← Back to search

Lacka Cross Lackanastooka Ballydesmond

CONDITIONAL

Planning application 09/4620

Cork - Cork County Council

Proposed Development

Retention of a reinforced concrete retaining wall used to retain the ground of a high level access road which is paralell to the public road

View the full application file on the council's planning portal →

Application Timeline

  1. Application received

    2 Mar 2009

  2. Decision due

    28 Jul 2009

  3. Decision: CONDITIONAL

    28 Jul 2009

Application Details

Location
Lacka Cross Lackanastooka Ballydesmond
Applicant
N/A
Application Type
PERMISSION
Planning Authority
Cork County Council

Timeline

Registration Date
2 March 2009
Status
APPLICATION FINALISED
Decision
CONDITIONAL
Decision Date
28 July 2009

Location

Loading map...

Planning Applications Nearby

What the council has granted and refused around this site is the best guide to how a similar application will fare.

16m
18/6914CONDITIONAL2 Nov 2018

Construction of an extension to an existing canteen adjacent to the Softwood Building at the facility. The total floor area of the works is 135sq.m over two floors. A Natura Impact Statement will be submitted to the Planning Authority with this application.

Lacka Cross Lackanastooka Ballydesmond Co. Cork

70m
24/4237INCOMPLETED APPLICATION14 Feb 2024

Permission for the installation of 1 no. full retention separator, complete with ancillary works at the Gairdini facility. A Natura Impact Statement (NIS) will be submitted to the planning authority with this application.

Lackanastooka Ballydesmond Co Cork

70m
24/4591CONDITIONAL8 Apr 2024

Permission for the installation of 1 no. full retention separator, complete with ancillary works at the Gairdini Facility. This application relates to a development which comprises or is for the purposes of an activity requiring an integrated pollution control licence issued by the Environmental Protection Agency (EPA). A Natura Impact Statement will be submitted to the planning authority with this application.

Lackanastooka Ballydesmond Co.Cork

77m
07/7041CONDITIONAL16 Apr 2007

Retention of 2 no. extensions to softwood processing building and extension to main joinery building for the purpose of increasing production

Munster Joinery Lacka Cross Lackanastooka Ballydesmond

87m
07/5953INCOMPLETED APPLICATION13 Mar 2007

Retention of 2 no. extensions to softwood processing building and extension to main joinery building at window and door manufacturing facility

Munster Joinery Lacka Cross Lackanastooka Ballydesmond

92m
14/6456INCOMPLETED APPLICATION18 Nov 2014

Amendments to the previously granted planning application, Ref. No. 08/10253. The works will consist of replacing 4 no. roller shutter doors with 2 no. wider roller shutter doors and relocating the two existing personal access doors on the north elevation. Providing a new personal access door on the north elevation. Relocating the existing roller shutter door and two personal access doors on the east elevation. A new access parking bay to be provided in front of the relocated roller shutter door on the east elevation. And all ancillary site works

Lacka Cross Lackanastooka Ballydesmond

98m
06/7844CONDITIONAL7 Jun 2006

1 no. temporary 60m high meterological mast

Munster Joinery Lacka Cross Lackanastooka Ballydesmond

98m
06/6937INCOMPLETED APPLICATION5 May 2006

Temporary 60m high meterological mast for the collection of wind information

Munster Joinery Lacka Cross Lackanastooka Ballydesmond

103m
04/2701CONDITIONAL22 Apr 2004

Construction of building for the manufacturing of steel stairs and doors

Munster Joinery Lacka Cross Lackanastooka Ballydemond

115m
08/9148INCOMPLETED APPLICATION3 Oct 2008

Construction of 285 sqm new timber storage building, for storing timber for further processing

Lacka Cross Lackanastooka Ballydesmond

Planning a project of your own?

Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.

Do I Need Permission?