← Back to search

Dunowen Ardfield Clonakilty

CONDITIONAL

Planning application 08/1620

Cork - Cork County Council

Proposed Development

  1. (a)
    Retain roof light
  2. (b)
    Retain and complete extension, all to existing dwelling
View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    5 Sept 2008

  2. Decision due

    3 Dec 2008

  3. Decision: CONDITIONAL

    3 Dec 2008

  4. Grant issued

    19 Jan 2009

Application Details

Location
Dunowen Ardfield Clonakilty
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
5 September 2008Other applications received that week
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
3 December 2008
Grant Date
19 January 2009

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

49m
03/2511REFUSED27 May 2003

Construction of ground floor and first floor extensions to dwelling

DUNOWEN, DUNOWEN,

125m
99/2110CONDITIONAL27 Apr 1999

Demolition of ruined dwelling & construction of dwellinghouse & sewage treatment plant

DUNOWEN, DUNOWEN,

196m
05/2844CONDITIONAL29 Apr 2005

Extension to dwellinghouse

Ballyva Ardfield Clonakilty

198m
04/7469REFUSED4 Oct 2004

Construction of dwelling, installation of common proprietary treatment unit to serve existing temporary dwelling (mobile home), existing dwelling and proposed dwelling

Ballyva Ardfield Clonakilty

220m
20/102INCOMPLETED APPLICATION26 Feb 2020

Alterations and extension to existing dwelling house including demolition of existing glazed link, construction of single storey glazed link with flat roof, single storey extension with pitched roof and replacement of all windows

Redstrand Dunowen Ardfield Co. Cork

220m
20/194CONDITIONAL6 Apr 2020

Alterations and extension to existing dwelling house including demolition of existing glazed link, construction of single storey glazed link with flat roof, single storey extension with pitched roof and replacement of all windows.

Redstrand Dunowen Ardfield Co. Cork

220m
20/81INCOMPLETED APPLICATION19 Feb 2020

Alterations and extension to existing dwelling house including demolition of existing glazed link, construction of single storey glazed link with flat roof, single storey extension with pitched roof and replacement of all windows

Redstrand Dunowen Ardfield Co. Cork

222m
18/346INCOMPLETED APPLICATION18 Jun 2018

Permission for retention of extension to existing dwelling house

Dunowen Ardfield Clonakilty Co. Cork

222m
07/2658Conditional16 Oct 2007

Demolish existing fire place and chimney in sitting room, re-build new fire place and chimney to gable wall and construct new opening with double doors and windows from either side to access garden where fire place and chimney are removed, remove existing 2no. double doors from either side of existing chimney; Extension to side of dwelling, ground floor will consist of link through lobby to connect extension to dwelling and accommodation in extension will consist of 2no. bedrooms and 2no. en-suites on ground floor and first floor, will consist of access lobby, accessed from existing first floor, containing master bedroom, ensuite and walk in wardrobe

Red Strand Dunowen Ardfield

222m
07/1355INCOMPLETED APPLICATION23 May 2007

Demolish existing fire place and chimney in sitting room, re-build new fire place and chimney to gable wall and construct new opening with double doors from either side to access garden where fire place and chimney are removed, remove existing 2no. double doors from either side of existing chimney; Two storey extension with link through lobby on ground floor to connect to existing dwelling

Red Strand Dunowen Ardfield