EPA). A Natura Impact Statement will be submitted to the planning authority with this application.

Lackanastooka Ballydesmond Co.Cork