Site No.24 Euro Business Park Courtstown Little Island
CONDITIONALPlanning application 07/8343
Cork - Cork County Council
Proposed Development
Retention and completion of ESB substation and 2 no. switchrooms
View the full application file on the council's planning portal →Application Timeline
Application received
1 Jun 2007
Decision: CONDITIONAL
23 Jul 2007
Decision due
26 Jul 2007
Grant issued
23 Aug 2007
Application Details
- Location
- Site No.24 Euro Business Park Courtstown Little Island
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 1 June 2007
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 23 July 2007
- Grant Date
- 23 August 2007
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Retention and completion of warehouse building to include alterations to elevations comprising of new canopies to front and rear, relocation of entrance and alterations to road layout and drainage layout
Site No.24 Euro Business Park Courtstown Little Island
Alterations to elevtions, erection of canopies to front and rear of building, relocation of entrance and alterations to road and drainage layouts
Site No.24 Eurobusiness Park Courtstown Little Island
Construction of ESB sub-station and 2 no. switchrooms
Site 24 Eurobusiness Park Courtstown Little Island
Warehouse building containing self storage units and offices, signage, entrance, access road, car parking and all associated site works
Site 24 (a) Euro Business Park Courtstown Little Island
Construction of ESB substation and swithchrooms
Site 24 Eurobusiness Pk Courtstown Little Island
Construction of ESB substation and switchrooms
Site No.24 Eurobusiness Park Courtstown Little Island
15 no. light industrial units in 3 no. blocks, ancillary landscaping, signage, provision of 40 no. car parking spaces and site development works
Site No 24A Euro Business Park Courtstown,Little Island
Retention of the change of use from warehouse and distribution centre to training centre and offices, and internal alterations including construction of additional 78 sq.m mezzanine level, including kitchen, lift and staircase
Unit 25A Euro Business Park Courtstown Little Island Co Cork
Permission for retention of first floor internal office space at Unit 2.
Unit 2, Hillview Campus Euro business Park, Courtstown Little Island Co.Cork
Construction of a trade warehouse and distribution unit and associated works
Site No. 25 Euro Business Park Courtstown Little Island
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?