Proposed Development
Erection of wind farm comprising 5 wind turbines with towers up to 46m in height and rotor diameter up to 62m and ancillary equipment for generation of electricity with control building and substation and 40m wind monitoring mast
View the full application file on the council's planning portal →Application Timeline
Application received
1 Dec 2008
Decision due
3 Feb 2009
Decision: CONDITIONAL
3 Feb 2009
Grant issued
12 Mar 2009
Application Details
- Location
- Goulacullin Dunmanway
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 1 December 2008
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 3 February 2009
- Grant Date
- 12 March 2009
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Erection of wind farm comprising of 5 wind turbines with towers up to 46m in height and rotor diameters up to 62m and ancillary equipment for the generation of electricity with control building and substation and 40m wind monitoring mast
Goulacullin Dunmanway Co. Cork
Erection of wind farm comprising of 5 wind turbines with towers up to 46m in height and rotor diameters up to 62m and ancillary equipment for generation of electricity with control building and substation and 40m wind monitoring mast. An extension of time was subsequently granted on planning application reference 08/2119 under planning reference 14/00143
Goulacullin Dunmanway Co. Cork
Wind farm to include 5 wind turbines, ancillary equipment for generation of electricity, control buildings, substation and 40m wind monitoring mast
Goulacullin Dunmanway
Erection of a windfarm comprising of 12 no. wind turbines & ancillary equipment for generation of electricity & control building
GOULACULLIN, GOULACULLIN,
Erection of wind farm comprising 5 wind turbines with towers up to 46m in height and rotor diameter up to 62m and ancillary equipment for generation of electricity with control building and substation and 40m wind monitoring mast
Goulacullin Dunmanway
Windfarm to include 5 no. turbines, ancillary equipment for generation of electricity, control buildings, substation & 40m wind monitoring mast
GOULACULLIN, GOULACULLIN,
Dwellinghouse
BARNAGOWLANE EAST, BARNAGOWLANE EAST,
Windfarm to include 7 no. turbines, meteorological mast, control building,notice board, access tracks, upgrading of laneway & ancillary works
COOMLEAGH EAST, COOMLEAGH EAST,
Construction of a dwelling house attached to an existing dwelling to the north and west elevation of the existing dwelling house
Goulacullin Bantry Co. Cork
Construction of farm building for storage of farm machinery and associated site works
Goulacullin Dunmanway
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?